List Your Equipment For Free  /  Seller Login

$100M Chicago Bridge Flyover Project Enhances Downtown

Wed February 16, 2022 - Midwest Edition #4
Chuck MacDonald – CEG CORRESPONDENT


The spine and ribs of the Flyover Bridge are held in position and ready to be secured. For this operation, the Granite team used a Grove GMK7550 all-terrain crane.
The spine and ribs of the Flyover Bridge are held in position and ready to be secured. For this operation, the Granite team used a Grove GMK7550 all-terrain crane.
The spine and ribs of the Flyover Bridge are held in position and ready to be secured. For this operation, the Granite team used a Grove GMK7550 all-terrain crane.
 Concrete is pumped onto the Flyover Bridge deck. The Flyover Bridge seamlessly connects an 18-mi. trail in downtown Chicago.
 The Lake Shore Drive Bridge over the Chicago River is under construction. This view looks west at the east sidewalk and the two bridge houses being finished.
 The bridge had three bays like this on each level. The Granite team removed the deteriorated steel and replaced it. The bridge was built in 1937.

Poking a half mile into Lake Michigan, Navy Pier is one of Chicago's most popular destinations for both visitors and locals. Throughout its history, Navy Pier served as a Navy training center during World War II; welcomed a university and its students; and was a shipping terminal and a tourist hotspot. The site celebrated its 100th birthday in 2016 as a redesigned multi-use location for business, visitors and for its unparalleled views of the Chicago skyline and waterfront. Officials estimate that some nine million people visit Navy Pier annually.

The Navy Pier Flyover project is nearing completion and will enhance the area, making it safer and more accessible for walkers, joggers and bikers. The three-phase project will cost approximately $100 million and was possible only because construction teams embraced unique challenges. Phase one of the project was completed by F.H. Paschen with the second two phases done by Granite Construction's Midwest Civil Division.

"The Lakefront Trail is undoubtedly one of Chicago's crown jewels — a reputation that has only been amplified due to the completion of the Navy Pier Flyover project, which seamlessly connects our north and south sides," said Chicago Mayor Lori E. Lightfoot at the official opening of the Flyover in May 2021. "This incredible project also improves public safety and provides stunning views of our lakefront and Navy Pier for pedestrians, joggers and bikers alike."

A signature element of the Flyover is a steel spine, created by rolling flat steel plates that were rolled into 10-ft. can sections. The can sections were then welded together into longer spine sections. Using heat induction, the spine sections were bent to achieve vertical and horizontal curves. The sections were then assembled onsite and welded together by Granite ironworkers. Ribs were bolted onto the spine, then normal timber falsework was used so that the concrete deck could be poured.

The shape and curve of the spine bifurcation section required complicated rigging and rerigging by multiple cranes to get the unique structure positioned. Finally, traditional bridge-building activities could begin. The Flyover Ramp steers a portion of the pedestrian and recreational traffic onto Navy Pier and other traffic onto the North Lakeshore Drive section of the 18-mi. trail.

"Placing the spine over the water at the Ogden slip was challenging," said Ryan Clark, Granite's regional vice president. "The unusual shape of the spine with its compound curves required us to use a 550-ton crane. Our team had to use multiple lifts then employ temporary hold points to readjust the rigging."

A mistake hoisting this one-of-a kind section into place would have jeopardized the months and thousands of labor hours that went into fabricating the bifurcation spine section. Due to careful planning, complicated engineering and attention to detail, the Granite construction team successfully completed the lifts as planned. The lifts were completed at night to minimize impact on the multiple waterway commercial vendors that operate out of Ogden slip.

"This was a unique project and one we will remember for a long time," said Clark. "We were not the only ones who noticed. People walking the trail complimented us even before it was complete."

Retooling an Iconic Bridge

At the conclusion of phase 2 of the Flyover project, the trail had been connected in a safe and atheistically pleasing way. However, phase 3 brought an equally difficult test: remaking an iconic Lake Shore Drive bridge originally constructed in 1937. The double-decker bascule drawbridge over the Chicago River presented safety hazards for bikers and walkers using the trail. The 16-ft.-wide trail pinched down to just 6-ft. wide in some places over the bridge causing congestion and a somewhat dangerous path.

Design for the bridge rehabilitation was done by HNTB.

"Sometimes we like to find work that is technically challenging," said Clark of his team of engineers and workers at Granite.

To widen the bicycle path over the bridge, a significant amount of deteriorated steel had to be replaced. The bridge is composed of expanded metal grating supported by steel floor beams spanning between the main bridge trusses. Six lanes of traffic flowed over Upper Lake Shore Drive on the top level and six lanes traveled across the intermediate level of Lower Lake Shore Drive.

The bridge had to remain fully operational throughout construction, not just for the traffic and the trail, but also for the boats on the Chicago River below.

Complex Project

Fixing the bridge tested the ingenuity of Granite engineers and workers.

"Bascule bridges are complex," said Clark. "We had to take apart much of the bridge's mechanisms, then put them together again. Of course, replacement bridge parts from that era are no longer available."

The nature of bascule bridges requires each movable leaf section be well balanced between the "heel" and "toe," so the machinery can lift each leaf. While Granite workers worked on the renovations, they had to make sure not to disturb this delicate balance.

"We had to custom refurbish the center lock drive equipment and the center lock jaw mechanism assemblies," said Clark. "We also refurbished the eight motors that raises and lowers the bridge. We installed 325 tons of new steel on the bridge and retooled the counterweight shoring capacity that weighed 600 tons."

In addition to the steel repairs and the mechanical upgrades, the Granite team crafted architectural restoration on the nearly 100-year-old limestone bridge houses.

"Chicago lakefront parks and trails are among the city's most popular destinations," said Michael Kelly, Chicago Park District general superintendent. "The completion of the Navy Pier Flyover and Lakefront Trail Separation will dramatically minimize congestions, making the experience more enjoyable and safer for everyone."

The final piece of the project is scheduled for completion in spring 2022.

"This project, especially the bridge, is a testament to our people being willing to tackle complex projects," said Clark. "We have a team of young, enthusiastic people from the Chicago area who are willing to put their engineering skills to the test. They are completing a complicated project that will benefit the entire community." CEG


Chuck MacDonald

Chuck MacDonald is an editor, blogger and freelance feature writer whose writing adventures have taken him to 48 states and 10 countries. He has been the editor for magazines on pavement construction, chemicals, insurance and missions. Chuck enjoys bicycling, kayaking and reading. He graduated from the University of Missouri with a degree in journalism. Chuck lives in Annapolis, Md. with his wife Kristen. They have seven grandchildren.


Read more from Chuck MacDonald here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA