List Your Equipment For Free  /  Seller Login

$1.4B TxDOT Project Aims to Ease Traffic on I-35 Near Dallas

A major reconstruction project will make a difference for travelers through Denton and Dallas counties in Texas when it is finished.

Fri April 01, 2016 - West Edition
Brenda Ruggiero


AGL Constructors photo.
Beams for the new southbound bridge over Lewisville Lake.
AGL Constructors photo. Beams for the new southbound bridge over Lewisville Lake.
AGL Constructors photo.
Beams for the new southbound bridge over Lewisville Lake.
 AGL Constructors photo.
Preparing the 600-ton (544.3 t) crane to place beams over the DART rail line. AGL Constructors photo.
Belt Line — I-35E at Belt Line looking north.
 AGL Constructors photo.
Beams for the new southbound bridge over Lewisville Lake.
 AGL Constructors photo.
Setting beams for the new southbound bridge over Lewisville Lake.
 AGL Constructors photo.
Setting forms at the Belt Line bridge.

A major reconstruction project will make a difference for travelers through Denton and Dallas counties in Texas when it is finished.

The approximately 30-mi. (48.28 km) project travels through two counties and nine cities, and Phase I will cost $1.4 billion. Construction on this phase started in October 2013, and is currently on schedule to be substantially complete by mid-2017. Funding comes from federal, state and local sources. The construction is being led by AGL Constructors, a joint venture including Archer Western, Granite Construction Incorporated and Lane Construction Company.

The 35Express Project reconstructs I-35E between U.S. Highway 380 in Denton County and I-635 in Dallas County. The contract calls for the reconstruction or rehabilitation of more than 75 bridges, adds an 18-mi. (29 km) reversible managed lane system, an additional lane of traffic in each direction between the Sam Rayburn Tollway and U.S. Highway 380, continuous frontage road, and a new southbound bridge across Lewisville Lake.

According to the project Web site, Interstate 35E (I-35E) serves the rapidly growing areas of southern and central Denton County, as well as the major Dallas suburbs immediately north of I-635.This corridor is a major artery for hundreds of thousands of commuters, as well as a primary link to major universities in the city of Denton, including the fourth-largest university in the state, the University of North Texas (UNT).

In addition, I-35E is an important truck corridor and accommodates more than 12,000 trucks daily. The interstate also handles almost 200,000 total vehicles daily near I-635, and 128,000 vehicles a day across Lewisville Lake. In addition, because of a lack of continuous frontage roads across Lewisville Lake, there are no viable north-south commuting alternatives to I-35E at this crossing.

This section of the I-35 corridor is on the list of Texas' 100 most congested roadways. Expanding I-35E will reduce congestion that results in lost work time, increased fuel costs and higher price of goods. The project will improve mobility across Lewisville Lake with construction of a second bridge that will offer more reliability for commuters during major incidents.

The $4.8 billion project will be constructed in phases, and will rebuild the entire 30-mi. corridor. Approximately $1.4 billion in funding has been identified for Phase 1 of this project, which includes SH 121 regional toll revenue (RTR) funds dedicated to Denton County. Phase 2 of the project will occur when the additional funding becomes available.

“The length and amount of coordination needed for this project makes it unique,” said Kimberly Sims, public information manager. “AGL coordinated with various entities on ROW acquisition, utilities, design, traffic control, and aesthetics. In addition, we are demolishing four bridges and converting them into at-grade roadways with increased capacity. Belt Line Road is one of the more complicated pieces of the project — AGL is essentially building two bridges at once. The mainlane bridge is being raised 25 feet above its current elevation and Belt Line Road is being raised to the elevation of the existing mainlane bridge. Improving mobility is one of the reasons for elevating this interchange. The newly elevated interchange will allow motorists to travel over the railroad track near the intersection.”

According to Sims, the project will include a total of 2.04 million man hours worked; 9,920 traffic barrels placed; and 8,267 cu. yds. (6,320.5 cu m) of concrete recycled. More than 190,113 tons (172,468 t) of asphalt have been used for paving, and more than 113,113 tons (102,614 t) of asphalt has been recycled. Over 62 mi. (99.77 km) of protective concrete barrier has been placed, 66 mi. (106.2 km) of utilities have been relocated and 17 mi. (27.4 km) of drainage has been installed.

The south segment (I-635 to PGBT) covers 7.5 mi. (12 km), the middle segment (PGBT to FM 2181) covers 12.1 mi. (19.5 km), and the north segment (FM 2181 to U.S. 380) covers 10.5 mi. (17 km). There will be an additional general purpose lane in each direction, N of SH 121 to U.S. 380; two reversible managed toll lanes from I-635 to Turbeville/Hundley; a new southbound bridge over Lewisville Lake; Belt Line Road intersection reconstruction; intersection improvements at Dickerson, FM407, Garden Ridge, S. Denton/Oak, Turbeville/Hundley, Corinth, Post Oak, and North Texas Blvd.

I-35E was originally constructed in the 1950s and 60s. In 1998, TxDOT began a comprehensive review and planning study of the I-35E corridor in Dallas and Denton counties. For the next 13 years, TxDOT and communities and stakeholders refined the designs and upgrades for this corridor. In 2011 and 2012, TxDOT received environmental clearance for the $4.8 billion infrastructure project. Also, $1 billion in funding was identified for an initial phase of the project with most coming from SH 121 regional toll revenue funds dedicated to Denton County. In accordance with state law, TxDOT and corridor stakeholders held seven public meetings to determine the method and scope of the initial phase (Phase 1) as well as lay the ground work for Phase 2 to complete the remaining elements of the corridor.

Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA