Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
Thu December 31, 2020 - Northeast Edition #1
The Virginia Department of Transportation (VDOT) is heading up a bridge replacement in a sensitive and highly trafficked area of Newport News, Va.
The contract was awarded to i+iconSOUTHEAST.
Construction on the $17.8 million project began in spring 2020 and is expected to be complete by fall of 2022.
"This project consists of the reconstruction of this 0.56-mile segment of VA Route 105 and two access ramps to U.S. Route 60 including the full removal and replacement of the Fort Eustis Bridge with a wider cross section," said Katie Spear, vice president of marketing of i+iconSOUTHEAST.
The new bridge will be 690 ft. long and 87.67 ft. wide, according to Spear, and the existing 16-span, pre-stressed concrete girder bridge on concrete pile bents will be replaced with a 676-ft. bridge with nine pre-stressed concrete bulb-T spans on concrete pile bents to meet current standards.
She said the Fort Eustis Bridge, built in 1960, is a part of a heavily trafficked road that leads directly onto the Fort Eustis Army Base and is one of only two access roads on and off the base.
"For years, the bridge has experienced deterioration under the bridge as well as on top that is leading the joint effort between VDOT, EFL (Eastern Federal Lands) and the city of Newport News to address the concerns," she said. "The bridge crosses Newport News's city reservoir and is a highly sensitive area, as such the new bridge will also help redirect pollution from entering the city reservoir."
The work includes raising the grade of the bridge surface and roadway, replacing precast concrete piles, utility relocation, and other miscellaneous work. The deck will be supported by prestressed concrete beams.
The construction of the new bridge will be done in stages so that the existing bridge can remain open during the replacement. The bridge can be accessed by U.S. Route 60 (Warwick Blvd) on the west, and by I-64 on the east.
As of mid-December, the i+iconSOUTHEAST team had established and cleared approximately two acres to accommodate the laydown area and access to the water.
"Barges have been assembled and set in the water," Spear said. "The elevated work platform (trestle) is nearing completion, which will allow the Manitowoc 4100 crane to walk from land onto the barges that are currently in the water. The crane is being used to float and drive piles at the bents; a Pileco D46 diesel hammer is driving the piles; and a Conmaco MDL 24 pile cutter is being used to cut the existing 24-inch piles at the bents."
i+iconSOUTHEAST employees have already demoed 10 spans and abutment B on the eastern side.
"The biggest challenge to date is the sensitive work area and highly trafficked area close to the base," Spear said. "The city reservoir is held back by a dam, which requires a special cofferdam for the construction of abutment A. This cofferdam will be left in place and cut off at the mudline once construction of Abutment A is complete."
Spear reported that the dam is a sensitive area with multiple stakeholders.
"Coordination between all parties has been challenging to get approvals to install the cofferdam and construct abutment A," she said. CEG
Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.
Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.
Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.