Allan Myers Leads MD 97 Relocation Construction Project

Thu January 28, 2021 - Northeast Edition #3
Brenda Ruggiero – CEG Correspondent


This project is part of Maryland Gov. Larry Hogan’s $1.97 billion investment in roads and bridges that was announced in 2015.
This project is part of Maryland Gov. Larry Hogan’s $1.97 billion investment in roads and bridges that was announced in 2015.
This project is part of Maryland Gov. Larry Hogan’s $1.97 billion investment in roads and bridges that was announced in 2015. Crews began pile driving at S2 Abutment A this past November. Crews backfill with GAB for WSSC sewer line work south of Meadow Branch. Workers pre-drill pile at Abutment A in December 2020. S1 Form Abutment B form liner installation took place in August 2020. The contract was awarded to Allan Myers Inc. of Worcester, Pa. The project is valued at $43.4 million, with $1.1 million coming from federal aid.

The Maryland Department of Transportation's State Highway Administration (MDOT SHA) continues work on the MD 97 (Georgia Avenue) Relocation Construction Project in the town of Brookeville, which is in Montgomery County.

The project includes a new 0.7-mi., two-lane highway with bicycle-compatible shoulders between north of Goldmine Road and south of Holiday Drive.

The contract was awarded to Allan Myers Inc. of Worcester, Pa. The project is valued at $43.4 million, with $1.1 million coming from federal aid.

Construction began in the fall of 2018. As of Jan. 22, the project was 41 percent complete, with an end goal of late summer 2021. Javier Arias serves as the MDOT SHA project engineer.

"With this project, the Maryland Department of Transportation State Highway Administration is building a new two-lane highway with bicycle compatible shoulders that will make MD 97 more accessible to residents, bicyclists and pedestrians," said Shanteé Felix, assistant media relations manager of the office of communications.

"The project also includes construction of two bridges — one at Meadow Branch stream and the other at Reddy Branch stream — and two single-lane roundabouts that will improve traffic and safety operations."

Felix reported that MD 97 is a major north-south commuter route between Brookeville and northern Montgomery and Frederick counties.

"Currently, motorists and residents experience congestion when navigating the two-lane roadway that travels through the historic town of Brookeville," she said. "This new highway will preserve the town of Brookeville's historic nature while also enhancing safety and reducing travel times for commuters."

According to Felix, January work for crews included roadway fill for the High Street roundabout; drainage structure and pipe installation; Brookeville Road's Pepco cable wire installation; and concrete pours for bridge abutments. Over the next month, they will be working on wetland mitigation.

MD 97 has a 90-degree curve at Market Street, which is accompanied by a steep hill. The increasing volume of peak-hour traffic combined with the roadway's geometrics contribute to the need to improve the overall operational characteristics of Georgia Avenue through the community.

Nearly 11,400 drivers travel this section of Georgia Avenue every day. By 2040, nearly 14,800 drivers are projected to use the new MD 97 Relocated in Brookeville.

This project is part of Maryland Gov. Larry Hogan's $1.97 billion investment in roads and bridges that was announced in 2015.

"In Montgomery County and all across the state, we are moving forward on nearly all of the highest priority transportation infrastructure projects in every single jurisdiction from one corner of the state to the other," said Hogan at the project groundbreaking. "The new highway will enhance safety, reduce travel times and preserve the historic nature of the beautiful town of Brookeville while ensuring that commuters have access to businesses, churches, and recreation."

Felix spoke about the challenges with the project, which included dealing with issues relating to the location of the proposed roadway and bridges.

"The proposed roadway is adjacent to environmentally sensitive areas and sensitive archeological areas," she said. "The proposed roadway required utility relocations for Pepco, Comcast and Verizon at three locations within the new alignment."

In addition, she noted that one of the proposed bridges is adjacent to a historic Washington Suburban Sanitary Commission (WSSC) pre-stressed concrete cylinder pipe sewer force main, which was built in 1968. The design/construction team for the bridge needed to account for the protection of the WSSC facility.

Felix reported that crews had to coordinate rock excavation (blasting for rock removal); a Construction Protection Plan for four properties adjacent to the project limits; underground stormwater retention facilities; wetland mitigation at Reddy Branch; and stream restoration at Meadow Branch and softball field construction following Maryland National Capital Park and Planning Commission standards/details.

To date, Felix reported 113,633.74 cu. yds. of earth movement and 2,306 cu. yds. of concrete delivered to the site.

Major subcontractors include Midlantic Piling Inc., which installed pile for S-2 bridge abutment A and will install permanent pile sheeting for S-2 bridge abutment B; Mohawk Bridge and Iron Inc., for rebar work for bridges S-1 and S-2; Shelly Drilling Co., for pre-drilling for piles at S-1 bridge; Sunrise Safety Services Inc., for traffic control; Erosion Control & Landscape Service Inc., for erosion and sediment control; and Maine Drilling and Blasting, which performed the blasting for rock excavation.

Major equipment used on the job includes a Grove RT 735 crane owned by the contractor, a rented APE D19-52 pile driving hammer, a LS-218H crane owned by the contractor, a Texoma drill rig owned by the contractor and a Schwing 39 meter concrete pump owned by the contractor. CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA