List Your Equipment For Free  /  Seller Login

Bertha Bashes Past Half-Way Tunnel Point

The tunnel will replace the Alaska Way Viaduct, an elevated double-deck road that is part of state Route 99 and an important corridor through Seattle.

Thu October 20, 2016 - West Edition
Lori Tobias


WSDOT photo.
Looking south at the SR 99 tunnel from the back end of the SR 99 tunneling machine on May 12, 2016. From this viewpoint, you can see that the tunnel takes a slight westward turn as it heads under downtown Seattle near Yesler Way.
WSDOT photo. Looking south at the SR 99 tunnel from the back end of the SR 99 tunneling machine on May 12, 2016. From this viewpoint, you can see that the tunnel takes a slight westward turn as it heads under downtown Seattle near Yesler Way.
WSDOT photo.
Looking south at the SR 99 tunnel from the back end of the SR 99 tunneling machine on May 12, 2016. From this viewpoint, you can see that the tunnel takes a slight westward turn as it heads under downtown Seattle near Yesler Way. 
 WSDOT photo.

A specially designed truck carries the next 10 tunnel liner segments – one ring’s worth – into the SR 99 tunnel. That’s a 360,000-lb. (176,901 kg) load. WSDOT photo.
Load master Thomas Nixon watches closely as excavated tunnel material, known as muck, traverses the final feet of a conveyor system that reaches all the way to Bertha’s front end.
 WSDOT photo.

In late December 2012, representatives of WSDOT and Seattle Tunnel Partners were on hand in Japan to officially accept the machine from its manufacturers, Hitachi Zosen.  WSDOT photo.
This August 2016 photo shows completed sections of the SR 99 tunnel’s top, southbound roadway deck. Crews are building the double-decked roadway behind Bertha, the SR tunneling machine. 
 WSDOT photo.
Crews working for Seattle Tunnel Partners build the rebar cage for a section of the west wall of the future roadway in the SR 99 tunnel in Seattle.
 WSDOT photo.
In this June 2016 photo, crews working for Seattle Tunnel Partners clean the surface of the SR 99 tunnel in Seattle as they prepare to pour the concrete that will flatten the bottom slope of the tunnel. Engineers call this the invert slab, and it provides a better foundation for vehicles and for construction of the roadway inside the tunnel.

Three years after the tunneling machine dubbed "Bertha" began work on a 2-mi. (3.2 km) tunnel beneath the city of Seattle, the machine has passed the half-way point. Bertha pushed past the Pike Place Market on Sept. 30, successfully excavating more than 4,635 ft. (1,413 m) of the 9,270-ft. (2,825 m) tunnel, said Washington Department of Transportation spokeswoman Laura Newborn.

The tunnel will replace the Alaska Way Viaduct, an elevated double-deck road that is part of state Route 99 and an important corridor through Seattle. Built in the 1950s, the viaduct sustained damage in a 2001 earthquake. In 2009, the Washington State Legislature agreed to replace the viaduct with the tunnel. In 2011, the southern mile of the viaduct was demolished and replaced with new roadway.

WSDOT awarded Seattle Tunnel Partners a $1.35 billion contract to design and build the tunnel, which includes a double-deck highway inside the tunnel, tunnel entrances and exits and two tunnel operations buildings. The price tag for the entire Alaskan Way Viaduct project is $3.1 billion.

Much of the progress has been made in the past five months with the machine tunneling more than 3,000 ft. (914 m) since a planned maintenance stop in April, according to a press release from WSDOT.

"Bertha has been steadily on the move and made her way to the second half of the tunnel," said Washington Gov. Jay Inslee. "This is good progress and I appreciate everyone's focus on making sure we safely complete this project."

The tunneling has not always gone so smoothly. In December 2013, work on the tunnel came to halt after high temperatures were registered on the tunneling machine. A little over 1,000 ft. (304 m) had been excavated at the time. It was determined there was damage to the seal system on the machine. The manufacturer, Hitachi Zosen chose to repair the machine from the surface, requiring construction of an 80-ft. (24 m) wide, 120-ft. (36.5 m)-deep access pit in a work zone west of the Alaskan Way Viaduct. Between March and August 2015, Hitachi Zosen installed a re-designed seal system and made additional repairs to the machine, then lowered the front end back into the ground. In December 2015, STP refilled the access pit and again began tunneling.

Bertha is now about 190 ft. (58 m) below First Avenue between Pike and Pine Streets, according to WSDOT. Crews will continue mining for a short time and then stop for about a month to perform planned maintenance.

"While STP's crews are making progress, they are also taking time for routine maintenance to help ensure the machine successfully completes the tunnel drive," WSDOT said. "Like previous maintenance stops, crews will use the upcoming stop to inspect machine components and replace cutterhead tools in hyperbaric conditions. STP expects this round of maintenance to last approximately one month, but it could take more or less time depending on the extent of work needed."

The two-year delay has prompted WSDOT to request an additional $60 million from the state legislature for the 2017-2019 budget cycle to continue progress on the project. The team has completed 21 of 31 projects in the viaduct replacement plan that will reshape SR 99. Five additional projects are under way and five more are in the planning stages.

The "finish line" is a 90-ft. (27 m)-deep receiving pit at the north end of downtown Seattle and, along with many other aspects of tunnel portals, is largely complete, WSDOT said. Future contractors will make the final connections to the highway, but several of the ramps and roadways into and out of the tunnel are already in place.

"This program turned a corner earlier this year," said Secretary of Transportation Roger Millar. "We're now closer to the end of the tunnel than we are to the beginning, and everyone on the team is working toward the day when the machine comes out on the other side."

The most recent schedule calls for tunneling to wrap up in the summer of 2017.

"Work to complete the tunnel's interior structures, along with installing and testing systems should be finished by late 2018. Based on STP's schedule, WSDOT estimates the tunnel would open to traffic in early 2019 when crews finish connecting the tunnel to the existing SR 99 roadways."

Some other facts about the project, courtesy WSDOT:

• At 57.5 ft. (17.5 m) in diameter, Bertha was the largest tunnel boring machine in the world until a slightly larger machine built part of an undersea tunnel in Hong Kong.

• The inside diameter of the tunnel is 52 ft. (15.8 m), big enough to support a double-deck roadway inside.

• The bored portion of SR 99 tunnel is 1.7 mi. (2.7 km) long. Cut and cover construction at both ends brings the tunnel length to 2 mi.


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA