Cast & Baker Make Emergency Repairs While ODOT Works to Prevent Future Slides

Tue November 09, 2021 - Midwest Edition #23
Cindy Riley – CEG Correspondent


ODOT is overseeing an emergency landslide repair and realignment project.
(Ashley Rittenhouse/ODOT photo)
ODOT is overseeing an emergency landslide repair and realignment project. (Ashley Rittenhouse/ODOT photo)
ODOT is overseeing an emergency landslide repair and realignment project.
(Ashley Rittenhouse/ODOT photo) Work on the $9.5 million landslide repair project involves the construction of a new 0.55-mi. section of SR 537.
(Ashley Rittenhouse/ODOT photo) The contractor for the project is Cast & Baker Corporation. The estimated completion date for all work is December 2022.
(Ashley Rittenhouse/ODOT photo) Equipment being used on the job includes 40-ton articulating end dump trucks; 50-ton end dump trucks; large excavators; Cat D8 and D9 dozers; and embankment compactors.
(Ashley Rittenhouse/ODOT photo) The project calls for approximately 500,00 cu. yds. of excavation and 735,000 cu. yds. of embankment.
(Ashley Rittenhouse/ODOT photo) Four culverts will be installed.
(Ashley Rittenhouse/ODOT photo) ODOT has identified more than three dozen locations in more than a dozen counties where slips and rockfalls are likely to occur in the near future.
(Ashley Rittenhouse/ODOT photo) According to an ODOT news release, officials will make use of $35 million in federal stimulus funding to complete dozens of projects designed to address landslide and rockslide issues early, or possibly prevent them.
(Ashley Rittenhouse/ODOT photo)

In Monroe County, the Ohio Department of Transportation (ODOT) is overseeing an emergency landslide repair and realignment project. Work on the $9.5 million undertaking involves the construction of a new 0.55-mi. section of SR 537, which includes retaining walls, drainage structures and the removal of a portion of existing SR 537.

"The pavement is slipping over the hillside, and a full closure of this route would result in a significant detour for drivers," said Ashley Rittenhouse, ODOT District 10 public information officer. "This landslide has been on our radar for a few years, but it worsened due to rain/flood events in 2018. There is visible slipping and cracking of the pavement."

Experienced geotechnical engineers search the state regularly, looking for potential hazards. According to Rittenhouse, landslides in the area are not unexpected.

"The hilly terrain in southeastern Ohio, coupled with moisture from heavy rains, causes the landslides that we see."

Since this is a realignment project, much of the site was essentially undisturbed ground along hilly terrain that is typical of southeastern Ohio. Initial steps that had to be taken by construction crews included the clearing of trees within the project limits and borrow/waste area.

Two retaining walls will be constructed as part of the project, involving drilled shafts and installation of concrete lagging panels. Four culverts also will be installed.

"This work involves excavating the culvert trench to grade, placing appropriate bedding material, installing the culvert and backfilling the culvert with appropriate material," Rittenhouse said. "Additionally, concrete headwalls will be installed on the inlet/outlet of each of the proposed culverts."

The removal of a portion of existing SR 537 is a key part of the assignment.

"A portion of this work will be performed during the Phase II and III closures, and the remainder will be performed after the new section of roadway has traffic rerouted onto it. It will be a fairly straightforward process of excavating the remaining pavement, removing guardrail and a few existing culverts and then re-grading the area to drain."

Rittenhouse noted that the biggest challenge on the project will be managing the Phase I culvert installation and embankment operation over the fall/winter months of 2021, such that the 180-day closure for Phase II and III work can start on time. This should take place at the beginning of April 2022.

"Currently, the contractor is working on excavating the benches and constructing embankment between roughly Stations 153+00 to 158+00. They also are working on the installation of ‘Culvert B', which crosses the proposed mainline of SR 537 near Station 155+00."

So far, there have been no unexpected issues for workers. Tasks already completed include clearing and grubbing, portions of excavation/embankment and "Culvert B" installation.

Rittenhouse said plenty of work remains.

"A significant amount of excavation/embankment has yet to be completed, in addition to culvert installation/drainage work, drilled shaft retaining walls and the proposed pavement for the proposed mainline SR 537, as well as the east/west tie-ins. Removal of portions of existing SR 537 also needs to be completed."

Weather also is a concern for crews. Excess rain and/or snow can reduce the production of embankment operations over the fall/winter months.

Equipment being used on the job includes 40-ton articulating end dump trucks; 50-ton end dump trucks; large excavators; Caterpillar D8 and D9 dozers; and embankment compactors. The machinery will be used to perform the necessary excavation and embankment to construct the new alignment.

Embankment material will be required on the project, along with various culvert material types (CMP, concrete, etc.); HP12x53 and HP14x73 steel; concrete and concrete lagging panels for the drilled shafts; asphalt for pavement; and guardrail.

The most time-consuming part of the work will involve excavation/embankment, due to the volume of material necessary to be moved.

"ODOT D10 has significant experience in both the design and construction of projects that involve a significant amount of excavation/embankment work," said Rittenhouse. "This previous experience is beneficial in understanding what is required in order to construct a safe and reliable repair.

"Additionally, the district personnel's experience and understanding of this work type allows us to make relatively quick and informed decisions if unexpected conditions are encountered."

The vast majority of excavation and benching will be performed during Phase 1. This excavated material will generally be used as embankment material for the concurrent embankment operation. The project calls for approximately 500,00 cu. yds. of excavation and 735,000 cu. yds. of embankment.

No demolition of structures is necessary. Pavement, guardrail, culvert and other removals will be performed on existing SR 537.

As for detours affecting area motorists, the road is currently reduced to one lane and traffic is being maintained with temporary signals.

"The necessary lane closures and barriers will be placed according to traffic standards to protect the traveling public from the existing landslide and new realignment work. The contractor performs daily safety talks before work and performs job site analysis to keep the crews informed and aware of safety issues."

The contractor for the project is Cast & Baker Corporation. The estimated completion date for all work is December 2022.

According to an ODOT news release, officials will make use of $35 million in federal stimulus funding to complete dozens of projects designed to address landslide and rockslide issues early, or possibly prevent them. When these unfortunate events do happen, repairs can be very costly and, in many cases, take many months to complete. With few convenient detours available, getting around closed roads can often add a lot of time and distance to travel.

"ODOT is looking to prevent both landslides and rockslides from happening to avoid significant damage to our roadways," said Gov. Mike DeWine. "The use of these funds will help to keep our roadways safe for travelers in areas prone to landslides and rockslides."

ODOT has identified more than three dozen locations in more than a dozen counties where slips and rockfalls are likely to occur in the near future. CEG




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA