List Your Equipment For Free  /  Seller Login

CDOT Replaces Obsolete Bridge in Westminster

The $11,669,000 project is sponsored by the Bridge Enterprise Program.

Fri January 08, 2016 - West Edition
Brenda Ruggiero


Last winter, the Colorado Department of Transportation (CDOT) began reconstructing a one half mile portion of Federal Boulevard (U.S. 287) from W 67th Avenue to W 70th Avenue through the City of Westminster in Adams County.
Last winter, the Colorado Department of Transportation (CDOT) began reconstructing a one half mile portion of Federal Boulevard (U.S. 287) from W 67th Avenue to W 70th Avenue through the City of Westminster in Adams County.
Last winter, the Colorado Department of Transportation (CDOT) began reconstructing a one half mile portion of Federal Boulevard (U.S. 287) from W 67th Avenue to W 70th Avenue through the City of Westminster in Adams County. The new bridge will accommodate the new RTD Eagle P-3 Commuter Rail Line underneath and will be built wider to meet phasing requirements for maintaining two lanes in each direction during construction. The project also will include extensive earthwork at the bridge approaches and new retaining walls, as well as an asphalt overlay, safety improvements, storm sewer expansions for better roadway drainage, and enhancements to the recreational path underneat The $12 million project was awarded to Hamon Infrastructure Inc., and notice to proceed was given in January 2015. The project will be completed in three phases, and is scheduled to be finished in January 2017.

Last winter, the Colorado Department of Transportation (CDOT) began reconstructing a one half mile portion of Federal Boulevard (U.S. 287) from W 67th Avenue to W 70th Avenue through the City of Westminster in Adams County. The $11,669,000 project is sponsored by the Bridge Enterprise Program. The reconstruction of the area includes the replacement of a structurally deficient and functionally obsolete bridge over the Burlington Northern Santa Fe Railroad.

The new bridge will accommodate the new RTD Eagle P-3 Commuter Rail Line underneath and will be built wider to meet phasing requirements for maintaining two lanes in each direction during construction. The project also will include extensive earthwork at the bridge approaches and new retaining walls, as well as an asphalt overlay, safety improvements, storm sewer expansions for better roadway drainage, and enhancements to the recreational path underneath the bridge.

As part of the project, CDOT also will be constructing enhancements and aesthetic improvements for the City of Westminster that tie into work occurring for the Westminster Station Transit-Oriented Development adjacent to the project. These enhancements include aesthetic fencing and pedestrian railing, sidewalk additions and improvements, a raised median with planters, and a new signal at 69th Avenue.

The $12 million project was awarded to Hamon Infrastructure Inc., and notice to proceed was given in January 2015. The project will be completed in three phases, and is scheduled to be finished in January 2017.

A shoring failure area on southbound Federal Boulevard just north of the bridge abutment delayed the original project end date.

“Completion of this project will result in a wider bridge that will allow for future expansion of the roadway,” said Emily Wilfong, CDOT communications manager. “ADA curb ramps will be added for handicap access, and new wider sidewalks on each side of Federal Boulevard will improve pedestrian safety. Raised medians will be added to separate traffic and aesthetic enhancements will include a raised median planter with the Westminster city logo and future sculptures. Further benefits include added lighting for Little Dry Creek pedestrian trail and a new signal at 69th Avenue to access the future RTD Eagle-P3 commuter rail station.”

Wilfong noted that the existing soil was required to be removed and replaced with geofoam blocks because the existing fill had a low angle shear failure, which caused a global stability issue with the added load of the widened roadway.

Some funding for the project also is provided by the City of Westminster.

Another challenge for crews has been coordination with BNSF & RTD tracks, as well as the City of Westminster's contractor (CEI), who is working on the adjacent Little Dry Creek and park improvements.

Major equipment used on the job includes dozers, trackhoes, cranes, loaders, skidsteers and forklifts.

Major subcontractors include Chavez Construction Inc., PLM Asphalt, Rocky Mountain Reinforcement Inc., Sturgeon Electric Inc. and Zenitram Traffic Service Inc.

Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA