List Your Equipment For Free  /  Seller Login

Charter Oak Bridge Project Set to Bring Congestion Relief for Connecticut's Capitol Region

Wed February 24, 2021 - Northeast Edition #5
Irwin Rapoport – CEG Correspondent


Crews work on the future Exit 29 Bridge.
Crews work on the future Exit 29 Bridge.
Crews work on the future Exit 29 Bridge. Steel erection takes place at the Exit 29 bridge. The delivery of the Connecticut Department of Transportation’s (CTDOT) I-91 Charter Oak Bridge (COB) Project, a large-scale initiative that combines two projects to reduce congestion and improve safety in the city of Hartford, and towns of East Hartford, and Wethersfield, is less than two years away. New tub girders are being installed. Crews install the last tub girder for Exit 29. Crews perform the median pour for Bridge 813. The contract, administered by CTDOT, District 1 and the Federal Highway Administration, was awarded to O&G Industries/Barletta Heavy Division, Joint Venture (OGBHD), at a cost of approximately $213 million. The anticipated completion date is May 26, 2022. Project Consultant Inspection is being done by WSP, and the infrastructure was designed by CME Associates (CME) and HW Lochner (HWL).

The delivery of the Connecticut Department of Transportation's (CTDOT) I-91 Charter Oak Bridge (COB) Project, a large-scale initiative that combines two projects to reduce congestion and improve safety in the city of Hartford, and towns of East Hartford, and Wethersfield, is less than two years away.

The contract, administered by CTDOT, District 1 and the Federal Highway Administration, was awarded to O&G Industries/Barletta Heavy Division, Joint Venture (OGBHD), at a cost of approximately $213 million. The project, which began April 1, 2019, involves multiple stages and an aggressive schedule with incentives for the contractor to not only finish on time, but ahead of schedule wherever possible.

The anticipated completion date is May 26, 2022. Project Consultant Inspection is being done by WSP, and the infrastructure was designed by CME Associates (CME) and HW Lochner (HWL).

The purpose of the project is to strategically target and alleviate recurring traffic congestion along I-91 northbound by constructing a new, two-lane exit-ramp to the COB (Route 5/15) at Exit 29 (Bridge 6947) in place of the existing, single-lane ramp configuration. It will replace — doubling the capacity and improving the geometry — the current operationally deficient ramp, well-known for creating traffic tie-ups on northbound I-91 and on the COB.

Congestion results in daily delays and safety concerns for motorists as traffic slows or stops on the highway. The project will relieve this bottleneck for roughly 80,000 drivers per-day by improving through-traffic capacity and reducing weaving maneuvers on I-91 northbound and on Route 5/15 northbound on the COB.

"This addresses safety concerns associated with congestion and operational shortcomings in Hartford and East Hartford at I-91NB Exit 29," said CTDOT Project Engineer Juan Ruiz. "Congestion, with queueing in the right lane of I-91 NB, has been observed to extend as far as approximately 1.4 miles. This is due the steep vertical grade of the existing Exit 29, with a significant volume of heavy vehicles and traffic volumes that are near capacity. In addition, the lane-drop from four, to three lanes, at Exit 27 contributes to this congestion; the northbound portion of the Charter Oak Bridge has experienced heavy weaving of vehicles entering from the I-91 Exit 29 with vehicles on Route 5/15."

Crews are relocating the future I-91 northbound Exit 29 and constructing the new ramp such that two lanes will exit I-91 northbound from the left, fly over Route 5/15 southbound, and enter the COB from the left lanes.

"The I-91 NB Exit 29 is being redesigned to be a major diverge, with two dedicated lanes for the left exit ramp to Route 5/15 NB," said Ruiz. "The new ramp will have added capacity and improved grades so that trucks can maneuver easier, and these changes will improve traffic flow and reduce recurring congestion."

Work is being done in four stages: Stage 1 — lower roadways under bridges; Stage 2 — widen portions of I-91 northbound and Route 5/15 northbound; Stage 3 — construct a new Exit 29 ramp, and Stage 4 — remove the existing Exit 29 ramp. The overall project entails:

  • Widening of northbound I-91 from Exit 27 to Exit 29 for approximately 5,700 ft. to allow for the installation of an additional travel lane. This requires the widening of the bridges over Route 15, the Airport Road on-ramp, and Airport Road, as well as the lowering of the roads below all three bridges to allow for adequate overhead clearances.
  • Construction of a new two-lane exit ramp from northbound I-91 to the COB, including: construction of one new bridge; widening the portion of the northbound COB over I-91 to accommodate four northbound travel lanes, and eventually, the removal of the existing single-lane ramp from I-91 northbound to the COB.
  • Installation of new lane markings on the new Exit 29 on-ramp and on the COB to accommodate four travel lanes (two lanes from the new on-ramp and two from Route 5/15).
  • Widening of northbound Route 15 to add an additional lane from the COB to the Silver Lane underpass in East Hartford, as well as the widening of the bridges over Main Street and Silver Lane.
  • Improvements to extend the service life of the pavement and bridges (milling, paving and subsurface concrete repairs) on I-91 north and south between the Elm Street overpass in Wethersfield and the new Exit 29 off-ramp in Hartford, drainage system upgrades, and guiderail upgrades to meet current standards

"Considering the complexity of the project and the multitude of on- and off-ramps, the nightly lane closures and work zones, installed per-plan, are working very well," said Ruiz. "They are very clear and defined for the motoring public."

The interchange is within a heavily traveled urban corridor and one of the biggest challenges was to provide a design that could be constructed while maintaining traffic throughout the project site. Detours and lane closures are planned to avoid pattern overlaps and traffic volumes are monitored on a regular basis using Smart Work Zones (SWZ), which are applications of Intelligent Transportation Systems (ITS) utilized to help improve safety and mobility.

The new structures are designed for a 75-year design life.

The management and protection of traffic plan includes closures and detours, and daytime and nightly lane and ramp closures based on the work scheduled, such as paving and steel erection. To get materials and equipment on to the project site, the team uses the temporary lane closures and/or off-peak hours. CTDOT is maintaining all existing lanes during off-peak hours.

The joints on the COB consist of a molded rubber and a steel expansion joint unit, which accommodates structural movements and concrete headers. High strength aluminum wear-plates are molded into the top surface and grooved to provide skid resistance. The concrete header will be normal deck concrete, while the joint itself is rubber, steel and aluminum. While not exactly the same, the new joints are very similar to the existing joints.

The pavement surface on the Route 3 ramp is known as a High Friction Surface Treatment (HFST), composed of calcined bauxite aggregate that is bonded to the existing pavement surface with epoxy. HFSTs are increasingly used nationwide due to what many regard as superior friction characteristics. CTDOT is looking for further opportunities to use the material in additional areas that have a high friction demand.

For the roadway areas being widened, the existing poles, foundations and underground foundations are being removed and replaced, and new LED luminaires will be installed. In the areas where no roadway changes are occurring — I-91 southbound, COB, I-91 and the Route 3 Interchange — the existing lighting infrastructure will remain, but the high pressure sodium (HPS) lights are being converted to LED. Existing HPS under bridge luminaires are being converted to LED within the project limits.

Michael Daley, OGBHD's project manager, who has managed several large projects, noted that the two JV partners have worked together on previous projects, and that the JV and CTDOT are united in ensuring the outcome is a success.

Thus far, the JV has completed the I-91 median from Cove Bridge to Route 5/15 Bridge, I-91 NB sign structures, I-91 concrete pavement repairs and substructure on bridges 6947, 6000, 0480 and 1466. The 2021 construction season will focus on opening the new I-91 northbound ramp to Route 5/15 northbound over the COB, completed I-91 northbound and southbound, including ramps and East Hartford Bridges at Silver Lane and Main Street.

The project has its challenges, including securing experienced construction workers.

"Obtaining and developing the best trade's people possible, while maintaining productivity, are our overall challenges," said Daley. "Without them, the work cannot get done or be done to the highest standards. General Superintendent Larry Doyon, Roadway Superintendent Bill Noll, Bridge Superintendent Bob Nardi, and Night Superintendent Ryan O'Halpin have done an awesome job of finding these trades people and training them for the future."

"They have been working with the unions and other sources to obtain the best possible trades people in order to get the work done with the best quality and safety in mind, while maintaining the schedule," he added. "They used a retired foreman to help train the new foreman and trades people not only to make sure this project goes well, but to build a future for the company. We give them all the credit. It's a real team-effort."

Soil issues are minimal, and water and utility issues were overcome with the assistance of the CTDOT, WSP and CME.

Careful coordination allows crews to work day and night shifts at multiple locations.

"Bill Noll has been key in coordinating all aspects of the night work and making sure they run smoothly and productively with the day work," said Daley. "This project has tight work zones. We work with CTDOT and WSP on each work zone to make sure we have the safety of the traveling public, as well as that of our own workers in mind."

Despite the many elements, Daley keeps his eyes on the prize.

"The key construction activities are completing the first stage of the Charter Oak Bridge widening and the new off-ramp Bridge (6947) from I-91 NB to Route 5/15 NB by May 26, 2021," he said. "We have worked around-the-clock to complete these bridges this year so we can tie them in by next May. Challenges started with utilities, piles and bridge substructure — piers and abutment — and now have moved on to the bridge superstructure — the decks. Each activity was addressed with CTDOT, WSP and CME as the work progressed. Utilities were relocated, piles driven through caissons and bridge structures formed and poured."

Specialty equipment such as an ICE Auger 5550 for drilling and ICE vibratory and diesel hammers are helping push the project.

"We will be working through this winter to maintain the schedule," said Daley. "Any work that can be done in the cold weather will be done."

Daley is assisted by Kevin Mierzejewski, James Drake, Kevin Bernard, Michelle Fredette, Brett Stackhouse, Craig Miller, Joe Hudach, Joe Sefcik, Mike Lenhardt, Kevin Voelker, Nate Marsili, Paul Kuna and Jenica Herazo.

"The team is working well together," said Daley. "All work is done ahead of schedule and any issues that come up are addressed quickly to keep the project moving. The crews have been great, working safely and pushing through the work to stay on schedule while we deal with the current health issues."

Peak days have 220 construction workers on site, with local and regional subcontractors brought on board.

Excavation and demolition is expected to generate 25,000 tons of concrete, 210,000 tons of asphalt, 1,000 tons of steel, and 170,000 tons of earth and rock. For new materials, the JV is bringing in 31,000 tons of concrete, 260,000 tons of asphalt and 5,800 tons of steel.

"We are reusing as much of the earth excavation as much as possible;" said Daley. "Recycling is very important to us, but due to the specifications, reuse of materials is limited."

Other equipment on-site includes: Cat 345 and 330 excavators, Cat D4 and D6 dozers, Cat 966 loaders, Cat and Bomag rollers, Woodings drills, Grove and Manitowoc cranes, and Kenworth tri-axles and crash trucks.

Maintenance is crucial to ensure production is continuous.

"We have three mechanics on duty between the day and night shifts," said Daley, "and we keep tabs on the equipment on a daily basis and repair as necessary."

OGBHD purchases and rents equipment from dealerships such as H.O. Penn in Newington, W.I. Clark in Wallingford, and Shawmut Equipment in Manchester (all in Connecticut), and ICE Incorporated in Sayreville, N.J. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA