List Your Equipment For Free  /  Seller Login

Cleaning Up Moab UMTRA Site Will Likely Top $1B

Tue February 13, 2018 - West Edition #4
Chuck Harvey


A gantry crane is used on the rail bench to transfer containers to and from the train at the Moab site.
(S&K Moab TAC Team, Contractor to the U.S. Department of Energy photo)
A gantry crane is used on the rail bench to transfer containers to and from the train at the Moab site. (S&K Moab TAC Team, Contractor to the U.S. Department of Energy photo)
A gantry crane is used on the rail bench to transfer containers to and from the train at the Moab site.
(S&K Moab TAC Team, Contractor to the U.S. Department of Energy photo) Reach stackers are used at the Moab site to transfer containers to and from haul trucks and at the Crescent Junction site to transfer containers to and from the train. 
(S&K Moab TAC Team, Contractor to the U.S. Department of Energy photo) Excavated tailings are being loaded into a haul truck to be spread out on drying beds on the tailings pile where they are conditioned to reach the proper moisture content for compaction in the disposal cell.
(S&K Moab TAC Team, Contractor to the U.S. Department of Energy photo)
 At the Crescent Junction site, tailings are end-dumped from the containers into the disposal cell.
(S&K Moab TAC Team, Contractor to the U.S. Department of Energy photo)  Water wagons or water trucks are used at both sites for dust suppression to help keep the radon gas from dispersing.
(S&K Moab TAC Team, Contractor to the U.S. Department of Energy photo)

A massive undertaking to remove and relocate uranium-ore tailings from a Moab, Utah, site is in its eighth year with materials continuing to be extracted and carried by train to a site in Grand Junction, Utah.

It's called the Moab UMTRA (Uranium Mill Tailings Remedial Action) Project.

The project site — 3 mi. northwest of downtown Moab within Grand County — covers about 480 acres, with mill tailings sitting on 130 acres within the site. The site is near Arches National Park and the Colorado River

The project is a long-term effort. Crews started shipping tailings in 2009. The current estimated completion date for the cleanup project is 2034.

Initially the funding amount was $35 million, but over the last five years has averaged about $36 million per year. The total estimated lifecycle cost for the project is approximately $1 billion.

The project involves excavation and removal of health-threatening uranium-ore mill tailings and other contaminated materials and transport of the materials in containers by train to a disposal site near Crescent Junction, Utah. Huge hauling trucks receive the materials and carry them to awaiting rail cars.

An overpass was built across Potash Road at the Moab site, so haul trucks will not have to encounter highway traffic. A gantry crane is used to transfer containers of the contaminated materials to and from the train.

Crews constructed an engineered disposal cell near Crescent Junction to receive the mill tailings. The mined uranium was used in making atomic bombs during the cold war era.

The Moab UMTRA project also includes remediation of ground water at the mill site. The U.S. Department of Energy Office of Environmental Management in Grand Junction, Colo., manages the project.

The uranium mining mill operated at the site until 1984. In 2009, the federal government provided an initial $108 million in federal stimulus money to fast-track the clean up.

The funding was part of the American Recovery and Reinvestment Act of 2009. Most of the money was used to accelerate tailings shipments from the Moab site to the Crescent Junction disposal site.

Part of the annual $36 million in funding goes toward covering the disposal cell near Crescent Junction. Crews will cover about 50 acres of the disposal site with clay and rock material.

Engineers have designed protective berms to keep the water away from the radioactive dirt.

Multiple Contractors

Portage Inc., which is owned by Northwind, both of Idaho Falls, Idaho, is the prime contractor for the Remedial Action Contract (RAC). Portage has subcontracted some of the RAC scope to Utah-based-Nielson and Wood, its teaming partners.

S&K Logistic Services LLC (SKLS) of Byron, Ga., is the prime contractor for the Technical Assistance Contract (TAC). It teamed with Pro2Serve of Oak Ridge, Tenn., to perform the TAC scope.

Portage was awarded a follow-on contract beginning in October 2016. SKLS was awarded its current contract beginning Sept. 20, 2017, after a competitive bid.

The project has multiple local and regional subcontractors for various smaller scopes of work, such as electrical, pest control, portable toilets, rail maintenance and laboratory analyses. Union Pacific Railroad is the rail transportation subcontractor. Some of the major names include Bodec Electric of Price, Utah; London-based Balfour Beatty; and ALS Environmental of Simi Valley, Calif.

The train is loaded at Moab and then unloaded the following day at Crescent Junction with a roving crew that works at the site based on where the train is located. Overall, about 95 workers are on duty daily at the Moab and Crescent Junction sites.

Uranium Ore Shipments

Current work features regular shipments of the uranium-ore tailings.

The shipping schedule is one train, two days a week for most weeks unless there is a holiday. The project began shipping 140 containers on each train last summer and has continued that level with a total of slightly more than 4,600 tons per trainload.

About 450,000 tons are planned to be shipped to the disposal cell annually. The total estimate to be shipped over the life of the project is 16 million tons.

Heavy equipment at Moab includes articulated haul trucks, dozers, excavators, reach stackers, tractor with disc, grader, gantry cranes, water trucks and wagons, over-the-road haul trucks and trailers.

Heavy equipment at Crescent Junction includes articulated haul trucks, excavators, compactor, reach stackers, loaders, water trucks and wagons.

The trucks hauling containers to the train in Moab are a standard over-the-road tractor pulling a triple-axle trailer. The trucks transporting containers at Crescent Junction are a 40-ton articulated haul truck modified to carry containers. At each location, trucks travel about one-quarter to one-half mile to and from the train.

The project has two gantry cranes at the Moab site; however, only one is currently used at a time. There are no gantry cranes at Crescent Junction. Reach stackers are used to transfer containers to and from the train at that site.

Preventing Contamination

The project will help prevent contamination caused by floods.

“Moving the mill tailings to a permanent disposal cell away from the Colorado River will eliminate the risk of tailings being washed into the river from a catastrophic flood event,” said Wendee Ryan, public affairs manager for S&K Moab TAC team, a contractor to the U.S. Department of Energy.

She added that most employees live within a 100 mi. radius of Moab and that the project provides stable, year-round employment to the area.

Ryan said the Moab tailings pose no direct threat to Arches National Park. However, contaminants, mainly ammonia and uranium, from the tailings pile have seeped into the ground water, causing concentrations to exceed regulatory limits. In 2003, crews installed an interim action ground water remedial action system to capture contaminant mass and to reduce contaminant concentrations prior to them discharging to the river.

The groundwater at the site is not a drinking water source.

“Flash flooding of the Moab Wash can occur and severe storm events can cause erosion of the tailings pile,” Ryan said. “The project has constructed berms around the base of the pile to minimize release of contamination off site during events like these.”

Protocol

Materials are dumped at the disposal cell according to a specific protocol.

At the Crescent Junction site, crews unload the containers carrying tailings from a train onto trucks that take them to the disposal cell dumping area.

The containers are a modified intermodal container constructed of steel and equipped with a locking metal lid placed on top. Each container also has a top-hinged gate the truck driver can open and close. The tailings are top-loaded in the containers in Moab and emptied in the disposal cell via the gate.

The 1-ft. lift refers to the non-compacted thickness in which the material is spread in the disposal cell. The thickness of the lift is limited to 1 ft. to ensure sufficient compaction is achieved through the entire thickness of the lift prior to the placement of the next lift on top of it.

The tailings are dumped through end gates in the containers and placed in the cell in 1-ft. lifts to meet compaction specifications. Workers then reload the empty containers onto railcars and returned to the Moab mill site.

The disposal site is rectangular and is aligned in a west-to-east direction. The completed cell will be about 5,200 ft. long by 2,400 ft. wide. The cell is excavated about 25 ft. below the existing grade. Then the deposited materials are built up to a height of about 25 ft. above ground level. Crews are capping the top of the contaminated materials with a 9-ft.-thick multi-layered cover composed of native soils and rock.

Located northeast of the eastern junction of I-70 and U.S. Highway 191, planners selected the location disposal location because of its ideal geological setting.

To keep the project moving, crews operate one tailings-carrying train a day, two days a week. The trains carry 136 containers for a total of about 4,600 tons per trainload.

Project Phases

Because of the vast size of the project, work is being done in multiple phases. A third phase began in spring of 2016.

The first two phases of excavation of the disposal cell have been completed, as space is needed for placing tailings material. A portion of the third phase was excavated in spring 2016 and another portion of that phase was excavated in spring 2017.

The third phase is about halfway complete; however, the remaining half will likely not need to be excavated for several years.

A total of four phases of excavation are planned.

Uranium Milling Near Moab Began in the 1950s

Uranium Reduction Co. constructed the Moab mill in 1956 and operated it until 1962 when the assets were sold to Atlas Minerals Corp.

Workers milled uranium concentrate called yellowcake. The yellowcake was sold to the U.S. Atomic Energy Commission through December 1970 for use in national defense programs.

After 1970, production was primarily for commercial sales to nuclear power plants. During its years of operation, the mill processed an average of about 1,400 tons of ore per day.

The milling operations created tailings, a radioactive sand-like material. The tailings were pumped to an unlined impoundment in the western portion of the property. The material then accumulated over time to form a pile exceeding 80 ft. thick.

Although more than 90 percent of the uranium was removed during processing, radium and other decay products remained in the tailings.

Atlas operated the mill until 1984 when it demolished the processing buildings and buried them in the southwest corner of the tailings pile and covered the material with an interim cover. It was part of decommissioning activities between 1988 and 1995.

Atlas proposed to stabilize the tailings pile at Moab by permanently capping it in place. However, Atlas declared bankruptcy in 1998 requiring the company to relinquish its mining license.

The U.S. Nuclear Regulatory Commission then appointed PricewaterhouseCoopers as the trustee for the Moab Mill Reclamation Trust and licensee for the site.

Regulations dealing with uranium mill sites began in the 1970s when scientists, community leaders and public officials became more aware of the potential health risks associated with long-term exposure to uranium mill tailings. The Uranium Mill Tailings Radiation Control Act of 1978 required the cleanup of inactive uranium-ore processing sites.

Equipment Maintenance

Maintaining equipment in the long haul has been a challenge for companies involved in the Moab-Crescent Junction project.

Much of the heavy equipment at both sites has been in use for eight years and maintaining or replacing the aging equipment is a costly challenge. In addition, the tailings material has corroded the inside of some of the shipping containers. New metal panels have been welded to the outside of many containers and a polyurea liner has been sprayed on the inside of about 150 of the original roughly 350 containers. Twenty-two new containers were purchased in 2016 and more may be purchased in 2018 to replace those beyond repair.

CEG




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA