Company Sues R.I. Over Providence Viaduct Project

Wed December 14, 2016 - Northeast Edition #25
Construction Equipment Guide


PROVIDENCE, R.I. (AP) A Connecticut construction company working to rebuild the southbound bridge section of the Providence Viaduct on Route 95 is suing the state for breach of contract.

The Providence Journal reported the suit filed in September says Manafort Brothers Inc. is asking the state for damages “in excess of $4 million' for extra work the company performed as the project fell behind schedule.

The project started in 2013 and was expected to end last year. Manafort had signed a $66.8 million contract but the Department of Transportation's most recent quarterly report estimates construction costs will total $74.4 million.

DOT spokesman Charles St. Martin said the report pegs the initial estimated cost at $68.9 million.

The state has paid Manafort $64.1 million as of Sept. 30.

It countersued in October.




Today's top stories

Iconic Hotel Being Demolished to Make Way for Baseball Stadium

MD 4 Project to Add Diamond Interchange

Volvo Construction Equipment Showcases New Products at North American Volvo Days

VIDEO: Anniversary of Highway Workers' Memorial Renews Calls for Work Zone Safety

Yanmar Compact Equipment Introduces New Line of Branded Attachments for Compact Track Loaders

Caterpillar Introduces Dynamic Energy Transfer Solution for Battery, Diesel-Electric Mining Equipment

Five Finalists Compete for Grand Prize Makeover in Bobcat Park and Rec Makeover Contest

VIDEO: Students From Washington, Ohio Earn Top Honors in Annual ARTBA Transportation Video Contest


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA