List Your Equipment For Free  /  Seller Login

Brosamer & Wall Utilize Unique Concrete On 130-Year-Old Canal

Wed July 27, 2022 - West Edition #16
Irwin Rapoport – CEG Correspondent


Brosamer & Wall Inc. recently completed the $52 million second phase of the Florence Canal Reach 2 Rehabilitation and Lining Project in Arizona by utilizing a 3,000 PSI mix for concrete, a material not usually seen in similar projects.
(Photo courtesy of Brosamer & Wall.)
Brosamer & Wall Inc. recently completed the $52 million second phase of the Florence Canal Reach 2 Rehabilitation and Lining Project in Arizona by utilizing a 3,000 PSI mix for concrete, a material not usually seen in similar projects. (Photo courtesy of Brosamer & Wall.)
Brosamer & Wall Inc. recently completed the $52 million second phase of the Florence Canal Reach 2 Rehabilitation and Lining Project in Arizona by utilizing a 3,000 PSI mix for concrete, a material not usually seen in similar projects.
(Photo courtesy of Brosamer & Wall.) (Photo courtesy of Brosamer & Wall.) The project features construction of approximately 11.50 mi. of concrete lined canal, structures, and concrete pipes.
(Photo courtesy of Brosamer & Wall.) The project features canal excavation, compacted embankment and embankment construction, soil blending, trench excavation and backfill and more.
(Photo courtesy of Brosamer & Wall.) This major initiative has B&W crews excavating approximately 300,000 cu. yds. of earth and rock and installing approximately 25,000 cu. yds. of concrete lining.
(Photo courtesy of Brosamer & Wall.) To date, Brosamer & Wall has completed all the canal excavation, paving and lining, installation of all the substructure and turnouts, as well as the gates and radio gates.
(Photo courtesy of Brosamer & Wall.) (Photo courtesy of Brosamer & Wall.) (Photo courtesy of Brosamer & Wall.) (Photo courtesy of Brosamer & Wall.) (Photo courtesy of Brosamer & Wall.)

Construction crews from Brosamer & Wall Inc. (B&W) have completed work on the second phase of the $52 million Florence Canal Reach 2 Rehabilitation and Lining Project.

The firm is aiming to complete the rest of the Pinal County, Ariz., project checklist by January 2023.

The project is based on concerns of excessive seepage losses. The primary purpose of the project is to address agricultural water management, supply and conservation issues affecting the San Carlos Irrigation And Drainage District (SCIDD).

This major initiative has B&W crews excavating approximately 300,000 cu. yds. of earth and rock and installing approximately 25,000 cu. yds. of concrete lining. The concrete is being supplied by CEMEX, which has a nearby plant.

What makes this project unique is the material that is being used. The SCIDD dries the canal twice a year — in mid-October for six weeks — and then returns the water for four weeks, followed by another five dry weeks.

"We put in long hours during those weeks to ensure everything was done within the timeframe," said Russell P. Gonzalez, B&W's project engineer. "We used a 3,000 PSI mix for the concrete. With these types of canals, it requires a certain level of air for the mix and a fiber in the substrate of the concrete that one does not normally see in other projects."

The work to improve the canal was essential.

The project features construction of approximately 11.50 mi. of concrete lined canal, structures, concrete pipes and other appurtenances. The existing Florence Canal Reach 2 includes an existing earthen canal with flow control structures and equipment, turnout structures and pipes, road crossings, wells, utilities and other features.

"These upgrades are needed to update the aging structures, improve the hydraulic efficiency of the system and minimize canal system water losses," said Shane Lindstrom, general manager of SCIDD. "This 130-year old earthen canal will be concrete-lined, with five new check structures, 27 turnouts and modern electronic and manual flow measurement.

Project Scope

The project consists of many obstacles. B&W is responsible for site clearing, the removal of existing canal structures such as canal gates and the removal and salvage of select canal gates and the removal and legal disposal of various features coated with lead based paint.

The project features canal excavation, compacted embankment and embankment construction, soil blending, trench excavation and backfill, riprap with geotextile fabric, cleaning and stockpiling of riprap for reuse, the building of reinforced concrete structures, canal trimming, concrete lining with fibrous reinforcing that includes hand placed concrete lining with fibrous reinforcing; and the installation of reinforced concrete pipe along with 78-in. and 54-in. concrete siphon pipe extensions; and other mechanical work.

To date, Brosamer & Wall has completed all the canal excavation, paving and lining, installation of all the substructure and turnouts, as well as the gates and radio gates.

"There is one structure left where have to install gates and we need to install all the electrical and solar equipment," said Gonzalez. "Next season we'll start doing the road crossings, which [brings] everything together.

"We started at the end of the project and worked our way to the beginning in the first season, which started in late August 2020 and went to January 2021," Gonzalez added. "We covered six miles. Then we went to the beginning because there was some land acquisition and utilities to be moved in middle part of the project. We went downstream from April to May, paving all of it. In August 2021 we were working in the middle and completed all the paving last January."

It took approximately three days for the concrete to cure and gain strength. The concrete lining is 4 in. thick.

Jayco, a subcontractor, performed the earthwork

"They kept ahead of the canal trimming and lining," said Gonzalez. "In one segment of the project we installed a water bypass to allow the earthwork to start eight weeks before the scheduled dry up period. Once you build a canal, you have to start the trimming process no more than two days before you pave. That is where you go with the trimmer and shave about six inches."

While this was Gonzalez's first canal project, he was surrounded by many with a wealth of experience.

"Our owner, Bob Brosamer, has been building canals for more than 30 years," said Gonzalez. "John Pologar, our project manager, this will be his eighth canal project. Our superintendents, Mike Newman and Jack Beale, have more than 20 years of experience. Basically everyone on the project had a lot of canal experience."

Precast concrete elements were utilized, including those for the turnout structures, which were supplied by Jensen Precast .

"The turnout structure was five to seven days to build," said Gonzalez. "The curing took a few days and then they were transported in two, top and base."

The structures were set in using a 250 ton hydro crane, which was supplied by Marco Crane and Rigging Company.

Reinforced concrete pipes were required for the turnouts — 36-in. and 24-in. — which were manufactured by Forterra, a local supplier.

Also installed were steel pipes at well discharges and 54-in. and 78-in. reinforced concrete low head pressure pipe.

The lining of the canal required approximately 29,000 cu. yds. of concrete.

"On average, we were doing about 3,000 linear feet a day and on a good day, about 5,000 linear feet," said Gonzalez. "The check structures were built before or at the same time as the paving. In two areas the check structures were already built, so as we paved up, we used a crane to jump each piece of paving equipment. We would be able to jump all the equipment and start back up within two hours, usually we would make this day our short day and resume the next day."

The jumping required coordination to move the equipment to the other side. Hunter Contracting was responsible for all the cast in place structures, which was approximately 6,000 cy. yds.

Equipment in these operations consisted of a Case 621B loader and a Cat 302D excavator. The excavation operations has crews using excavators, a 14G Cat motor grader, a 289 Cat skid steer and a Cat D6 dozer.

Peak days had 50 to 60 people on-site. The major subcontractors are Hunter Contracting for major concrete structures, Ludvik for electrical, Western Technology for quality control, D2 for surveying, DEG for concrete structures, Harris for rebar and Municipal Treatment for all the gates.

"The soil did not affect the equipment," said Gonzalez. "There were times when we had a track go out. Sometimes we would be able to fix it — it would be down for 20 to 30 minutes. We'd have a hydraulic line go down and be able to fix it on the spot. There were a few times when something would break down for a day. We had our mechanics on-site to take care of equipment large and small.

"Ken Gilmour configured all the paving equipment," he added. "He's been in the canal industry for a long time.

Working in Summer Heat

The project has its challenges, such as paving in the hot Arizona summers.

"It gets up to 110 and 120 degrees," said Gonzalez. "To keep the work moving in April and May, we started paving around 11 p.m. until 5 or 6 a.m. — before it got too hot. CEMEX added ice to kep the mix cool and sprayers would spray the drums on the outside to keep the concrete cool."

The crews were well hydrated, but working at night was not uncomfortable until the morning when the sun began to shine.

"There were electrical and gas utilities that needed to be relocated," said Gonzalez. "Some of the lines were too low and had to be moved and raised. It was a challenge working with the utilities — trying to work around them and with them to keep the work moving. For soil, there were some areas with unsuitable soil, heavy clay, but that was accounted for in the estimate and specifications. In those areas we removed the unsuitable material and replaced it with good soil. Our goal was to keep all operations going to stay on schedule for the canal lining.

"The original canal was a dirt-lined canal," he added. "We widened it, built it up, and lined it with concrete. There were some areas where there was going to be a new alignment, so we built a new portion." CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA