Contractors for the Georgia Dept. of Transportation (GDOT) — including ER Snell — have started to continue construction activities related to the I-16/I-75 Interchange Improvement Project in Macon-Bibb County.
After C.W. Matthews completed Phase 1 of the $500 project, which covered the area of I-16 from the I-16/ I-75 split to the Martin Luther King Jr. Boulevard exit, crews from E.R. Snell now are executing Phases 2 and 3, which cover the area of I-75 from Hardeman Avenue to I-16 eastbound.
Work for this portion of the project includes:
Crews began the newest phases of construction on Feb. 10.
Work for these phases consists of:
Contracting crews and members from GDOT currently are evaluating project area for remaining work items of Phase 1.
Overall, the I-16/I-75 Interchange Improvement project will enhance safety and mobility of the interchange by widening and reconstructing I-75 from Hardeman Avenue to Pierce Avenue and I-16 from I-75 to Walnut Creek within the city of Macon and Macon-Bibb County. This project represents a $500 million investment in the city, the Middle Georgia region and the state's transportation system and will support Georgia's growing freight and logistics industry.
More specficially, the project aims to construct additional interstate lanes, wider shoulder lanes and additional on- and off-ramps. A new collector/distributor (CD) road system will be constructed parallel to both I-16 and I-75, which will allow additional non-interstate traffic capacity. Modifications will be made to bridges and surface streets within the project area to accommodate the additional interstate and CD lanes. These surface street improvements will add or expand dedicated turn lanes, which will reduce congestion and improve mobility for commuter traffic.
Phase 1: I-16 Eastbound — Improved approximately 1.5 mi. of I-16 EB between I-75 and Coliseum Drive. Phase 1 construction contract was awarded to C.W. Matthews, low bid at $70 million.
This portion was completed in summer 2022. Roadwork included operational improvements to I-16 WB at the Spring Street interchange. These improvements eliminated the existing weave and improve safety on I-16 EB between I-75 and Spring Street. Crews also closed the Spring Street loop ramp and constructed the I-16 EB collector distributor (CD) road between I-75 and Spring Street.
Phase 1B — Involved the mitigation improvements to the Pleasant Hill Neighborhood on each side of the I-75 corridor. The Phase 1B construction contract was awarded to E.R. Snell for $13 million.
This portion of the project was completed in spring 2018. Roadwork included the relocation and rehabilitation of home to seven vacant lots and building 17 new residential structures throughout the community; created a linear park that includes green space and multi-use trail, lighting and information kiosks along the east side of I-75; created the Jefferson Long Park on the west side of I-75; the boyhood home of Little Richard, the Penniman House, was relocated adjacent to the Jefferson Long Park and serves as a community resource center, where specially created mobile interpretative panels are now displayed; constructed noise and visual walls along I-75 within Pleasant Hill; replaced the David Lucas Pedestrian bridge, transformed an existing open drainage ditch into a grass-covered culvert and streetscaping (resurfacing and sidewalk rehabilitation) throughout the community; and the closure of Frontage Road between First and Second Streets to be used as greenspace access to pedestrian bridge.