List Your Equipment For Free  /  Seller Login

Vecellio & Grogan Leads Project Along Heavily Traveled Route

Mon December 20, 2021 - Northeast Edition #26
Brenda Ruggiero – CEG Correspondent


The contract was awarded to Vecellio & Grogan Inc. for an authorized amount of $27.2 million. Cody Webb serves as the project manager.
The contract was awarded to Vecellio & Grogan Inc. for an authorized amount of $27.2 million. Cody Webb serves as the project manager.
The contract was awarded to Vecellio & Grogan Inc. for an authorized amount of $27.2 million. Cody Webb serves as the project manager. One unique aspect noted by engineers was that the existing abutments and piers of both the northbound and southbound remained in place. Phased construction was used for the three bridges while maintaining traffic flow. In addition, a tunnel below the project was backfilled with 1,500 cu. yds. CLSM (low strength concrete) and 1,400 cu. yds. of stone. A configuration change at Exit 99 of Interstate 79 in Weston, W.Va., is nearly complete. Engineers at WVDOT’s District 7 reported that one challenge of the project involved the high volume of traffic on Interstate 79.

A configuration change at Exit 99 of Interstate 79 in Weston, W. Va., is nearly complete.

The project, headed by the West Virginia Department of Transportation (WVDOT), began in March 2019. An extension took the project to November of this year, but Dec. 31 is the actual expected completion date, according to Jennifer J. Dooley, WVDOT public relations director.

The contract was awarded to Vecellio & Grogan Inc. for an authorized amount of $27.2 million. Cody Webb serves as the project manager.

Funding was received through West Virginia Gov. Jim Justice's Roads to Prosperity highway construction program, which provided $2.8 billion to many projects.

The contract calls for changing the configuration of the entrance ramp and exit ramp on I-79 southbound at this exit to make the intersection safer.

"In the previous configuration at this exit, traffic exiting I-79 southbound on to a ramp and traffic entering I-79 southbound from another ramp would do so at nearly the same point, resulting in accidents," Dooley said. "In addition to new road construction and earthmoving, the contractor has reconstructed new decks and installed new beams for both northbound and southbound bridges. Two new traffic signals were also installed on Rt. 33."

Engineers at WVDOT's District 7 reported that one challenge with the project involved the high volume of traffic on Interstate 79. In addition, they cited the longer timeframe of construction, which was more than two years.

A large volume of earthwork was required to create the exit ramp from I-79 southbound. Phased construction (concrete pouring) was used to allow traffic to continue traveling on the bridge decks. Basically, half of the deck was poured at one time.

Narrowing of the two-lane interstate down to one lane was necessary as paving took place, and construction and paving of the ramps was done under traffic.

Another challenge was paving the heavily-traveled section of Route 33 under traffic.

One unique aspect noted by engineers was that the existing abutments and piers of both the northbound and southbound remained in place. Phased construction was used for the three bridges while maintaining traffic flow. In addition, a tunnel below the project was backfilled with 1,500 cu. yds. CLSM (low strength concrete) and 1,400 cu. yds. of stone.

"Backfilling tunnels with CLSM is not common on WVDOH construction projects but can be a useful method for eliminating mine voids below building footprints," Dooley said. "Patience has to be exercised with this method to allow material to build and set up within the voids, rather than to allow material to run completely free."

Currently assigned to the job are four GPI consultant inspectors, including Keith Loar, C.J. Skeens, Chase Lewellyn and Russ Conrad. On the contractor's crew, an average of 12 workers are on site daily, primarily operators, laborers and carpenters.

Dooley said that there are 22 subcontractors for this project, with the 10 most prominent being WVA Paving for asphalt placement on the entire project, PDK Construction for guardrail installation; Reclaim Company for existing bridge deck demolition; C & L Welding for installation of Class H concrete stay-in-place deck pans; Martin Reinforcing for installation of approach steel, parapet, deck pier cap and abutment steel and erection of the superstructure; Roadsafe Systems for installation of traffic control devices for the project, temporary signage, barrels, cones, striping, Type V markings, message boards, arrow boards and RPM's; Swank Construction Company for saw cutting the existing bridge decks for demolition; Specialty Groups for signal work, signals, signal controllers, sign lighting and signal heads; Oglesby for forming and pouring concrete structures, i.e. concrete flume, parapet walls; and BOCA Milling for asphalt milling with a Wirtgen milling machine.

The equipment list, a combination of rented and owned pieces, includes various excavators, a Caterpillar dozer, manlifts, dump trucks, pavers, dozers, heavy-duty cranes, light plants, backhoes, generators, various hand tools and asphalt rollers. Already removed from the project were a grader, steel drum roller, articulated trucks and drills. CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA