Covington Road Upgrade Aims to Relieve Congestion

Wed October 17, 2018 - Southeast Edition #22
Irwin Rapoport – CEG Correspondent


A multilane roundabout is being constructed at the intersection of Georgia SR 12 and SR 142.
A multilane roundabout is being constructed at the intersection of Georgia SR 12 and SR 142.
A multilane roundabout is being constructed at the intersection of Georgia SR 12 and SR 142. The existing bridge remains in use as construction proceeds on a new bridge over the Alcovy River. Widening Georgia SR 12 is expected to use 4,000 cu. yds. of concrete, 55,000 tons of asphalt, and 498,000 lbs. of steel. A $19.3 million GDOT project is reconstructing and widening a 3.5-mi. section of State Route 12/U.S. 278 from the city of Covington limits to east of SR 142. Plans call for the installation of a traffic signal at the intersection of Georgia SR 12 and Elks Club Road.

E.R. Snell Contractor Inc. is on schedule and on budget in the construction of the Georgia Department of Transportation's (GDOT) $19.3 million project to reconstruct and widen a 3.5-mi. section of State Route 12/U.S. 278 from the city of Covington limits to east of SR 142.

The Newton County project, which began in March 2017, is nearly 40 percent complete and has a contract completion date in May 2020.

The project involves widening and reconstructing SR 12 from west of Henderson Drive to just beyond the SR 142 intersection. The route will consist of two 12-ft. lanes in each direction separated by a 24-ft. raised, grass median, with 10-ft. rural shoulders, 6.5 ft. of which will be paved. Also included is a multilane roundabout at the intersection of SR 12 and SR 142, the replacement of two bridges, construction of an interchange where two highways connect, and the installation of a traffic signal at the intersection of SR 12 and Elks Club Road.

The project has been planned since the early 2000s, and state and federal funding is covering the cost of the initiative from right of way to engineering and construction. ROW acquisition began in 2014 and exceeded $2 million.

SR 12/U.S. 278 is industrial and commercial toward the Covington (western end) of the project, but then begins changing to rural and residential as it approaches SR 142.

"The goal of this project is to combat the potential growth of the area, which is based on the heavy truck use supporting several plant facilities," said GDOT project manager Gregory L. Bailey. "With the potential expansion of these businesses, as well as population growth, it was necessary to widen this road to meet those needs."

Prior to the construction, 2016 daily traffic counts along SR 12 varied from 13,500 to more than 18,000 vehicles a day. The new infrastructure, designed by GDOT, will meet traffic demands for several decades.

A unique safety feature of the project is the multilane roundabout design on the eastern end.

"The decision to construct a roundabout for the intersection of SR 12 at SR 142 was based on the preferred safety and operational improvements a roundabout would offer," states a GDOT engineering report for the project. "The geometries of the intersection also make this intersection a good candidate for a roundabout."

The report also noted that widening SR 12/U.S. 278 will improve the projected level of service, reducing congestion and driver discomfort, as well as addressing concerns about safety raised by accident statistics for SR 12 from SR 142 to the Alcovy River.

"The accident rates along this section of SR 12 are extremely high for a rural minor arterial," it stated.

The two bridges have a sufficiency rating of 79.8 and were deemed "acceptable to be widened."

"The purpose of the widening is to better facilitate the current traffic demands we currently have and to project down the line and facilitate that traffic as well," Bailey said. "All of our bridges were designed to withhold the anticipated load based off the heaviest traffic with the heaviest load. Many of our subsidiary roads had sight distance issues involving alignment, so this project aims to address those issues with relocation of Mason Drive, Fairfield Drive, McGruits Bridge Road and Elks Club Road."

Traffic management measures during construction include relocation of traffic signals and additional shifts of side roads.

"We are staging construction to ensure that motorists are not inconvenienced and construction personnel are as safe as possible," said Bailey. "To better facilitate this, we are doing minor traffic shifts for the subsidiary roads before the major shifts to allow motorists to adapt to the new configuration. During the time of construction, E.R. Snell elected to lower the speed limit 45 miles per hour for the safety of the public."

E.R. Snell crews, led by project manager Thomas Byrd, have completed 75 percent of Stage 1 of the roundabout and 80 percent of Stage 1 of the bridges.

"On Nov. 15 we're planning on switching traffic to the corridors over to the new Stage 1 areas so we can start on Stage 2 construction," said Scott Briscoe, president of E.R. Snell. "Our crews are working year-round, although we may have a little bit of slowdown in winter. We had some utility issues around the bridges with some gas line work and that delayed the project slightly."

Utilities are making efforts to reroute their infrastructure as the construction proceeds.

"This hasn't been a hard job — the challenges were nothing extreme," said Briscoe. "Any time you work around a bridge or a river, you have to deal with water levels during the rainy season, and that's been a little challenge this year. We have bridge and grading crews working, and pipe crews for the light drainage work."

E.R. Snell management personnel continue to update the schedule and coordinate the work to meet the delivery date.

"Communications with GDOT has always been good," said Briscoe, who noted that issues are resolved rapidly as the project is a straightforward one.

The majority of the work is done via day shifts, with some paving operations taking place at night.

Briscoe added that traffic is a constant concern for the crews, which are building the new lanes like a train in motion, with multiple moving parts.

"In addition to the road work," said Briscoe, "we have a lot of storm drains and boxes to install. The utility relocations and installations are the responsibility of the utilities, but we're coordinating this work."

The two existing east-west bridges on SR 12/U.S. 278 are being rebuilt. The two-lane Alcovy River bridge is being replaced with a 204- by 88-ft. bridge accommodating two 12-ft. lanes in each direction divided by a 24-ft. raised concrete median, including 8-ft. concrete shoulders. The two-lane Alcovy River overflow bridge is being replaced with a 400- by 88-ft. bridge accommodating two 12-ft. lanes in each direction divided by a 24- ft. raised concrete median. It also will have 8-ft concrete shoulders.

The existing bridges continue to be used, with no off-site detour while the new bridges are being constructed.

"Once we complete Stage 1," said Briscoe, "then we'll demolish the old bridges and complete Stage 2."

Peak days have about 40 construction workers on site. The subcontractors are the CLA-Neel Company Inc. for concrete flatwork, Mario Reinforced Steel for all bridge superstructure steel, Augusta Quality Lawn Care for grassing and erosion, American Lighting & Signalization for electrical, Peck Pavement Markings for striping, and Lee & Sims Drilling Services Inc. for caissons.

The work will see the removal of 5,000 tons of concrete, 16,000 tons of asphalt, and 20,000 cu. yds. of earth and rock. New materials are expected to include 4,000 cu. yds. of concrete, 55,000 tons of asphalt, and 498,000 lbs. of steel.

"We're recycling the asphalt from the old roadway," said Briscoe. "The concrete will be broken up and used as fill material. A lot of materials can be recycled."

The project is about 20 mi. from E.R. Snell's main yard/repair facility. It is using a variety of standard equipment, such as cranes (Link-Belt and Kobelco), as well as excavators, dozers, loaders, backhoes, motorgraders, rollers, and pavers manufactured by Cat, John Deere, and Komatsu.

General wear and tear issues include parts and teeth, roughed up edges, and tires.

"Most repairs can be done within a day," said Briscoe, who added that the maintenance crews are top-notch and no additional equipment was purchased or rented for the job.

E.R. Snell purchases equipment from various dealerships.

Briscoe said that good communications with the dealerships are essential, especially in knowing what the company will require in terms of replacements.

"Good service, repairs, and replacement parts when you need them are important considerations," he said, "and price is always a factor."

The general contractor usually replaces equipment based on age and number of hours used.

With about 1.5 years to complete the project, Briscoe is confident in the ability of his crews.

"We try to run a family business and to have everyone involved in the end goal," he said, "and keep them involved in the scheduling, day-to-day activities, and how decisions are made."

CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Construction Industry Optimistically Preparing for New Year Ahead

CFX Oversees $412M SR429 Expansion in Florida

Capital Express Central Project Ramps Up in Texas

VIDEO: NCDOT Plans Major Road Upgrades in Wilmington Over Next Several Years

DEVELON Set to Exhibit at ARA Show 2025

Des Moines Airport Works With Weitz/Turner On Expansion

Ring Power Lift Trucks Partners With Hiab to Bring MOFFETT Truck-Mounted Forklifts to Florida Customers

Earthborne Demo Day Draws Crowd Despite Downpour


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA