List Your Equipment For Free  /  Seller Login

Crane Armada Keeps Tappan Zee Project Afloat

The $3.9 billion N.Y. bridge is one of the largest infrastructure projects in North America.

Fri April 03, 2015 - National Edition
Construction Equipment Guide


The $3.9 billion N.Y. bridge is one of the largest infrastructure projects in North America and nearly half of the cranes on the job are made by Manitowoc. The venture is constructing a 3-mi. (4.8 km) twin bridge to replace the 60-year-old Tappan Zee Bridge that spans New York’s Hudson River. It is being run by Tappan Zee Constructors (TZC), a consortium composed of four contractors.

Bob Hammond, equipment manager of the consortium, said that of the approximately 30 cranes on site, 14 of them are made by Manitowoc. He joins the group from Watsonville, Calif.-based Granite Construction, one of the four companies that comprise TZC.

“Many of our partners in the consortium brought Manitowoc cranes to the project,” Hammond said. “Among them are a Manitowoc 11000-1 crawler crane loading and unloading supplies from barges; two Manitowoc 4600 RINGER cranes that are doing pile driving work, driving sheets, setting concrete and casting forms, and performing form work; a Manitowoc 14000 cleaning piles and handling dig out chores; and a Manitowoc 999 using a clam bucket to handle clean out work for piles.”

A Manitowoc MLC165, a Manitowoc 3900 and a Manitowoc 4000W also are on the job site that is a buzzing hive of activity, hosting up to 500 workers on site at any one time. With some 6,000 pieces of rigging equipment and 55 rigging crews working with an armada of cranes that lift from sunrise to sundown, there is no room for error.

While several of the cranes on site were brought by consortium partners, together as the TZC consortium the companies chose to purchase two of these cranes especially for the project: the Manitowoc MLC165 and the Manitowoc 11000-1.

Both cranes were purchased from Piscataway, N.J.-based Hoffman Equipment. The Manitowoc dealer has four locations in New York and New Jersey. The company has been renting, selling and repairing construction equipment both in the United States and abroad for the past 40 years.

“Hoffman’s been a key element for us to help with assembly of the majority of the cranes we brought to the project,” Hammond said. “Hoffman has also been very instrumental in helping us maintain our fleet and getting machines up and running.”

The 182-ton (165 t) capacity Manitowoc MLC165 chosen for the project is Manitowoc’s newest compact crawler crane. It’s set up on a barge with 177 ft. (53.9 m) of main boom, utilizing a static list load chart configuration. The crane’s list and trim meter has come in especially handy, as the crane is being used on a barge — it’s floated into position before making lifts up to 20 tons (18 t) at heights reaching approximately 90 ft. (27.4 m).

“This size machine was a perfect match for their application,” said Pasquale Tomasetti, an account manager of Hoffman Equipment who facilitated the cranes’ purchase. “It’s extremely versatile too. Not only is it being used as a barge-mounted crane for construction, it’s also performing maintenance and assistance duties for nearly all 30 cranes on the job site.”

TZC chose the Manitowoc 11000-1 for the new N.Y. bridge project for its versatility in setup. The group erected the crane on a trestle, which has a steel platform with wood on top to support the crane. The crane has an ideal size and design for this type of set up and its 110-ton (99 ton) capacity was more than adequate for the project’s lift designs. Along with loading and unloading supplies from the hundreds of barges working along the waterway, it’s also being used as an accessory crane, according to Hammond.

“We’re using the Manitowoc 11000-1 to convey delivery from water to land and back,” Hammond said. “Everyday something different comes in, from lumber to I-beams. Right now we have 150 feet of boom on the crane and we’re using it eight hours a day, shipping materials on and off the job site. Most of the loads run from 20 to 50 tons. The other day we were loading out boom sections at 45 to 50 feet for a Manitowoc 4600, and the loads were 6 tons.”

Following dredging and other preliminary work, permanent construction operations began in October 2013. As the area is cleaned out and piles are driven, construction of the bridge itself is occurring 130 mi. (209.2 km) north of the job site. When completed, the sections will be floated down the Hudson River for assembly this spring.

The cranes will be on site until the end of the project in 2018. The new bridge is being built parallel to the old one, following the same basic contours. After the new bridge is finished, the cranes will stay on site to help demolish the old structure.

“When working on water you can’t move anything around without a crane, so they’re crucial to the project,” Hammond said.

With so many cranes on site, service and support are central to the success of the project. Manitowoc Cranes has helped TZC, deploying its Crane Care service when needed.

“We’ve had really great success with Manitowoc on parts, service and technical support. The company is even supporting older cranes, such as the Manitowoc 4600 and Manitowoc 4100W RINGER. We look to continue getting that kind of support with the new products, too. We don’t want to buy something and not have Manitowoc Cranes’ support behind us.”




Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

VIDEO: Two Major Roadway Project Contracts Awarded by State Officials in West Virginia

VIDEO: First of Two Sections of NYC's $1.45B East Side Coastal Resiliency Project Is Complete

John Deere Construction Introduces Flexible Customer Training Options

INFRA Grant Moves Ohio's N. Coast Connector Project Steps Closer


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA