Crews Keep Busy on Infrastructure Projects Across Rhode Island

Wed November 20, 2019 - Northeast Edition #24
RIDOT


Rhode Island Department of Transportation (RIDOT) crews have been busy working on various projects across the state. Here is a pictorial roundup of some of these recent projects.

Workers are installing new catch basins and drainage pipes, and continue demolition of old Carolina Bridges components in Charlestown/Richmond.
Workers are installing new catch basins and drainage pipes, and continue demolition of old Carolina Bridges components in Charlestown/Richmond.  

Workers install drainage pipes, catch basins and electrical conduit.
Workers install drainage pipes, catch basins and electrical conduit.  

Crews install new curbing, perform drainage work and make electrical upgrades for LED lighting around the roundabouts on Diamond Hill Road, from Industrial Road to Bear Hill Road and Angell Road.
Crews install new curbing, perform drainage work and make electrical upgrades for LED lighting around the roundabouts on Diamond Hill Road, from Industrial Road to Bear Hill Road and Angell Road.  

RIDOT crews recently worked on replacing the Lafayette Road South bridge.
RIDOT crews recently worked on replacing the Lafayette Road South bridge.  

Crews were busy prepping parts of the old Baker Pines bridge in Richmond for concrete repair and replacement on Route 3 under I-95 and finishing median barrier work.
Crews were busy prepping parts of the old Baker Pines bridge in Richmond for concrete repair and replacement on Route 3 under I-95 and finishing median barrier work.  

Crews install guardrail and plant grass behind a barrier on Route 102.
Crews install guardrail and plant grass behind a barrier on Route 102.  

RIDOT crews are scheduled to relocate the temporary median barrier from the Cowesett Road overpass to Exit 11 in Warwick.
RIDOT crews are scheduled to relocate the temporary median barrier from the Cowesett Road overpass to Exit 11 in Warwick.  

Route 6/10 Interchange Reconstruction, Providence: crews continue building the retaining walls for the Route 10 North to Route 6 West flyover bridge approach, performing utility work on Westminster Street over Route 10, and forming and pouring the concrete bridge barriers on the Plainfield Street Bridge on Route 6 East.
Route 6/10 Interchange Reconstruction, Providence: crews continue building the retaining walls for the Route 10 North to Route 6 West flyover bridge approach, performing utility work on Westminster Street over Route 10, and forming and pouring the concrete bridge barriers on the Plainfield Street Bridge on Route 6 East.  




Today's top stories

Mississippi DOT's Road Work in Full Swing at 15 Sites in State's Western Counties

Liebherr Produces Its 10,000th XPower Wheel Loader

At Nearly 100 Years Old, Waterbury, Vt.'s Stowe Street Bridge in Need of Replacement

Intelligence in the Work Zone

ConExpo-Con/AGG, The Utility Expo Partner With American Foundation for Suicide Prevention

All Material Handling Celebrates More Than Two Decades of Customer-Focused Excellence

New Cat Single Life Cutting Edges Deliver High Wear Life, Simplified Maintenance

DEVELON Returns to Washington, D.C., for AEM Celebration of Construction on National Mall


 







39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019