Crews Work to Rebuild Sand Dunes After Hurricane

The plan calls for 60,000 cu. yds. of sand to be trucked in from the Little River area. The work should be finished by March 1.

Fri December 15, 2017 - National Edition
The Associated Press


“The dunes were largely destroyed and totaled by Hurricane Matthew. He dealt the death blow, but prior storms had eaten away at those dunes,” said Pat Dowling, a spokesman of the city of North Myrtle Beach.
“The dunes were largely destroyed and totaled by Hurricane Matthew. He dealt the death blow, but prior storms had eaten away at those dunes,” said Pat Dowling, a spokesman of the city of North Myrtle Beach.

NORTH MYRTLE BEACH, S.C. (AP) Work has started on rebuilding sand dunes at a South Carolina beach damaged by Hurricane Matthew last year.

Trucks filled with sand started rolling into North Myrtle Beach under the project expected to take about three months, The Sun News of Myrtle Beach reported.

“The dunes were largely destroyed and totaled by Hurricane Matthew. He dealt the death blow, but prior storms had eaten away at those dunes,” said Pat Dowling, a spokesman of the city of North Myrtle Beach.

The plan calls for 60,000 cu. yds. of sand to be trucked in from the Little River area. The work should be finished by March 1.

Between five and 15 dump trucks will work each day hauling sand, which will be bulldozed into place. Because of the small number of trucks being used in the effort, there are not expected to be any traffic impacts.

Parts of the beach will be closed temporarily during the work.

“As far as blocking beach lots, there won't be the degree that it was during renourishment,” Dowling said.

The Army Corps of Engineers conducted a nearly $11 million beach nourishment project in October.

The city is paying $616,000 to get the dunes rebuilt to protect ocean-front buildings from storm surges, Dowling said. The new dune berm will be about 7 ft. high and about 35 ft. wide.

There should be no problem with lights and night work, Dowling said.

“It's a probability there won't be a lot of night work, unless they get behind the eight-ball and they have to,' he said.




Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA