Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
The plan calls for 60,000 cu. yds. of sand to be trucked in from the Little River area. The work should be finished by March 1.
Fri December 15, 2017 - National Edition
NORTH MYRTLE BEACH, S.C. (AP) Work has started on rebuilding sand dunes at a South Carolina beach damaged by Hurricane Matthew last year.
Trucks filled with sand started rolling into North Myrtle Beach under the project expected to take about three months, The Sun News of Myrtle Beach reported.
“The dunes were largely destroyed and totaled by Hurricane Matthew. He dealt the death blow, but prior storms had eaten away at those dunes,” said Pat Dowling, a spokesman of the city of North Myrtle Beach.
The plan calls for 60,000 cu. yds. of sand to be trucked in from the Little River area. The work should be finished by March 1.
Between five and 15 dump trucks will work each day hauling sand, which will be bulldozed into place. Because of the small number of trucks being used in the effort, there are not expected to be any traffic impacts.
Parts of the beach will be closed temporarily during the work.
“As far as blocking beach lots, there won't be the degree that it was during renourishment,” Dowling said.
The Army Corps of Engineers conducted a nearly $11 million beach nourishment project in October.
The city is paying $616,000 to get the dunes rebuilt to protect ocean-front buildings from storm surges, Dowling said. The new dune berm will be about 7 ft. high and about 35 ft. wide.
There should be no problem with lights and night work, Dowling said.
“It's a probability there won't be a lot of night work, unless they get behind the eight-ball and they have to,' he said.