List Your Equipment For Free  /  Seller Login

Crews Work to Stabilize MD 135 After Rock Slide

The Maryland Department of Transportation’s State Highway Adminstration (SHA) is currently working to remedy a rock slide that occurred in western Maryland near the Allegany/Garrett County line in ear

Mon March 21, 2016 - Northeast Edition
Brenda Ruggiero


The SHA started a $2.7 million project to stabilize the rock face on Thursday, Jan. 28. The repair is expected to take up to 20 weeks, weather permitting.
The SHA started a $2.7 million project to stabilize the rock face on Thursday, Jan. 28. The repair is expected to take up to 20 weeks, weather permitting.
The SHA started a $2.7 million project to stabilize the rock face on Thursday, Jan. 28. The repair is expected to take up to 20 weeks, weather permitting.
 The Maryland Department of Transportation’s State Highway Adminstration (SHA) is currently working to remedy a rock slide that occurred in western Maryland near the Allegany/Garrett County line in early January.
 The process being used is called “rock bolting.” This is different from a technique that was used in spring 2015 for a slide in Westernport called “soil nailing.”
 Rock bolting involves removing any loose or unstable rock from the mountainside, a process known as scaling.
 A containment area made of concrete barrier was set up on westbound MD 135 to catch any rocks that may slide. SHA also placed a protection mat on WB MD 135 to protect the road surface from damage. 
 Although the repair will stabilize the mountain’s rock face, the repair is not considered permanent, and engineering geologists are developing a long-term solution to stabilize the mountainside.

The Maryland Department of Transportation's State Highway Adminstration (SHA) is currently working to remedy a rock slide that occurred in western Maryland near the Allegany/Garrett County line in early January.

According to Charlie Gischlar, public information officer of the SHA, the Jan. 2 slide involved a section of the rock face on Bloomington Mountain adjacent to MD 135 (Bloomington Road) near Upper Savage River Road.

As a result, large boulders fell onto MD 135. Because the mountainside was unstable and a risk for further rock slides existed, the SHA closed a westbound lane on MD 135 and traffic was alternated using the eastbound lane guided by a temporary traffic signal.

A containment area made of concrete barrier was set up on westbound MD 135 to catch any rocks that may slide. SHA also placed a protection mat on WB MD 135 to protect the road surface from damage.

The SHA started a $2.7 million project to stabilize the rock face on Thursday, Jan. 28. The repair is expected to take up to 20 weeks, weather permitting.

“Based on data collected from SHA's engineering geologists and other experts in this field, the rock face of the mountainside is highly unstable and emergency measures are required to prevent further rock slides,” said Anthony Crawford, SHA district engineer. “Safety is our number-one priority and we are taking measures to lessen the chances of another rock slide.”

The process being used is called “rock bolting.” This is different from a technique that was used in spring 2015 for a slide in Westernport called “soil nailing.” The mountain along MD 135 is comprised mainly of rock rather than soil. Although the repair will stabilize the mountain's rock face, the repair is not considered permanent, and engineering geologists are developing a long-term solution to stabilize the mountainside.

According to Gischlar, rock bolting involves removing any loose or unstable rock from the mountainside, a process known as scaling. Crews will drill to insert steel rods, such as rebar, into the affected region. The area is then draped with wire meshing and bolted down. Next, experts will apply shotcrete (a spray form of concrete) to anchor, or bolt, the rock face to the mountainside, stabilizing it from further slides.

SHA established a containment area with concrete barrier to catch any unstable rocks and to protect motorists, as well as the pavement on MD 135. Traffic is currently being controlled through this area by a temporary traffic signal. Motorists are told that they should plan an extra 15 minutes of travel time.

SHA's contractors for the repair are KCI Technologies of Sparks; rock stabilization experts Merco Inc. of Lebanon, N.J.; Belt Paving of Cumberland; and East Coast Bridge of Nitro, W.Va.

Major equipment used in the project includes excavators, grade-alls, graders, jackhammers, heavy dump trucks; rubber blast matting (used to protect the pavement on WB MD 135); manlifts; and drilling rigs.

Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA