Crews Working to Replace Post Office Canyon Bridge

Wed August 11, 2021 - West Edition #17
Arizona Department of Transportation


Officials from the Arizona Department of Transportation are in the process of replacing the current bridge deck with reinforced 8-in. thick concrete and to replace deck drains, deck joints and bridge barrier transitions, among a host of other improvements.
Officials from the Arizona Department of Transportation are in the process of replacing the current bridge deck with reinforced 8-in. thick concrete and to replace deck drains, deck joints and bridge barrier transitions, among a host of other improvements.

On State Route 73 in the Fort Apache Reservation, alongside the North Fork White River, ADOT is in the process of replacing an old bridge deck.

By the standards of the region, the Post Office Canyon Bridge, built in 1968, isn't quite a senior citizen at 53 years. But if it could talk, it would tell you the top song that year was "Hey Jude," by The Beatles, minimum wage was $1.60 an hour and a Big Mac was 49 cents.

The single span, steel girder bridge rises more than 1 mi. above Post Office Canyon at 5,912 ft.

By ADOT engineering measurements, the bridge is safe, but because ADOT specifications and standards have evolved, it's time to replace the current deck with reinforced concrete 8-in. thick and to replace deck drains, deck joints and bridge barrier transitions, among a host of other improvements. The project will reconstruct and significantly extend the life of the bridge.

The project is in full swing and crews are demolishing and replacing the old decks.

When residents cross the newly refurbished span, they now know they will be 1 mi. high, on the White River Scenic Road and a Rural Major Collector Road — and on a passage whose history began in the 1800s.

According to the project website, the following restrictions are in place from 6 a.m. to 6 p.m. seven days a week through September:

  • SR 73 is narrowed to one lane of alternating north- and southbound travel near the Post Office Canyon Bridge (mileposts 348-349).
  • A temporary traffic signal helps drivers travel through the construction area.
  • 12-ft. vehicle width restriction in the work zone.
  • Reduced speed limit in the work zone.
Bridge Background

It is located nearly half-way down an 11-mi. stretch of SR 73, between Indian Pine near State Route 260 and the Alchesay National Fish Hatchery, that was designated in 1993 as the White River Scenic Road. The route is a U-shaped loop, about 40-mil. long with one end on U.S. 60 north of Carrizo and the other near Indian Pine and State Route 260.

According to the state-published Arizona Memory Project, SR 73 started out as little more than a foot trail:

"With the establishment of a military camp in 1870 that would be renamed Fort Apache in 1879, the development of rough trails into passable packed-earth roads became necessary. In 1929, the old trail that would become SR 73 allowed horse-riding soldiers and mule-drawn freight wagons to reach the remote garrison from both the north and the south."

The Post Office Canyon Bridge was named after the canyon it crosses, the Post Office Canyon, said Navaphan Viboolmate, the ADOT engineer who is overseeing the deck replacement, of ADOT's Bridge Design Section.

Before 1968, an earlier bridge across the canyon had a deck built from timber, Viboolmate said. It was torn down to make way for the current bridge.

"It was an open design," he said. "Driving on it you could see side rails and cross rails."

Located in Navajo County between mileposts 348 and 349, the bridge sits on a section of SR 73 that is classified as a Rural Major Collector Road.

"It connects to local communities, including Fort Apache, Whiteriver and Cedar Creek," Viboolmate said. "It connects State Route 260 and U.S. 60."




Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA