List Your Equipment For Free  /  Seller Login

Crossing the 'Yough' in Ohiopyle, Pa.

Thu July 16, 2020 - Northeast Edition #15
Brenda Ruggiero – CEG Correspondent


Prime contractor Plum Contracting Inc. used a Terex Bid-Well finishing machine. The challenge was to finish the concrete deck surface to the specified longitudinal and transverse grades. Once set up to do so, the Bid-Well automatically finished the deck surface to the desired grades.
Prime contractor Plum Contracting Inc. used a Terex Bid-Well finishing machine. The challenge was to finish the concrete deck surface to the specified longitudinal and transverse grades. Once set up to do so, the Bid-Well automatically finished the deck surface to the desired grades.
Prime contractor Plum Contracting Inc. used a Terex Bid-Well finishing machine. The challenge was to finish the concrete deck surface to the specified longitudinal and transverse grades. Once set up to do so, the Bid-Well automatically finished the deck surface to the desired grades. Pennhall Company “grooves” the deck. The bridge approach slabs also are “grooved” this way. Technically, the process is referred to as “Texturing Bridge Deck Concrete Wearing Surface.” Plum Contracting uses Cat and Hitachi hydraulic excavators to remove rock, which made room for new Upper Falls parking lot. Oglesby Construction Inc. use a slipform curb machine on the project. The Ohiopyle Multimodal Gateway Project will be finishing up shortly in Ohiopyle Borough, Fayette County, Pa. The Youghiogheny River Gorge or “Yough” provides whitewater boating opportunities as well as scenery. The challenge was how to get concrete from the ground into the bridge deck without interfering with traffic. Howard Concrete Pumping Company Inc. provided the means to do so. The challenge was how to get concrete from the ground into the bridge deck without interfering with traffic. Howard Concrete Pumping Company Inc. provided the means to do so. Concrete work is performed on a bridge along Route 381. The subcontractor saws through the existing bridge barrier in a vertical position. The nickname for the saw being using is a “rope saw” with diamond tips on the belt that cuts through the concrete. The challenge for the contractor is figuring out how to remove more than 300 ft. of barrier the quickest way possible due to time-constraints of the schedule. The solution was to cut up the barrier in pieces, so it wasn’t too heavy to lift.

The Ohiopyle Multimodal Gateway Project will be finishing up shortly in Ohiopyle Borough, Fayette County, Pa.

According to Jay Ofsanik, acting press officer of the Pennsylvania Department of Transportation (PennDOT) District 12, this project is to improve the Route 381 (Main Street) corridor by minimizing conflict points to better serve all users and all modes of travel.

"This project will focus on improvements to better serve all members of the traveling public and result in a cohesive multimodal corridor," he said.

Plum Contracting Inc. is the prime contractor on the $12.4 million project, with Brian Miller in charge.

"The project was different in that the work was restricted to the off-seasons between Labor Day and Memorial Day," Ofsanik said. "No work was conducted during the summer months in order to minimize the effect on summer tourism."

He noted that Ohiopyle is one of the most popular state park destinations in Pennsylvania and every effort was made to minimize any negative effects.

Ohiopyle State Park encompasses approximately 20,500 acres of rugged natural beauty and serves as the gateway to the Laurel Highlands. Millions of visitors reportedly pass through annually.

The Youghiogheny River Gorge or "Yough" provides whitewater boating opportunities as well as scenery.

Construction began in the fall of 2018. Due to the unexpected statewide shutdown of projects, the expected completion date became July 3, with final work being done by September.

The highway and pedestrian construction work at Ohiopyle was suspended on March 17 due to the COVID-19 outbreak and work did not resume until April 7. As a result, the construction team lost 21 days in the construction schedule.

Work on the project was in accordance with Centers for Disease Control and State Department of Health guidance, as well as a project-specific COVID-19 safety plan, which includes protocols for social distancing, use of face coverings, personal and jobsite cleaning protocols, management of entries to the job site and relevant training.

PennDOT's District 12 executive is Joseph Szczur. The project manager is William Beaumariage and the PennDOT inspector is Chris Bardi, who serves as the onsite manager.

The contract calls for the realignment of Sugarloaf Road with the lower (falls) parking area, construction of a new upper parking area, construction of a pedestrian tunnel under Route 381 connecting the upper parking area with the park office and river access for boaters, the widening of Route 381 to include a bike lane and rehabilitation of the bridge that carries Route 381 over the Yough River.

"There was 62,300 cubic yards of material that was excavated, of which 58,500 cubic yards of it had to be wasted," Ofsanik said. "four thousand cubic yards of material was then placed as completed embankment."

He reported that another 6,300 cu. yds. of various sizes of rock was placed in and around the job site, either in fills, drainage channels or the rock buttress that was built to prevent the hillside from sliding once it was excavated to make room for the new alignment of Sugarloaf Road.

Bardi reported that the deck and bridge approach slabs were "grooved."

"Technically, it's referred to as ‘texturing bridge deck concrete wearing surface' per Special Provision-language," he said.

This work was done by subcontractor Pennhall Company.

Subcontractor Pitt Industrial sawed through the existing bridge barrier in a vertical position.

"The nickname for the saw they're using is called a ‘rope saw.'" Bardi said. "There's diamond tips on the ‘belt' that cuts through the concrete. The challenge here for the contractor is figuring out how to remove over 300 feet of barrier in the quickest way possible due to time-constraints of the schedule. The solution is to cut up the barrier in ‘pieces' so they aren't too heavy to lift."

Subcontractor Ogelsby Construction Inc. of Ohio used a slipform curb machine on the project.

All Crane Rental of Pa. used several cranes to set the new bridge girders.

Howard Concrete Pumping Company Inc. helped to overcome another challenge, according to Bardi, which was how to get concrete from the ground into the bridge deck without interfering with traffic. They used a concrete pump truck and a concrete delivery truck to do so.

Folino Construction Inc. placed pervious asphalt in the Upper Falls Parking Lot.

"The challenge was to try to pave the two paving courses during the same shift," Bardi said. "Folino decided to perform this work during the middle of the night in hopes the first layer of asphalt would cool enough to permit the second layer to be placed upon it soon thereafter."

Subcontractor Green Acres Contracting Company Inc. hydro-seeded the project.

A Terex Bid-Well finishing machine was used by the prime contractor Plum Contracting Inc.

"The challenge is to finish the concrete deck surface to the specified longitudinal and transverse grades," Bardi said. "Once set up to do so, the Bidwell automatically finishes the deck surface to the desired grades.

Subcontractor Beeghly Tree LLC used a bucket truck to remove the larger trees in the area.

Project specifications also stated that snow removal within project limits had to be performed as part of contract work. This was done by Plum Contracting with a snowplow kept on site.

Plum Contracting also used two hydraulic excavators to remove rock to make room for the new Upper Falls Parking Lot. CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA