List Your Equipment For Free  /  Seller Login

DelDOT Constructs State's First Bulb-Tee Girder Bridge

Mon January 22, 2018 - Northeast Edition #2
Brenda Ruggiero


The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13.
The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13.
The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13. The first spliced prestressed bulb-tee girder bridge in Delaware is currently being built near Wilmington under the direction of the Delaware Department of Transportation (DelDOT). The project creates a new multi-modal crossing of the Christina River to add another access point to Wilmington Riverfront attractions. It also will improve access to U.S. 13, I-495, and I-95. The project began in May 2017, and will continue through the spring of 2019. According to Jason N. Hastings, M.C.E., P.E., state bridge engineer of DelDOT, it is currently on schedule. The contract was awarded to RE Pierson Construction Company of Woodstown, N.J., with Nick Hetrick in charge. The bridge will include two 12-ft. travel lanes and shoulders, as well as a 14-ft. wide bicycle/pedestrian path. The path will connect to the Riverfront walkway and other bicycle/pedestrian facilities in the area. The aesthetic nature of the bridge was another issue. According to Jason N. Hastings, M.C.E., P.E., state bridge engineer of DelDOT, it is currently on schedule.

The first spliced prestressed bulb-tee girder bridge in Delaware is currently being built near Wilmington under the direction of the Delaware Department of Transportation (DelDOT).

The project creates a new multi-modal crossing of the Christina River to add another access point to Wilmington Riverfront attractions. It also will improve access to U.S. 13, I-495, and I-95.

The project began in May 2017, and will continue through the spring of 2019. According to Jason N. Hastings, M.C.E., P.E., state bridge engineer of DelDOT, it is currently on schedule.

The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13. The contract was awarded to RE Pierson Construction Company of Woodstown, N.J., with Nick Hetrick in charge.

The bridge will include two 12-ft. travel lanes and shoulders, as well as a 14-ft. wide bicycle/pedestrian path. The path is will connect to the Riverfront walkway and other bicycle/pedestrian facilities in the area.

“There are several challenges associated with the project,” Hastings said. “In an effort to reduce the contract costs to the department, RE Pierson worked with Hardesty and Hanover and with the assistance of DelDOT and RK&K to redesign the foundations to 30 in. and 24 in. prestressed concrete pile (from drilled shafts). Driving pile of that dimension and length (up to 100 ft.) requires specialized equipment, which R.E.P. has experience with.”

Another challenge noted by Hastings was the erection and setting of the spliced prestressed bulb-tee girders, which required additional supports, detailed erection design and plans, splicing design, and post tensioning.

“The existing ground conditions required the implementation of several different ground improvement and mitigation techniques,” Hastings said. “These included a sizable surcharge area — quarantined for 150 days; the use of lightweight foamed concrete as abutment backfill; the use of expanded polystyrene as an embankment material; and the installation of controlled modulus columns — rigid inclusions to support the weight of one of the approach embankments.”

The aesthetic nature of the bridge was another issue noted by Hastings. This includes the extensive use of Formliner concrete on all of the exposed bridge elements. It will be stained to look like natural rock. There also is an extensive decorative lighting package.

“The project is located on a brownfield site, where the challenges of working with and managing potentially contaminated soil, debris and groundwater takes extensive daily coordination with various stakeholders,” Hastings noted. “The project's location is adjacent to a highly-populated urban business district that requires coordination and cooperation from all stakeholders to ensure that construction does not disrupt or detract from their operations.”

Hastings reported that the project includes 12,100 cu. yds. of excavation, 22,000 cu. yds. of borrow import for the embankment, 3,500 cu. yds. of concrete, and 800,000 lbs. of rebar.

In addition, there are 69 – 24 in. prestressed concrete piles averaging 80 ft. in length and 52 – 30 in. prestressed concrete piles averaging 100 ft. in length.

Also included are 1,300 cu. yds. of expanded polystyrene embankment; 1,900 sq. yds. of CMC rigid inclusion ground improvements; 340 linear ft. of MSE wall; and 8,000 sq. ft. of Formliner.

CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA