List Your Equipment For Free  /  Seller Login

DelDOT's $400M U.S. 301 Project to Ease Congestion

On the project website, DelDOT states that the new U.S. 301 will remove the “neck in the bottle” of the regional highway network.

Tue November 01, 2016 - Northeast Edition #22
Brenda Ruggiero


DelDOT photo. DelDOT expects to have the roadway open by December of 2018 to start collecting tolls.
DelDOT photo. DelDOT expects to have the roadway open by December of 2018 to start collecting tolls.
DelDOT photo. DelDOT expects to have the roadway open by December of 2018 to start collecting tolls.
 DelDOT photo. The new U.S. 301 will improve safety, manage truck traffic and reduce congestion. 
 DelDOT photo. On the project website, DelDOT states that the new U.S. 301 will remove the “neck in the bottle” of the regional highway network.
 DelDOT photo. The new U.S. 301 will convert existing U.S. 301 to a local roadway that is key to the local roadway network and approved and proposed development in this designated Delaware growth area.
 DelDOT photo. The biggest challenge with this project involves dirt movement.
 DelDOT photo. The full scope of project includes building a toll road with bridges and a four-lane concrete highway (two lanes in each direction) with interchanges.
 DelDOT photo. The full dollar amount for the entire contract is just under $400 million.
 DelDOT photo. The project is divided into seven contracts that will be built concurrently. It is anticipated to take three years to complete all the contracts and open the road to traffic.
 DelDOT photo. Work on the project began on Dec. 24, 2015. Since then, multiple contracts were put out for bids.

A large road project is progressing as planned in southern New Castle County, Delaware. The new U.S. 301 will reportedly improve safety, manage truck traffic and reduce congestion; support approved and proposed economic development in a key Delaware growth area; enhance the region's ability to compete for economic development; create needed jobs; improve local access to the Northeast Corridor Rail (Amtrak), commuter rail (SEPTA) and bus (DART) services; improve livability in the region; and reduce fuel consumption and greenhouse gas emissions.

On the project website, DelDOT states that the new U.S. 301 will remove the "neck in the bottle" of the regional highway network, i.e. existing U.S. 301 from the Maryland/Delaware state line to I-95 and its two-lane sections (one lane in each direction); 29 at-grade intersections (18 signalized); and numerous driveways with direct access to existing U.S. 301. The new U.S. 301 will convert existing U.S. 301 to a local roadway that is key to the local roadway network and approved and proposed development in this designated Delaware growth area.

The project is divided into seven contracts that will be built concurrently. It is anticipated to take three years to complete all the contracts and open the road to traffic.

"We have seven mainline contract projects, and then we also have land clearing contracts that were started very early on in the project," explained Javier Torrijos, assistant director of construction. "We had to get in there and do the clearing right away, so we put together advanced clearing contracts so there would not be an issue from an endangered species requirement for the northern long eared bat."

Work on the project began on Dec. 24, 2015. Since then, multiple contracts were put out for bids, and six of the seven mainline contracts have been awarded. DelDOT expects to have the roadway open by December of 2018 to start collecting tolls.

According to Torrijos, the full dollar amount for the entire contract is just under $400 million.

This includes the construction cost, the contingency, the inspection cost, a section-designed consultant report, utilities costs, traffic costs, construction engineering, and other miscellaneous costs. An additional amount is budgeted for potential future projects, such as landscaping, a park-and-ride, and possibly a future maintenance facility.

Contracts are as follows:

• U.S. Route 301 and SR 1 Interchange — A 782-calendar-day project to construct the interchange north of the Biddles Corner Toll Plaza. Tutor Perini Corporation of New Rochelle, N.Y, was the successful bidder with a proposal of $35,388,000. The project manager is Dan Myers.

• U.S. Route 301, Route 896 to State Route 1 — A 1,230-calendar-day contract awarded to Tutor Perini Corporation, with the successful bid of $69,842,468.80. The project manager is Dan Myers.

• U.S. Route 301, Levels Road to Summit Bridge Road — A 1,230-calendar-day contract awarded to Allan Meyers Contractors of Fallston, Md., with the successful bid of $93,777,777. The project manager is Chris McKew.

• U.S. Route 301, Maryland State Line to Levels Road — A 850-calendar-day contract awarded to Greggo and Ferrara Inc. of New Castle, Del., with the successful bid of $46,054,715.79. The general superintendent is Samuel Whitaker

• U.S. Route 301, Norfolk Southern Railroad to Route 896 — An 840-calendar- day awarded to Richard E. Pierson Construction of Woodstown, N.J., with the successful bid of $21,315,701.98. The project manager is Dan Orr.

• U.S. Route 13 and Port Penn Road providing toll-free access to State Route 1 — Of the four submissions, Diamond Materials of Newport, Del., was the successful bidder with a proposal of $11,142,890.35. Notice to proceed was given on June 13.

• The final contract has not yet been advertised, and is expected to go out for bids in the fall.

The full scope of project includes building a toll road with bridges and a four-lane concrete highway (two lanes in each direction) with interchanges.

According to Torrijos, the biggest challenge with this project involves dirt movement.

"We've got about 7 million yards of dirt that we have to move in 750 calendar days, plus we have 40 structures that we have to construct and the mainline has to be open in 1,065 calendar days to collect tolls, which takes us to December of 2018 — a lot of work in a very short period of time," he said. "When you've got to move 11 million yards of dirt and build 40 structures — culverts and bridges — that's a lot of work. So that's the biggest challenge is coming in on time and on budget. We have borrowed money from the federal government, and we have also sold bonds to pay for this project, so it's imperative that we start collecting tolls at the end of 2018."

Besides the timeline, the project has some aspects that set it apart from others.

"I think what makes it unique is that basically you have a bunch of contractors playing in a big old sandbox here — you've got six contractors that have been awarded contracts, and basically they all have to play nicely in the sandbox," Torrijas said. "Some of them are sharing the same pit where they're basically excavating a big hole that's down at the levels borrow pit. You have two contractors in there basically digging out of the same hole, and there are milestones…there are liquidated damages if they don't complete on time…so basically it's a lot of work in a very short period of time with five different contractors building six contracts currently — eventually there will be seven contracts, but the last one hasn't gone out yet."

Torrijas described the overall project as "very intense because of the complicated schedule.

"We have a very aggressive schedule," he explained. "It's an easy project to build because it's mostly away from traffic — you're basically out in the country away from traffic — there are some tie-ins at the north end and the south end, and there are some crossings of existing roadways to maintain traffic, but for the most part, it's basically off alignment, and it's a pretty easy project to build — there's just a lot of it in a very short period of time.

"The other thing is there are communities that surround us and there are also schools adjacent to us, so we have to be very mindful of working with these communities so we're not disruptive at night or during the daytime when it comes to traffic, construction noise at night, and things like that."

Torrijas stated that the project has been on the books for quite some time and there a lot of commitments were made.

"We had a record of decision that was submitted to the regulatory agencies and also FHWA — commitments that were made from an environmental standpoint, and to the communities, so we have worked through all of that," he said. "We are extremely cognizant of all the requirements that were in the record of decision and making sure that we meet those conditions."

Major subcontractors for the project include Crawford Trucking Co. LLC; Curbs Etc. Inc.; Eastern Steel Constructors Inc.; Erosion Control & Landscape; Seagull Fence and Concrete; Diamond Materials Inc.; Protection Services Inc.; Mattiola Services LLC; Talley Brothers Inc.; Janette Redrow LTD.; Wilton Corporation; Erosion Control & Landscape; B. W. Electric Inc., Callahan Paving Products Inc.; Crawford Trucking Co.; M & M Construction Inc.; Traffic & Safety Signs Inc.; Vega Solutions Inc.; Environmental Services LLC; Strobert Tree Services Inc.; Zone Striping Inc; and Ram-T Corporation.


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

Huntsville, Ala.'s Sandra Moon Community Complex to Begin Final, $31.3M Phase of Work

Unique Skid Steer Tire Increases Snow Clearing Performance, Safety

New Deutz Power Center Mid-Atlantic Opens in Ashland, Va.

2025 CGA Conference & Expo Opens Registration On Nov. 6


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA