List Your Equipment For Free  /  Seller Login

Despite COVID-19, Construction Continues on Milford Bridge

Thu April 23, 2020 - Northeast Edition #9
Ken Liebeskind -CEG Correspondent


New England Road of Clinton, Conn., is the general contractor and won the job with a low bid of $6,848,318.
New England Road of Clinton, Conn., is the general contractor and won the job with a low bid of $6,848,318.
New England Road of Clinton, Conn., is the general contractor and won the job with a low bid of $6,848,318. The construction of a replacement bridge that carries Wheelers Farms Road over State Road 796, a short highway that connects the Merritt Parkway and Wilbur Cross Parkway to I-95 and the Boston Post Road in Milford, Conn., resumed in early April. John Pryor, a son of one of the owners of New England Road of Clinton, Conn., is all smiles on the job site. The job has continued during the COVID-19 pandemic with construction jobs not stopped in Connecticut. Though Gov. Ned Lamont has established business restrictions during the pandemic, he has spared the construction industry, with limitations only placed on indoor construction jobs. The existing bridge was built in 1941 and is being replaced because it is structurally deficient and functionally obsolete, according to Kevin Nursick, a CTDOT spokesperson.

The construction of a replacement bridge that carries Wheelers Farms Road over State Road 796, a short highway that connects the Merritt Parkway and Wilbur Cross Parkway to I-95 and the Boston Post Road in Milford, Conn., resumed in early April with completion projected for the fall of 2021.

The job has continued during the COVID-19 pandemic with construction jobs not stopped in Connecticut. Though Gov. Ned Lamont has established business restrictions during the pandemic, he has spared the construction industry, with limitations only placed on indoor construction jobs.

"We're keeping our big, outdoor, public construction projects going, roads, bridges, schools — where it's easier to keep social distancing," Lamont said.

The new structure will be a two-span continuous multi-girder bridge resting on concrete abutments and a center pier. The profile of Wheeler's Farm Road will be raised to increase the minimum vertical clearance over SR 796 to the required 15 ft. The new spans will be lengthened to allow a 6.5-ft. inside shoulder, three 12-ft. travel lanes and a 10 ft. outside shoulder in each direction on SR 796.

New England Road of Clinton, Conn., is the general contractor and won the job with a low bid of $6,848,318, according to Alan Neri, an owner of the company.

The existing bridge was built in 1941 and is being replaced because it is structurally deficient and functionally obsolete, according to Kevin Nursick, a CTDOT spokesperson. "The structural deficiency is due to the deteriorated condition of the deck, superstructure and substructure. All three are rated poor. The deck has hollow area with spalling and the steel girder webs and bearings exhibit section loss and rust. The abutments exhibit numerous spalls and cracking and the steel pier girder has large areas of rust and section loss. It is functionally obsolete due to a substandard roadway width and minimum vertical clearance of 13.8 feet."

The job began a year ago but was held up by utility issues.

"The utility coordination shouldn't have taken as long as it did, but we're at the mercy of the utility companies to get coordinated," Neri said. "Gas, telephone and electric, there were a lot of facilities to relocate. Overhead electric, telephone and cable lines were relocated to clear the area for Stage One construction. In addition, an underground gas main was modified and underground communication lines were exposed and are to be protected and supported in place while the substructure and bridge are constructed around them. All this has delayed the project approximately one construction season."

With the utility issues out of the way, the company began construction of the bridge, which will be completed in three stages: demolition and construction of the East and West sections of the bridge and the addition of acceleration and deceleration lanes.

"We started the job this winter with the demolition of the Stage One section of the bridge," Neri said. "We removed the concrete deck over the connector using shielding to keep at least one lane of traffic open in each direction. Once the deck was removed, we removed the structural steel girders, cutting them at the center and picking them off with a crane. The existing steel pier was cut and removed in sections. The earth support around the excavation for the Stage One section of the pier has been installed and the pier footing section has been poured. Soon, we will pour the concrete for the pier and start reconstruction of the Stage One new abutment sections."

The existing bridge is a 100-ft. span and the new bridge will be a 150-ft. span, with lane widening occurring at the end of the job. "The last stage is to widen the connector," Remi said.

When asked why the bridge had to be expanded, Neri said, "The road is getting wider down below so the abutments needed to be built further from the edge of the road."

The company is using a Grove rough-terrain crane on the job, along with a Caterpillar wheeled excavator and Genie and JLG lifts.

New England Road will work with subcontractors on the job, including Kelly Steel of Hartford, Conn., that will do the steel erection; National Shoring of Waterford, Conn.; and Advance Resources, also of Waterford, that will do the paving and Total Fence of New Haven, Conn., that will construct the guardrails.

The 2019 ADT for Wheeler's Farm Road is 8064 vehicles per day, while the ADT for SR 796 is approximately 60,000 vehicles per day, according to CTDOT figures. CEG




Today's top stories

Pacific Coast Highway Drainage Infrastructure, Bridge Construction Proceed

Explore St. Louis: Gateway to Experiences at World of Asphalt 2025

AUSA Unveils Its Next-Generation of Compact Dumpers

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Werk-Brau to Host 2nd Annual Women In Construction Event

SpaceFactory to Build HQ in Huntsville; State Grant Boosts Etowah County's NEAR Megasite

HIPOWER HS Stationary Product Line


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA