List Your Equipment For Free  /  Seller Login

Dual Bridge Repair in Dayton

Tue May 25, 2021 - Midwest Edition #11
Lori Lovely – CEG Correspondent


The project encompasses repairing the two bridges on I-75. Interstate 75 is a major north-south interstate highway bisecting the country from southern Florida for 1,786.47 mi. up to the northeastern point on the Upper Peninsula of Michigan, making it one of the longest in the United States, as it passes through six states.
The project encompasses repairing the two bridges on I-75. Interstate 75 is a major north-south interstate highway bisecting the country from southern Florida for 1,786.47 mi. up to the northeastern point on the Upper Peninsula of Michigan, making it one of the longest in the United States, as it passes through six states.
The project encompasses repairing the two bridges on I-75. Interstate 75 is a major north-south interstate highway bisecting the country from southern Florida for 1,786.47 mi. up to the northeastern point on the Upper Peninsula of Michigan, making it one of the longest in the United States, as it passes through six states. 
 To complete the work, 1.4 million lbs. of reinforcing steel; 58,712 sq. ft. of structural steel painting; 6,960 cu. yds. of asphalt; and 6,300 cu. yds. of concrete will be used.
 When the Ohio Department of Transportation (ODOT) conducted routine inspections of the bridge decks and surface of Interstate 75 over Edwin C. Moses Boulevard and Carillon Boulevard near the Great Miami River in Dayton, Ohio, they concluded that the bridge decks built in 1963 had reached the end of their useful design life.  “The project sold in July 2020 for approximately $18.8 million,” said Tiffany Oliphant, ODOT District 7 public information officer. Work began a quick two months later. The project’s anticipated completion date is sometime in fall 2022.
 An average of 20 workers from Ruhlin Company as well as subs from John R. Jurgensen Company, a Cincinnati-based company providing asphalt pavement and aggregates; KLE Construction Company, a heavy civil contractor with headquarters in North Dakota; and 360 Construction Company Inc., a Brunswick, Ohio, company known for bridge restoration, industrial painting and sandblasting, have been working a 4 by 10 schedule (four 10-hour days)
 “Excavation is being performed with a Cat 336 excavator,” said Tiffany Oliphant, ODOT District 7 public information officer, estimating that approximately 2,000 cu. yds. of material will be moved.
 To update the bridges, ODOT awarded an $18.8 million contract to the Ruhlin Company, an employee-owned general contractor based in Sharon Center, Ohio. 
 Construction on the interstate started in 1957, but the bridges in Dayton were built in the early 1960s. Bridge work includes replacing bridge decks, removing hinge joints and removing the continuous U-turn lane from the Edwin C. Moses Boulevard interchange. In addition to the excavation, approximately 5,500 cu. yds. of material will be moved to construct a causeway into the Great Miami River to provide access for equipment.
 Two Cat 336 excavators; a Komatsu PC 228; a Link-Belt 138 lattice boom crawler crane; a Grove RT-760E crane; a Komatsu W380 loader; and a Cat D4 dozer are being used on the project.

Nothing lasts forever. When the Ohio Department of Transportation (ODOT) conducted routine inspections of the bridge decks and surface of Interstate 75 over Edwin C. Moses Boulevard and Carillon Boulevard near the Great Miami River in Dayton, Ohio, they concluded that the bridge decks built in 1963 had reached the end of their useful design life. ODOT rated them "poor."

To bring them up to date, ODOT awarded an $18.8 million contract to the Ruhlin Company, an employee-owned general contractor based in Sharon Center, Ohio. Founded by John G. Ruhlin in 1915, the company served as general contractor in the commercial and industrial markets in northeastern Ohio before expanding in 1955 to the civil market, where work included bridge and road construction and water and sewer treatment facilities. A structural division was added in 2006 to complement its heavy civil division.

"The project sold in July 2020 for approximately $18.8 million," said Tiffany Oliphant, ODOT District 7 public information officer. Work began a quick two months later. The project's anticipated completion date is sometime in fall 2022.

Doin' the Dual

The project encompasses repairing the two bridges on I-75. Interstate 75 is a major north-south interstate highway bisecting the country from southern Florida for 1,786.47 mi. up to the northeastern point on the Upper Peninsula of Michigan, making it one of the longest in the United States, as it passes through six states. Construction on it started in 1957, but the bridges in Dayton were built in the early 1960s.

Bridge work includes replacing bridge decks, removing hinge joints and removing the continuous U-turn lane from the Edwin C. Moses Boulevard interchange.

"The U-turn was installed to facilitate the modernization of I-75 projects and the U.S. 35/I-75 interchange projects to the north," Oliphant explained.

Both are complete, except for the last phase of U.S. 35/I-75 Interchange. Since the projects it was intended to assist are complete and because reconstruction of I-75 over Edwin C Moses structure will conflict with the U-turn, the U-turn lane will be taken out.

From Oct. 4 to 15, 2021, the GC shifted three lanes of I-75 northbound to the right of the interstate between Albany Street and S.R. 741.

"They also shifted the far-left lane of I-75 southbound [contraflow] onto I-75 northbound between Stewart Street and S.R. 741 [Springboro Pike]," Oliphant said.

There are two 10-ft. through-lanes on I-75 southbound along the median wall. The Edwin C. Moses Boulevard entrance ramp to I-75 southbound is closed from Oct. 16, 2020, through Oct. 15, 2021.

A detour for I-75 southbound traffic at Edwin C. Moses ramp closure sends motorists on Edwin C. Moses Boulevard to Dryden Road and then to I-75 southbound.

Traffic pattern shifts, ramp closures and lane restrictions in each direction of I-75, as well as the resulting delays, are expected to last for the duration of the project. Lane changes are expected to end this year.

Oliphant said, "Early in the project, Ruhlin and ODOT hosted a meeting with community members, including local towing companies, hospitals, Dayton Public Schools, the University of Dayton and Montgomery County Sherriff's Department, to explain how the project would impact traffic and provide time frames for the various phases of work."

Site Prep, Specs, Special Access

According to Oliphant, the majority of the excavation for this project is required at both bridge abutments.

"Excavation is being performed with a Cat 336 excavator," she said, estimating that approximately 2,000 cu. yds. of material will be moved.

In addition to the excavation, approximately 5,500 cu. yds. of material will be moved to construct a causeway into the Great Miami River to provide access for equipment.

"One of the unique aspects of this project is replacing the hinge joints on the bridge spanning over the Great Miami River," said Zachary Holowecky of Ruhlin Company. In order to access these joints for removal, a causeway was built out into the river to provide a working surface for the crane to remove the hinge joints and install new girders. The causeway was built using the concrete deck slabs from the demolition of the bridge.

An average of 20 workers from Ruhlin Company as well as subs from John R. Jurgensen Company, a Cincinnati-based company providing asphalt pavement and aggregates; KLE Construction Company, a heavy civil contractor with headquarters in North Dakota; and 360 Construction Company Inc., a Brunswick, Ohio, company known for bridge restoration, industrial painting and sandblasting, have been working a 4 by 10 schedule (four 10-hour days), using two Cat 336 excavators; a Komatsu PC 228; a Link-Belt 138 lattice boom crawler crane; a Grove RT-760E crane; a Komatsu W380 loader; and a Cat D4 dozer.

To complete the work, they'll use 1.4 million lbs. of reinforcing steel; 58,712 sq. ft. of structural steel painting; 6,960 cu. yds. of asphalt; and 6,300 cu. yds. of concrete.

"The project is progressing smoothly as [better weather] is approaching," said Holowecky, who expects the project to finish on time. CEG


Lori Lovely

Lori Lovely is an award-winning journalist, editor and author of the children's book Isadora's Dance. She has worked for newspapers, magazines and niche publications, covering a wide-ranging list of topics that includes motor sports, construction, MSW, energy, environmental issues, water, animal rights and issues, history, Native American issues and people, real estate and home decor, farming and more. Her degrees in History taught this dedicated professional to research thoroughly and ask detailed questions in order to winnow interesting facts that convey the essence of the story. As a seasoned writer and compassionate storyteller, she accurately portrays the subject in a manner that entrances the reader.

When she's not working on assignment, Lori is tending to her historic Indiana farm, where she raises alpacas. An inveterate animal lover, this vegetarian enjoys spending time with her animals and working in her garden.


Read more from Lori Lovely here.





Today's top stories

Iconic Hotel Being Demolished to Make Way for Baseball Stadium

MD 4 Project to Add Diamond Interchange

Volvo Construction Equipment Showcases New Products at North American Volvo Days

VIDEO: Anniversary of Highway Workers' Memorial Renews Calls for Work Zone Safety

Yanmar Compact Equipment Introduces New Line of Branded Attachments for Compact Track Loaders

Caterpillar Introduces Dynamic Energy Transfer Solution for Battery, Diesel-Electric Mining Equipment

Five Finalists Compete for Grand Prize Makeover in Bobcat Park and Rec Makeover Contest

VIDEO: Students From Washington, Ohio Earn Top Honors in Annual ARTBA Transportation Video Contest


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA