List Your Equipment For Free  /  Seller Login

Earthwork, Demo Proceed on IDOT's $48M I-55 Project

Tue December 22, 2020 - Midwest Edition #26
Irwin Rapoport – CEG Correspondent


Serious progress is occurring on the Illinois Department of Transportation’s (IDOT) $48,038,549.23 north contract for the I-55 Interchange at Weber Road project as Judlau Construction Inc. crews have put in a solid effort since spring 2019.
Serious progress is occurring on the Illinois Department of Transportation’s (IDOT) $48,038,549.23 north contract for the I-55 Interchange at Weber Road project as Judlau Construction Inc. crews have put in a solid effort since spring 2019.
Serious progress is occurring on the Illinois Department of Transportation’s (IDOT) $48,038,549.23 north contract for the I-55 Interchange at Weber Road project as Judlau Construction Inc. crews have put in a solid effort since spring 2019.
 For the pre-stage work, Judlau crews prepared the site for major construction via median removal; the installation of temporary pavement, traffic signals and storm sewer; and utility relocation.
 Judlau has quickly advanced from the pre-stage phase to the demolition of the eastbound bridge on the existing interchange, as well as engaging in earth work and other heavy construction activities, to meet the fall 2022 delivery date. The construction of the new roads and ramps for Stages 1 and 2 will be done in phases, along with traffic shifts. Crews have demolished eastbound interchange bridge and are working on new substructure. Prairie Material is providing some of the concrete being poured for the project.

Serious progress is occurring on the Illinois Department of Transportation's (IDOT) $48,038,549.23 north contract for the I-55 Interchange at Weber Road project as Judlau Construction Inc. crews have put in a solid effort since spring 2019.

They have quickly advanced from the pre-stage phase to the demolition of the eastbound bridge on the existing interchange, as well as engaging in earth work and other heavy construction activities, to meet the fall 2022 delivery date.

IDOT awarded the contract to Judlau in 2018. The plan was to start the operation in October 2018, but utility relocation delayed the operations. Commonwealth Edison (ComEd) completed the switching of power from the existing lines to new lines and services in 2019, and self-performed the removal of existing system. The removal of aerial cable over I-55 was accomplished last spring.

The pre-stage work had crews remove median barrier along I-55 within the staging area and engage in earth work operations that included topsoil stripping, embankment and aggregate sub-base installation for temporary pavement. Since then, crews have completed the following: stage 1 piers, abutments, pavement removal, embankment, ramp removal, subbase, subgrade and electrical, and they continue with storm sewer installation, and road, bridge and interchange activities.

The work zone for the entire project, the north and south segments, runs from 119th Street north/Rodeo Road of the interchange to 135th Street/Romeo Road to the south and 0.5 mi. east and west of Weber along I-55. The reconstruction and widening of the concrete road is taking place in Will County and within the villages of Romeoville and Bolingbrook.

The north contract work zone covers 1.55 mi. of road in Romeoville and Bolingbrook from Normantown Road to 115th Street, including the intersections at Rodeo Drive/Remington Boulevard, Remington Boulevard/Windham Parkway, Lakeview Drive and Normantown Road. Advance tree removal was completed in November 2017.

"A time extension was granted due to delays in relocating utility lines," IDOT officials told Construction Equipment Guide. "Based on the new completion date, the project is on schedule."

Weber Road, a north-south artery with two lanes in each direction, is being rebuilt to have three lanes each direction. The existing interchange is being reconstructed as a diverging diamond interchange (DDI). Crews also are reconstructing I-55 ramps; building dual bridge structures and retaining wall; installing interconnected traffic signals through the interchange, sidewalks and a 10-ft. wide shared-use path; overhead sign structures; CCTV cameras and fiber-optic connection and continuous LED roadway lighting with four high mast light towers; putting in an enclosed drainage system with in-line detention, signage, and pavement markings; and various intersection improvements.

In addition to new lanes, Normantown Road will have new dual left turn lanes for southbound and eastbound traffic and right turn lanes for three legs of the intersection. Fence stone sound walls are being placed adjacent to residential areas.

The Weber Rd. mainline will consist of a 12-ft. aggregate subgrade and a 10.25-in. PCC pavement (jointed). For the expressway ramps, there will be a 12-ft. aggregate subgrade; 8-ft. HMA binder course; 2.25-in. polymerized HMA binder; a 2-in. polymerized HMA surface; and a 12.25-in. HMA pavement. The side street pavement widening and resurfacing will have a 12-ft. aggregate subgrade; 8.75-in. HMA binder course; .75-in. polymerized HMA leveling binder; and a 1.25-in. HMA surface.

"The purpose of the project is to address safety, operational and capacity deficiencies in the Interstate 55 and Weber Road Interchange project study area," stated an IDOT web page. "This section of Weber Road and the interchange with I-55 are critical commuting links for the region and serve a number of businesses and industries locally."

The interchange was built in 1990 when much of the area around Weber Road was primarily used by farmers and motorists from nearby residential subdivisions.

"Since 1990, the population in Will County has nearly doubled, making it one of the fastest growing counties in the nation," stated the project web page. "The interchange and roadway are congested and traffic volumes are anticipated to continue to increase as growth continues in the region. In 2009, Will County completed a feasibility study of possible improvements to the interchange."

Stage 1 is ongoing and will see the reconstruction of the west half of Weber Road, construction of a new northbound bridge and ramp construction. Stage 2, fall of 2020 throughout 2021, will focus on the reconstruction of the eastern half of Weber Road, reconstruction of an existing bridge deck for future southbound traffic and ramp reconstruction. Stage 3, to start in 2021, will see the construction of new medians, complete ramp reconstruction and complete the installation of sidewalks and the multi-use path in the bridge area. Stage 4, the cleanup and punch list phase, will occur between the fall of 2021 and summer of 2022.

For the pre-stage work, Judlau crews prepared the site for major construction via median removal; the installation of temporary pavement, traffic signals and storm sewer; and utility relocation.

Key milestones for the 2020 construction season are: building a new bridge for future northbound traffic and completing the southbound lanes on Weber Road.

Much of the work centers on the interchange.

"The biggest challenge so far was getting all of the utilities relocated so work could begin on the new construction," stated IDOT construction officials. "ComEd experienced unanticipated challenges when they began transferring power to their relocated facilities. This, in turn, caused delays to the start of construction on the south half of the project. To help keep the project on track, we implemented the work zone on the north half of the project where ComEd no longer had conflicts."

Judlau crews completed the demolition work for Stage 1 — the westbound bridge on the interchange — and have started the substructure work. Night work has been minimal, but night shifts were scheduled to remove the deck and beams.

IDOT noted that it has a solid working relationship with Judlau, particularly in keeping the project moving on schedule.

The earth work operations are proceeding smoothly, with no major challenges expected. This work will continue for the duration of the project. Materials are brought in from outside sources to meet all structural requirements.

Lane closures provide crews with traffic-free work areas, particularly in the interchange section where the new west bridge is being constructed. Below the new span, another bridge is being constructed using a portion of the old bridge, which will see the installation of a new deck.

The new bridge, still under construction and 10 ft. longer than the old one, will be 252 ft. long and have a width of 60 ft.

"We are reducing the width because the DDI facilitates movement and allows for the free flow of traffic in the adjacent areas," stated IDOT, which pointed out that the demolition went smoothly and that a similar process will be repeated for the westbound bridge. "Judlau did it in stages, and every precaution was taken to ensure that debris did not fall below. For the overhang portion, this was done at night with lance closures."

False decking has been set up to separate the two bridges. For the main (upper) bridge, work is ongoing to build the substructure.

"All work is following the progress schedule," stated IDOT. "Work on the superstructure continues with portions of the new deck to be poured in fall 2021."

The construction of the new roads and ramps for Stages 1 and 2 will be done in phases, along with traffic shifts. Crews have demolished eastbound interchange bridge and are working on new substructure.

"Aggregate base for the new road was placed from the north end of the project down to the interchange," stated IDOT construction officials. "The retaining wall at the southwest corner of 119th and Weber Road is complete. Storm sewer work within the interchange is on-going. Earthwork in all four infields is on-going. The working platform for the ground columns was installed along with the Stage 1 ground columns. Stage 1 storm sewer work on Normantown Road is complete. All work in the center median of I-55 was complete and traffic shifted four feet left into the Stage 1A configuration. Construction of the abutments are complete, [as well as] drilled shafts and steel piles for the retaining wall in front of Speedway, south of the interchange.

"Earthwork and storm sewer will continue at the interchange. South of the interchange, concrete facing for the retaining wall in front of Speedway will be formed and poured, and embankment placed behind the wall and grading for the new roadbed will be done. Embankment and storm sewer will be placed in the slough area. Normantown Road will be graded for the new roadbed."

Peak days thus far have seen more than 40 Judlau and subcontractor employees on-site. Local and regional subcontractors have been hired.

The amounts of new materials to be removed via the demolition of the existing interchange and roads and new materials to be brought in, such as concrete and steel, are still being tabulated.

Judlau expects to re-use suitable earth that has been excavated, as well as HMA and crushed concrete from various items that have been removed.

Prairie Material is providing some of the concrete being poured for the project.

Equipment-wise, Judlau is using: cranes excavators, dozers — including Komatsu models, loaders, motor graders, rollers, pavers, telehandlers, pile driving equipment and other standard construction vehicles. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA