The retaining walls are the first to feature the “River Bank” aesthetic treatment reflecting Laveen’s agricultural heritage.
The retaining walls are the first to feature the “River Bank” aesthetic treatment reflecting Laveen’s agricultural heritage.

The first interchange under construction in Laveen for the Loop 202 South Mountain Freeway is taking shape, with a closure of Elliot Road at 59th Avenue allowing crews to make significant progress in a short time.

After extensive earthwork, six large concrete piers are now planted in the future median of the South Mountain Freeway. More than 300,000 cu. yds. of dirt has been moved to create bridge approaches and ramps.

The piers will soon support a 272-ft., two-span bridge that will carry Elliot Road traffic over the South Mountain Freeway. Soon, 26 concrete girders will be set on the piers to form the bridge.

Scheduled to open in late March, it will be the first South Mountain Freeway bridge to be used by motorists.

Since late October, crews also have installed underground utilities and drainage structures, including a 4-ft.-wide storm drain crossing, and built retaining walls, called mechanically stabilized earth walls.

The retaining walls are the first to feature the “River Bank” aesthetic treatment reflecting Laveen's agricultural heritage. This is one of five aesthetic patterns that will be used along various stretches of the South Mountain Freeway.

Following completion of the bridge and reopening Elliot Road at 59th Avenue in March, additional work needed to complete the interchange will include paving the ramps and mainline freeway, signage, final striping and landscaping.

Local traffic can detour to Dobbins Road between 59th and 75th avenues until the bridge is completed.

The South Mountain Freeway, which is slated to open late 2019, will provide a long-planned direct link between the East Valley and West Valley and a much-needed alternative to I-10 through downtown Phoenix. Approved by Maricopa County voters in 1985 and again in 2004 as part of a comprehensive regional transportation plan, the South Mountain Freeway will complete the Loop 202 and Loop 101 freeway system in the Valley.

For more information, visit SouthMountainFreeway.com.




Today's top stories

Construction Industry Optimistically Preparing for New Year Ahead

CFX Oversees $412M SR429 Expansion in Florida

Capital Express Central Project Ramps Up in Texas

VIDEO: NCDOT Plans Major Road Upgrades in Wilmington Over Next Several Years

DEVELON Set to Exhibit at ARA Show 2025

Des Moines Airport Works With Weitz/Turner On Expansion

Ring Power Lift Trucks Partners With Hiab to Bring MOFFETT Truck-Mounted Forklifts to Florida Customers

Earthborne Demo Day Draws Crowd Despite Downpour


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA