List Your Equipment For Free  /  Seller Login

Fay Forges Ahead Over the Yough

Thu June 03, 2021 - Northeast Edition #12
Brenda Ruggiero – CEG Correspondent


The contract was awarded to Fay for $15.4 million and construction is phased. Crews from the Pittsburgh company began work on this project in August 2020 and will finish in the summer of 2022.
The contract was awarded to Fay for $15.4 million and construction is phased. Crews from the Pittsburgh company began work on this project in August 2020 and will finish in the summer of 2022.
The contract was awarded to Fay for $15.4 million and construction is phased. Crews from the Pittsburgh company began work on this project in August 2020 and will finish in the summer of 2022. A bridge in McKeesport, Pa., is currently being revitalized for the Pennsylvania Department of Transportation.

A bridge in McKeesport, Pa., is currently being revitalized for the Pennsylvania Department of Transportation.

The Jerome Street Bridge is an arch bridge crossing the Youghiogheny River. It opened in the current design in 1937 and was previously rehabilitated in 1988. The bridge length is 755 ft. long with a main arch span of 455 ft. in length.

The contract was awarded to Fay for $15.4 million and construction is phased. Crews from the Pittsburgh company began work on this project in August 2020 and will finish in the summer of 2022.

According to Katie Spear, Fay spokesperson, the scope of work includes full blasting and painting, structural steel repairs, new concrete deck and sidewalk, barrier replacement, expansion dam replacements, concrete substructure repairs, bearing repairs, approach roadway work and other miscellaneous construction items.

Spear reported that a single 12-ft. lane will be maintained in the eastbound direction to allow the approximately 11,000 daily motorists to use the bridge during construction. The deck replacement will be completed during the 2021 season, opening the bridge to preconstruction traffic by November 2021.

"A unique aspect of the construction is that the demolition activities are working collaboratively with the installation of the new stringers," said Michelle Olszewski, project manager. "The two crews work together, immediately replacing old steel with new as they move across the structure."

Komatsu PC238 excavators with E64 hammers are being used to remove the existing grid deck, stringers and joists. Demolition began in the center of the bridge, progressing in each direction simultaneously, toward the abutments. These same excavators are used to install the new stringers as the crews work outwards. Additionally, the sidewalk and parapet will be removed.

Subcontractor Amelie Construction is responsible for concrete substructure repairs and bearing replacements, along with major steel repairs. Spear noted that this will improve the durability and lifespan of the bridge.

The new deck will be constructed of lightweight concrete and will receive a polyester polymer concrete (PPC) overlay to enhance the life of the bridge in the long-term. This method also is an accelerated construction method as it has a cure time of approximately four hours.

"Simultaneously, the entire superstructure will be painted to enhance the aesthetics," Spear said. "Our painting subcontractor, Avalotis Corporation, will use containment enclosures to prevent the debris generated during surface preparation on the bridge superstructure from entering the environment. Enclosures are generally made up of cover panels, scaffolds, supports, screens, and tarps. These systems also employ a vacuum system to capture the removed particles."

Once all the rehabilitation is completed, the bridge will look similar to a newly constructed one. Fay and Fay Southeast, both part of S&B USA Construction, have completed many similar rehabilitations of bridges and replacements of others in the Pittsburgh area, as well as in Maryland and Virginia. CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA