South Coast Rail Early Action construction projects are under way to prepare for Phase 1 main line rail construction. The first visible active construction project is drainage culvert replacement along the right-of-way.
The work includes drainage culvert repair and replacement, a railroad grade crossing upgrade and constructing wetlands as mitigation along the right-of-way.
From Middleborough to New Bedford and Fall River, MassDOT's contractor will replace a total of 46 culverts with new precast structures, clean an additional 16 existing culverts and remove one out-of-service culvert. Existing granite culverts are being replaced with new precast concrete structures.
This project also includes constructing six wetlands impact mitigation areas adjacent to the railroad right-of-way.
The culverts, grade crossing and wetland mitigation work is currently scheduled for completion in early 2020.
For more information, email the project team at SouthCoastRail@dot.state.ma.us or visit mass.gov/south-coast-rail.