List Your Equipment For Free  /  Seller Login

Harbor Bridge Crews Achieve Project Milestone

Tue June 19, 2018 - West Edition #13
Harbor Bridge Project website


A large auger is used to drill each shaft to a depth of approximately 200 ft. (Harbor Bridge Project photo)
A large auger is used to drill each shaft to a depth of approximately 200 ft. (Harbor Bridge Project photo)
A large auger is used to drill each shaft to a depth of approximately 200 ft. (Harbor Bridge Project photo) HBP crews prepare drilled shafts for the completion of the footings. (Harbor Bridge Project photo)

Harbor Bridge Project (HBP) crews have reached another milestone with the completion of 40 drilled shafts on both the north and south side of the project. The 40 drilled shafts will make up the foundations of the two bridge pylons.

There are 20 drilled shafts located on the north side of the project and 20 located on the south side of the project. Each of the shafts are 10 ft. in diameter and were drilled to a depth of just more than 200 ft.

More than 500 cu. yds. (approximately 70 truckloads) of concrete was placed in each of the completed drilled shafts. Crews have moved into the next stage of construction which includes trenching areas around the shafts to prepare for the completion of the footings.




Today's top stories

Depreciation Bonus Begins Phase-Out

California's I-80 Pavement Rehab Project Moving Along

VIDEO: Vermeer Unveils D24 Horizontal Directional Drill, Marking New Era in Utility Installation

ConExpo-Con/AGG Releases Essential Guide for Hiring, Retaining Top Construction Talent

Ole Miss Progressing Toward Construction of $125M Accountancy School

Boston, MBTA Officials Reveal New Designs for Future Blue Hill Avenue Transit Project

National Attachments Celebrates Its 35th Anniversary

CEG Speaks With New President of Chadwick-BaRoss, Thompson Equipment


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA