Harbor Bridge Crews Achieve Project Milestone

Tue June 19, 2018 - West Edition #13
Harbor Bridge Project website


A large auger is used to drill each shaft to a depth of approximately 200 ft. (Harbor Bridge Project photo) HBP crews prepare drilled shafts for the completion of the footings. (Harbor Bridge Project photo)

Harbor Bridge Project (HBP) crews have reached another milestone with the completion of 40 drilled shafts on both the north and south side of the project. The 40 drilled shafts will make up the foundations of the two bridge pylons.

There are 20 drilled shafts located on the north side of the project and 20 located on the south side of the project. Each of the shafts are 10 ft. in diameter and were drilled to a depth of just more than 200 ft.

More than 500 cu. yds. (approximately 70 truckloads) of concrete was placed in each of the completed drilled shafts. Crews have moved into the next stage of construction which includes trenching areas around the shafts to prepare for the completion of the footings.




Today's top stories

Virginia's CBBT Expansion Progress

VIDEO: Thompson Tractor Holds Tech Demo in Hanceville, Ala.

James R. Carter Paving Fashions Enviable Reputation in Its 70 Years

Yoder & Frey Returns to Newnan, Ga., for Big Auction

NED Hosts Grand Opening Ribbon Cutting in Apopka, Fla.

BOMAG Americas Adds Decades of Industry Experience to Its Light Equipment Sales Team

Manitou North America Adds Ferri Equipment as New GEHL Dealer

CTDOT Invests $10 Million in Transportation Infrastructure Upgrades in Eight Rural Towns


 







39.95234 \\ -75.16379 \\ Philadelphia \\ PA \\ US \\ 19019