High Court Upholds Lake Erie Wind Farm

Tue September 13, 2022 - Midwest Edition #19
Andrew Welsh-Huggins – ASSOCIATED PRESS


COLUMBUS, Ohio (AP) A company can proceed with plans to build what will be the first freshwater offshore wind-powered electric-generation facility in North America, in Lake Erie off the coast of Cleveland, the Ohio Supreme Court ruled Aug. 10.

At issue is the 2020 approval by the Ohio Power Siting Board of the project by Icebreaker Windpower, which proposed the six-turbine development about 10 mi. north of Cleveland.

Residents of the Cleveland-area village of Bratenahl sued to stop the project, arguing the siting board didn't have enough evidence to determine the project's environmental impact and that the project doesn't serve the public interest as defined in Ohio law.

The court ruled 6-1 that the board had multiple studies before it that found a low impact on birds and bats. The court also said the board properly determined the project would have "a minimal impact" on the public's ability to enjoy Lake Erie.




Today's top stories

Protecting Delaware Memorial Bridge

Widespread Catastrophic Damage From Hurricane Awaits Repair Crews in SE States

Flatiron, Dragados JV Set to Finish Major Job in Corpus Christi

JCB Celebrates 20 Years of Engine Making

Robert H. Finke & Sons Holds Open House at New Colchester, Vt. Facility

Snyder Civil Leads Way to Provide Clean Water, Safe Communities, More

Today's Security Tech Helps Contractors Combat Jobsite Theft

Komatsu Company Stores East Holds Open House in Pennsylvania


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA