List Your Equipment For Free  /  Seller Login

Indiana's I-65 Corridor Accommodates Expanding Population in Whitestown

Wed December 08, 2021 - Midwest Edition #25
Lori Lovely – CEG Correspondent


Approximately 150,000 tons of asphalt is being used on the project. It comes from the E&B Paving plant at Harding Street.
(INDOT photo)
Approximately 150,000 tons of asphalt is being used on the project. It comes from the E&B Paving plant at Harding Street. (INDOT photo)
Approximately 150,000 tons of asphalt is being used on the project. It comes from the E&B Paving plant at Harding Street.
(INDOT photo) Right of Way acquisition began in 2019 and the $62.8 million contract was let to bid in May 2020. E&B Paving LLC, based in Anderson, Ind., is the general contractor, with subcontractor Fox Contractors Inc. performing the dirt work.
(INDOT photo) Work on the two-year project began in July 2020. Completion is anticipated in August 2022.
(INDOT photo) Both the new I-65/SR 267 interchange and the I-65/CR 550 interchange will be “Diverging Diamond Interchanges,” which INDOT expects to alleviate traffic bottlenecks
(INDOT photo) The Indiana Department of Transportation (INDOT) is building a new interchange on Interstate 65 at Boone County Road 550 South and redesigning the I-65 and State Road 267 interchange at Whitestown Exit 133.
(INDOT photo)

The Indiana Department of Transportation (INDOT) is building a new interchange on Interstate 65 at Boone County Road 550 South and redesigning the I-65 and State Road 267 interchange at Whitestown Exit 133.

"The purpose of the project is to improve traffic operations along the I-65 corridor, from I-865 to S.R. 267 near Whitestown and to provide improved connectivity between I-65 and the rapidly developing area along the C.R. 550 S corridor," explained Debbie Calder, communications director of INDOT's Crawfordsville district.

Planned Growth

Last year, Whitestown was ranked Indiana's fastest-growing community for the eighth consecutive year. Its population increased from 3,132 to 8,627 between 2010 and 2018, when talks about this project began. Over the past decade, developers have added millions of square feet of industrial space and hundreds of thousands of square feet of retail along the Whitestown Parkway east of the southern I-65 interchange, according to the Indiana Business Journal.

After conducting an interchange capacity analysis, INDOT held a public meeting in 2017 to discuss plans to accommodate traffic resulting from so much growth.

Tanya Sumner, Whitestown director of public relations, reported that the audience was pleased about the proposed reconfiguration of Exit 133 at SR 247, which many feel is "badly needed" to prevent traffic backups.

"Adding a stoplight at Indianapolis Road also is something residents have been asking for," Sumner said, praising INDOT for "proactively planning for future growth and getting ahead of any potential traffic problems."

Whitestown Town Manager Jason Lawson told the Indiana Business Journal that he considers a brand-new interchange a game-changer for the community.

Prep Work

Right of Way acquisition began in 2019 and the $62.8 million contract was let to bid in May 2020. E&B Paving LLC, based in Anderson, Ind., is the general contractor, with subcontractor Fox Contractors Inc. performing the dirt work. Work on the two-year project began in July 2020. Completion is anticipated in August 2022.

"When work started on this contract, there [were] still 13 parcels of real estate that [were] not cleared," said Greg Hole, INDOT project engineer. "The contractor worked in available areas. As each parcel was cleared, utility relocation could begin."

The last parcel didn't clear until June 2021. It was a hog confinement farm on the east side of I-65 at CR 550.

"The pits under the barns were supposed to be empty," Hole said. "We were hoping the pits were full of ground water, but we had it tested. It was manure. We had to pay to have the manure removed."

Barrier walls were erected and E&B Paving began making minor paving improvements along three-quarters of a mile near the I-65/I-865 interchange in July 2020. This new pavement is for minor ramp improvements on the existing northbound I-65 exit ramp to Whitestown Parkway and the existing southbound I-65 exit ramp to I-865.

‘Diamond in the Rough'

Both the new I-65/SR 267 interchange and the I-65/CR 550 interchange will be "Diverging Diamond Interchanges," which INDOT expects to alleviate traffic bottlenecks. The interchange at CR 550 South is expected to reduce traffic on SR 267 and Whitestown Parkway by as much as 50 percent.

The Clinton County Daily News describes a DDI as a type of interchange "in which the two directions of traffic on a non-highway road cross to the opposite side on both sides of a bridge." It requires traffic on the highway overpass to briefly drive on the opposite side of the road than usual. As drivers enter a DDI, they cross over to the left side of the bridge, as directed by signals, signs and pavement markings. DDIs are said to be safer, more efficient and more cost-effective than traditional diamond interchanges.

Calder explained that the new interchange at CR 550 will divert "a significant amount of traffic" from both the SR 267 interchange and the Whitestown Parkway interchange.

"This diversion improves the operations of the corridor so much that a less expensive interchange at SR 267 can be constructed and still provide the desired level of service," Calder said.

Contract plans call for 600,000 cu. yds. of borrow to be placed for the new ramps and roadways, Hole stated.

"Fox Contractors bought a 40-acre field just north of the project to acquire the borrow for the job," he said.

Approximately 150,000 tons of asphalt is being used on the project. It comes from the E&B Paving plant at Harding Street. With as many as nine different operations going on at the job site at once, up to 75 workers are onsite at any time. Some of them are using as many as 32 dump trucks to haul 10 to 15 loads of borrow or asphalt each day, Hole calculates.

In addition to asphalt, crews will be pouring concrete. They're using a new concrete additive, E5, on all the bridge decks because it gives the concrete "better workability," Hole explained. E5 Internal Cure is a concrete admixture that provides proven benefits during placement and in the overall quality of in-place concrete, according to the company.

E5 chemically binds nan-silica in concrete at the initial reaction point — internally curing concrete. It produces a stronger, more durable concrete that resists chemical and physical attack. It also significantly reduces the carbon footprint of construction projects. Benefits include improved water retention, workability, pumpability and higher pozzolanic activity, which creates higher strength and reduced permeability. This alternate curing method is recommended for bridge decks, slab bridges and reinforced concrete bridge approaches. Hole said they will install monitoring equipment on the east MSW wall at CR 550.

There also are three bridges included in the contract. The Etter Ditch bridge on Indianapolis Road has four piers with a total of 38 12-in. H piles driven to approximately 50 ft.; the new bridge on S.R. 267 over I-65 has three piers with a total of 34 12-in. H piles driven to 60 ft.; and the new bridge at C.R. 550 over I-65 has three piers with 92 12-in. H piles driven to 78 ft.

Finances, Fickleness

Calder said the project will be paid for with federal funding, but that's only partly true. In 2017, reports the IBJ, Whitestown created a tax-increment financing district to pay off bonds that were sold to raise its $10 million portion of the $63 million interchange project. In addition, 50 percent of additional property tax revenue generated in the district during the next 10 years will go toward retiring those bonds.

However it gets paid for, the I-65 interchange project is expected to launch extensive commercial development. Initial plans called for a mix of retail and industrial development, along with office and health care space, but COVID-19 ended plans for several brick-and-mortar retail outlets.

For example, IBJ reports that Indianapolis-based Gershman Partners canceled three-year-old plans to build a 1 million sq.-ft. shopping center northeast of the proposed CR South interchange that was rumored to have big-name retailers like Ikea.

Whitestown's director of operations and economic development, Nate Messer, believes it to be a temporary setback and expects investors to return to claim the prime real estate with interstate access.

He appears to be right, as Duke Realty is forging ahead with industrial developments in Whitestown and Strategic Capital Partners, based in Indianapolis, has begun phase two construction on an industrial warehouse project that has already seen leases signed by Lowe's and other companies. With easy access to I-65, a major trade route connecting Chicago with the Gulf of Mexico, the area is likely to attract more warehouses in the future, even if Whitestown officials would prefer a mix of businesses.

Detours, Dates

According to Calder, some of the SR 267 interchange work, the northern SR 267 bridge and the CR 550 South interchange can be completed with minimal impact to traffic. Although there is no significant impact to traffic related to I-65, there are detours related to local roadway realignments associated with Perry Worth Rd. and Albert White Drive.

The scheduled completion date for an added travel southbound lane of I-65 at I-865 was Oct.15, 2020, and it finished on time, Calder said. The completion date for an added lane of northbound Whitestown Parkway exit ramp was Oct. 31, 2020 — also completed on time. A box culvert on Indianapolis Road was replaced with a bridge; it required 100 days of closure of the road. This project was completed on time.

An intermediate completion date of Nov. 15, 2021, has been delayed due to ROW acquisition; the current completion date is scheduled for Aug. 20, 2022. Calder thinks it may be possible to make the CR 550 South interchange operational before the reconstruction of existing portions of the SR 267 interchange are completed.

In order to keep to the schedule, the contractor usually works weekdays from 7 a.m. until 4 p.m., but Calder said that there has been some Saturday work.

"Any work that interferes with traffic on I-65 is being done at night, so there is occasionally some night work," she said.

Calder mentioned that community engagement about the project, which began with that public meeting years ago, continues "as needed" with a supportive population eager to see the results of this. CEG


Lori Lovely

Lori Lovely is an award-winning journalist, editor and author of the children's book Isadora's Dance. She has worked for newspapers, magazines and niche publications, covering a wide-ranging list of topics that includes motor sports, construction, MSW, energy, environmental issues, water, animal rights and issues, history, Native American issues and people, real estate and home decor, farming and more. Her degrees in History taught this dedicated professional to research thoroughly and ask detailed questions in order to winnow interesting facts that convey the essence of the story. As a seasoned writer and compassionate storyteller, she accurately portrays the subject in a manner that entrances the reader.

When she's not working on assignment, Lori is tending to her historic Indiana farm, where she raises alpacas. An inveterate animal lover, this vegetarian enjoys spending time with her animals and working in her garden.


Read more from Lori Lovely here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA