Interchange Work Complete at I-76/U.S. 85 in Henderson, Colorado

Wed December 20, 2017 - West Edition #26
Construction Equipment Guide


The project also improved roadway drainage, lighting and water quality measures. This $10 million improvement project was partially funded by FASTER Safety funds.
(Colorado Department of Transportation photo)
The project also improved roadway drainage, lighting and water quality measures. This $10 million improvement project was partially funded by FASTER Safety funds. (Colorado Department of Transportation photo)
The project also improved roadway drainage, lighting and water quality measures. This $10 million improvement project was partially funded by FASTER Safety funds.
(Colorado Department of Transportation photo) Crews have completed reconstructing Interstate 76 at U.S. Highway 85.
(Colorado Department of Transportation photo) More than 80,000 vehicles per day travel I-76.
(Colorado Department of Transportation photo)

Crews have completed reconstructing Interstate 76 at U.S. Highway 85. The most noticeable changes are along westbound I-76, where the project improved the curve approaching the southbound U.S. 85 merge area and added an additional lane from southbound U.S. 85 to 96th Avenue.

Before the project, westbound I-76 had a high accident history, including several truck roll-over incidents. The super-elevation of the curve, which is the raised or “banked” section, was redesigned to current standards. Traffic operations have also improved at the southbound U.S. 85 on-ramp. There are now two lanes entering I-76 instead of one.

Motorists also now experience a smoother ride on I-76.

“The concrete along both directions of I-76 was deteriorating rapidly and resulted in rough road conditions,” said Larry Quirk, CDOT project engineer. “Full reconstruction takes the highway down to the bare ground.”

Before crews could remove the old concrete, new detour pavement was placed to accommodate traffic during construction. Traffic shifted several times and ultimately reopened in the final configuration this fall.

More than 80,000 vehicles per day travel I-76. Fifteen percent or approximately 12,000 of these vehicles are large trucks.

“The amount of traffic during construction was impressive,” Quirk said. “Any time you have that much traffic so close to the work, motorist and worker safety is always on your mind.”

Project Info

CDOT and Villalobos Concrete Inc. began construction in October 2016. For a year, both directions of I-76 were down a lane in each direction while crews completely reconstructed the highway from 96th Avenue through the U.S. 85 interchange. Major project features included improving the westbound I-76 curve at U.S. 85, constructing a new auxiliary lane from southbound U.S. 85 to 96th Avenue and full replacement of deteriorated concrete pavement.

The project also improved roadway drainage, lighting and water quality measures. This $10 million improvement project was partially funded by FASTER Safety funds.




Today's top stories

Chicago Asphalt Contractor Embraces Electric Vehicles

New or Used, Prinoth Panther T14R Redefines Productivity, Performance for Crawler Carriers

VIDEO: Feds Award Massachusetts $472.3M to Replace An Old Drawbridge Over Charles River

Fleet Management Gets Smarter … Artificially

ARTBA Honors Top Women & Firms in Transportation Construction

Excavator Work Tools Startup HB Attachments Rebrands as TRUE Attachments

Montabert Introduces Upgraded Variable-Speed Breakers

Montabert Announces Surface, Underground Drills


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA