List Your Equipment For Free  /  Seller Login

John G. Walton Construction Leads Major SR-180 Work in Orange Beach

Wed July 08, 2020 - Southeast Edition #15
Irwin Rapoport – CEG Correspondent


The project schedule is based on many benchmarks: The installation of the 24-in. temporary sewer line bypass valve installation (done by the city); 11 pipe crossing crossings that required daily lane closures; and paving of the new westbound lane, as well as the drainage, have been completed.
(John G Walton Construction photo)
The project schedule is based on many benchmarks: The installation of the 24-in. temporary sewer line bypass valve installation (done by the city); 11 pipe crossing crossings that required daily lane closures; and paving of the new westbound lane, as well as the drainage, have been completed. (John G Walton Construction photo)
The project schedule is based on many benchmarks: The installation of the 24-in. temporary sewer line bypass valve installation (done by the city); 11 pipe crossing crossings that required daily lane closures; and paving of the new westbound lane, as well as the drainage, have been completed.
(John G Walton Construction photo) The pipe crossing work was not easy, but fortunately it did not require any night work.
(John G Walton Construction photo) “We had to do half of each crossing at a time, so we could keep traffic moving while we installed drainage pipe, placed backfill and paved with asphalt,” said Johnny Walton, the general contractor’s owner and president. “We had to coordinate the work of the pipe laying crews with asphalt crews. Everything went smoothly.”
(John G Walton Construction photo) The widened highway, with 6-ft. wide shoulders on either side, is designed to handle a projected average of 36,200 vehicles daily through 2039. 
(John G Walton Construction photo)

John G Walton Construction Co. Inc. started major work on the Alabama Department of Transportation's (ALDOT) $7.9-million SR-180/Canal Rd. widening in Orange Beach on Sept. 23, 2019, and the crews are very confident about meeting the December 2020 delivery date.

The project, financed by federal (80 percent) and state (20 percent), covers 2.3 mi. of SR-180 westbound between the Foley Beach Express and SR-161 in Orange Beach. Additional elements cover utility relocations, as well as clearing, placing drainage, paving and striping.

"When complete, this portion of roadway, which carried over 18,000 vehicles in 2018, will be a five-lane highway including a designated two-way turn lane," said Katelyn Turner, ALDOT public information officer for the southwest region. "We look forward to bringing this project to fruition as it will better accommodate the volume of traffic this roadway carries especially during the summer tourism season. The project was authorized in December 1999, however sufficient funds did not become available until the 2010 BP Oil Spill settlement, which provided enough funds to be able to let the project for contract. This project will help alleviate the congestion this portion of SR-180 experiences year-round, but especially in the summer as it carries traffic to and from the Foley Beach Express, which is a popular route for Orange Beach visitors as it provides the quickest access to that vacation hot-spot."

The widened highway, with 6-ft. wide shoulders on either side, is designed to handle a projected average of 36,200 vehicles daily through 2039.

The project is managed by ALDOT and designed by Burk-Kleinpeter Inc.

Preliminary utility work started prior to the Sept. 23 start and covered cable, water and sewer, and gas is 90 percent complete.

"We have weekly meetings with ALDOT, the city, and the utility companies," said Michael Gibson, P.E., John G Walton Construction's project manager. "We had to do a lot of coordination with every utility company to make sure they were ahead of the road construction and if they weren't, schedule accordingly. Mayor Tony Kennon was very helpful about getting them to cooperate so they didn't hold up the project."

The project schedule is based on many benchmarks: The installation of the 24-in. temporary sewer line bypass valve installation (done by the city); 11 pipe crossing crossings that required daily lane closures; and paving of the new westbound lane, as well as the drainage, have been completed.

The pipe crossing work was not easy, but fortunately it did not require any night work.

"We had to do half of each crossing at a time, so we could keep traffic moving while we installed drainage pipe, placed backfill and paved with asphalt," said Johnny Walton, the general contractor's owner and president. "We had to coordinate the work of the pipe laying crews with asphalt crews. Everything went smoothly."

Eastbound traffic was moved to the westbound side last March and the new eastbound lane should be completed in October. The final wearing surface and permanent stripe and markings will be placed after the eastbound lane is ready and the installation of two mast-arm signals components at the intersection of SR-180/Gulf Bay and SR-/William Silvers Road has started and should be completed in the summer.

"The biggest challenge is the traffic' said Walton. "We tried to get as much done in the fall and winter months to get ahead of the spring break season and we succeeded. This has allowed us to work more freely now that the traffic is more horrendous with the summer tourists and beach people."

The city is letting the general contractor use a vacant lot to store materials and equipment and set up a field office. The state's COVID-19 restrictions reduced the flow of traffic, which allowed crews to complete goals more rapidly.

Good relations with ALDOT have been essential.

"We had design changes and hiccups that had to be worked out with the designers and that went well," said Gibson.

The roadway has been temporarily striped into a five-lane highway with a designated center turn lane. Sodding was done by T.E.C.S LLC and was placed on the westbound side as the new lane and drainage ditches were built.

Excavation and road construction crews work simultaneously, following each other.

"Orange Beach had a big sewer line running under the shoulder of the westbound road, which was fairly shallow, so we couldn't do the full-depth excavation that was planned and run our compactor to get compaction," said Gibson. "ALDOT made a change. We shallowed up and didn't have to do as much excavating and we were able to build on top of the existing material as not to damage any of the sewer lines. It was all sand down there, so excavation was easier. The sand could not be reused on site."

On a good day, between 800 and 1,000 ft. could be graded and have crushed aggregate bases placed on the widening,

"They had a timeline to complete the westbound lane and we finished it a month ahead of schedule," said Walton. "This has sped up the project. We had a GPS model built for the job that allowed us to save a little bit on the surveying and run our GPS equipment with GPS systems."

Walton noted that the Komatsu PC210-LCi excavator and D39i dozer have been the most integral pieces needed to complete the job.

"The D51-i was too big to work on the widening of the lanes, so we purchased the D39i" he said, "which is a smaller dozer and much more suited to the widening work. They have GPS capabilities built-in to them and they really have it down pat — you don't have to add antennas to them."

Topcon GPS systems are in use on the project.

The pipe and drainage infrastructure installation for the eastbound lane construction is also ongoing.

Gibson and Walton are assisted by Scott Appleton, the project superintendent.

"Scott is our feet on the ground and runs the job — he makes mine and Johnny's life a lot easier and he is very knowledgeable about GPS systems," said Gibson. ‘We've got a good crew. They take long hours on day and don't complain. They'll stay late and do whatever it takes to get the job done."

Average days have around 15 John G. Walton Construction and subcontractor employees on site, with the major subcontractors being C&H Construction for traffic control and construction signs, Ingram Signalization for traffic signals, L&K Construction for concrete work, Ozark Striping for traffic striping, T.E.C.S. LLC for erosion control and W R Mitchell for utilities.

Materials removed should include 37 tons of asphalt and 28,000 cu. yds. of excavation. New materials to be brought in should tally 500 cu. yds. of concrete, 18,179 tons of asphalt and 30,150 cu. yds. of borrow material.

"The five inches of top soil was re-used on the project." said Gibson.

The company is using: excavators — a Komatsu PC210LCi and a Case CX80C; dozers — a Komatsu D31PX-22 and a D39i and a John Deere 650-J; loaders — a Volvo L90H front-end loader and a Cat 416E; a Vogele 4203 paver; a Dynapac CC524 HF DBL drum roller; a Broce RJ 350 self-propelled sweeper; a Cat 299 skid steer; a Cat 416F-2 backhoe; a Komatsu GD655-7 motor grader; a Weiler 1250 material transfer vehicle; a Wirtgen W200i milling machine; a GMC water truck; a New Holland TN55 farm tractor; and a Ford F150 truck.

"The pieces of equipment that we're using are relatively new and we've had very little repair work to do," said Walton. "Most of the equipment we buy nowadays has extended four-to-five-year warranties because with all the computers on equipment today, it's hard for us to work on them."

The firm has in-house mechanics that service equipment at the shop and in the field.

John G. Walton Construction purchases and rents equipment from Tractor and Equipment Company (Komatsu), Thompson Tractor Co. Inc. (Cat), Beard Equipment Co. (John Deere) and Cowin Equipment Co. (Volvo)

"These are your four major dealerships down here," said Gibson. "They're all pretty good about having spare parts readily available or next day service."

"They give us good service and we have good relations with them," said Walton. "It's all about good customer relations, having a relationship with them where they what you need and expect. If we need a part or piece of equipment, they'll make it happen." CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

Huntsville, Ala.'s Sandra Moon Community Complex to Begin Final, $31.3M Phase of Work

Unique Skid Steer Tire Increases Snow Clearing Performance, Safety

New Deutz Power Center Mid-Atlantic Opens in Ashland, Va.

2025 CGA Conference & Expo Opens Registration On Nov. 6


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA