Kentucky Transportation Cabinet Begins Work On Bridges Damaged By Flooding

Tue September 13, 2022 - Midwest Edition #19
Office of Gov. Andy Beshear


The KYTC will replace or repair more than 170 bridges in eastern Kentucky that were damaged by flooding. These are bridges serving state and county routes and are among nearly 1,100 sites assessed for damage by KYTC inspectors after the July flooding.
(KYTC photo)
The KYTC will replace or repair more than 170 bridges in eastern Kentucky that were damaged by flooding. These are bridges serving state and county routes and are among nearly 1,100 sites assessed for damage by KYTC inspectors after the July flooding. (KYTC photo)
The KYTC will replace or repair more than 170 bridges in eastern Kentucky that were damaged by flooding. These are bridges serving state and county routes and are among nearly 1,100 sites assessed for damage by KYTC inspectors after the July flooding.
(KYTC photo)
 The Kentucky Transportation Cabinet (KYTC) has begun construction to permanently replace county and state bridges damaged by the devastating flooding that occurred in eastern Kentucky in late July.
(KYTC photo)

Gov. Andy Beshear announced Sept. 2 that the Kentucky Transportation Cabinet (KYTC) has begun construction to permanently replace county and state bridges damaged by the devastating flooding that occurred in eastern Kentucky in late July.

The priority projects include publicly owned crossings that were damaged or destroyed and have significantly limited or eliminated access for drivers.

The cabinet will replace or repair more than 170 bridges in eastern Kentucky that were damaged by flooding. These are bridges serving state and county routes and are among nearly 1,100 sites assessed for damage by KYTC inspectors after the July flooding. Among the 170 bridges already identified for replacement or repair, approximately 100 require full replacement or replacement of the bridge superstructure, which is the area at the top of the bridge.

"Our teams have moved with unprecedented speed to restore access where these bridges were the only way many of our fellow Kentuckians were able to reach their homes," said Beshear. "We are utilizing all the resources at our disposal to restore access. This is a great example of how Team Kentucky is working day and night, not just to clean up, but also to rebuild what was lost. The residents need this critical access so they can return to their homes, to their lives and to a sense of normalcy as we rebuild damaged infrastructure throughout eastern Kentucky."

Currently, two permanent bridge replacement projects are under construction in Perry County. They are Dan Lane over Big Willard Creek and Macintosh Mt. over Little Willard Creek. Jave LLC, a contractor based in Lexington, recently began construction on the two projects. They are expected to be completed in less than 60 days.

The two bridges are among 33 structures that have been initially targeted for rapid replacements in Perry, Knott, Pike, Letcher and Floyd counties. All the bridges are expected to be ready for construction by the end of September and replaced by the end of the current construction season.

A team led by Central Bridge Co. and Bizzack Construction also has expedited work on a damaged bridge in Knott County that was already slated for replacement as part of an ongoing design-build project in eastern Kentucky.

In just more than a month since the flooding, KYTC and its partners have completed temporary crossings at 19 sites to restore vehicle access to homes that were cut off from their communities when bridges were damaged or destroyed during the flooding. Construction of temporary crossings is under way or pending at seven additional sites. These temporary crossings, called diversions, typically consist of culvert pipes overlaid with a hardpacked roadbed, allowing drivers to safely cross streams and creeks.

In addition to the rapid replacement projects, KYTC is working with design consultants to assess needs and prepare plans for more than 60 bridge projects where significant damage has been identified. Department of Highways staff and contractors are also working to repair damage to roadway approaches, retaining walls and embankments at dozens of other bridge sites.

To speed the completion of projects, KYTC has coordinated with contractors and suppliers to secure materials such as concrete and steel bridge beams, fill rock, culvert pipes and other items needed for bridge construction.

"KYTC has accessed every tool available to quickly advance these projects," said State Highway Engineer James Ballinger. "We are utilizing our state forces and existing contracts with consultants for site survey, design and construction management as well as existing and emergency contracts with contractors for construction and demolition. Each of these partners is moving deliberately and urgently, and our teams won't quit until the job is done."

The KYTC also launched an eastern Kentucky online flood debris removal schedule where residents of flood-affected areas can visit to monitor waterway and roadway debris cleanup efforts. To date, KYTC has collected 4,460 truckloads of debris from waterways and roadways. For more information on the state's debris removal process, visit governor.ky.gov/FloodResources.




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Liebherr to Exhibit at World of Concrete 2025

Pacific Coast Highway Drainage Infrastructure, Bridge Construction Proceed

Contractor Chosen for $22M Wastewater Pipeline Project


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA