Layton, Partners Pour 15 Million Lbs. of Concrete in SLC

Wed August 10, 2022 - West Edition #17
Layton Construction


Layton Construction and its partner W.E. O’Neil Construction recently completed one of the largest continuous concrete pours in Utah state history.
(Layton Construction/Twitter photo)
Layton Construction and its partner W.E. O’Neil Construction recently completed one of the largest continuous concrete pours in Utah state history. (Layton Construction/Twitter photo)
Layton Construction and its partner W.E. O’Neil Construction recently completed one of the largest continuous concrete pours in Utah state history.
(Layton Construction/Twitter photo) Approximately 4,000 cu. yds. were poured at the site of the joint-venture 31-story, high-end apartment tower in downtown Salt Lake City.
(Layton Construction/Twitter photo) Other contractors involved in the project included Geneva Rock, Burbidge Concrete Pumping and T&S/Harris Rebar.
(Geneva Rock photo) More than 415 truckloads of concrete (equivalent to covering four football fields 5-ft. deep) were delivered to the construction site.
(Layton Construction/Twitter photo)

Layton Construction recently completed one of the largest continuous concrete pours in Utah state history.

Crews from the Sandy-based contractor successfully placed 15.7 million lbs. of concrete in a 13-hour window for a 500,000-sq.-ft. residential high-rise that will feature 360 apartments, four levels of above-grade parking, retail and more.

The site of the project is located at 200 East and 300 South in Salt Lake City. Construction is expected to be complete in spring 2024.

"We hit a major milestone getting this massive pour done on time," Layton Superintendant Patrick Taylor said via Twitter. "I'm really proud of the team that worked tirelessly in the last three months to make it happen."

Approximately 4,000 cu. yds. were poured at the site of the joint-venture 31-story, high-end apartment tower in downtown Salt Lake City.

Layton partnered with W.E. O'Neil Construction to place more than 415 truckloads of concrete (equivalent to covering four football fields 5-ft. deep). Layton also partnered with Geneva Rock, Burbidge Concrete Pumping and T&S/Harris Rebar to make the feat happen.




Today's top stories

Chicago Asphalt Contractor Embraces Electric Vehicles

New or Used, Prinoth Panther T14R Redefines Productivity, Performance for Crawler Carriers

VIDEO: Feds Award Massachusetts $472.3M to Replace An Old Drawbridge Over Charles River

Fleet Management Gets Smarter … Artificially

ARTBA Honors Top Women & Firms in Transportation Construction

Excavator Work Tools Startup HB Attachments Rebrands as TRUE Attachments

Montabert Introduces Upgraded Variable-Speed Breakers

Montabert Announces Surface, Underground Drills


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA