Lemhi River Bridge Projects Under Way in East Idaho

Tue May 08, 2018 - West Edition #10
Construction Equipment Guide


ITD has identified nine bridges for reconstruction on ID-28 between April 2018 and October 2019.

Construction on the first three bridges began the week of April 2 and lasts until mid-Oct. 2018. The project calls for removing and replacing bridges; enhancing existing structures; and providing increased capacity for the river.

Bridge Locations
  • ID-28 at milepost 101.77 (11.3 mi. northwest of Leadore)
  • ID-28 at milepost 103.12 (located .16 mi. southeast of Lee Creek Road/Maier's Lane)
  • ID-28 at milepost 105.51 (2.64 mi. southeast of the Old Highway 28 Junction).
  • Traffic Impact
  • Traffic will reduce to one lane with temporary traffic signals directing traffic
  • Lanes reduced to 11-ft. openings
  • Speed reductions to 35 mph through construction zones
  • Expect delays
  • Shoulders will be closed
  • From June until November 2018, construction will take place on two additional bridges southeast of Salmon, at milepost 115.67 and 125.66.

    The remaining four bridges, located between Leadore and Salmon, will be rebuilt starting in April 2019, through October 2019.

    The construction budget for this project is approximately $13 million. Work will be done by Wadsworth Brothers Construction.




    Today's top stories

    Construction Market Boosts Economy

    Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

    VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

    'Machinery Pete' Interviews Jack Lyon On RFD TV

    Huntsville, Ala.'s Sandra Moon Community Complex to Begin Final, $31.3M Phase of Work

    Unique Skid Steer Tire Increases Snow Clearing Performance, Safety

    New Deutz Power Center Mid-Atlantic Opens in Ashland, Va.

    2025 CGA Conference & Expo Opens Registration On Nov. 6


     







    39.95234 \\ -75.16379 \\ Fort Washington \\ PA