List Your Equipment For Free  /  Seller Login

Lycoming Valley Railroad Bridge Nears Completion

The bridge was damaged beyond repair in 2011 by Tropical Storm Lee, and the project also involves the reconstruction of approximately half a mile of railroad track.

Tue July 15, 2014 - Northeast Edition
Brenda Ruggiero


A railroad bridge replacement project in Lycoming County, Pa., is nearing completion. The bridge was damaged beyond repair in 2011 by Tropical Storm Lee, and the project also involves the reconstruction of approximately half a mile of railroad track.

The bridge and track are owned by and are being rebuilt by SEDA-COG Joint Rail Authority under the direction of Jeffrey Stover, executive director. The bridge is called the Lycoming Valley Railroad Bridge No. 195.68 over Loyalsock Creek in Montoursville, Lycoming County, Pa.

The bridge reconstruction was bid in June 2013, started in July 2013, and will be finished in July 2014. The bid amount was $9.1 million, and the project is currently on schedule. The bridge was designed by John Conrad, P.E., railroad consultant, and Keller Engineers of Holidaysburg, Pa.

The new bridge is being built by Glenn O. Hawbaker Inc. of State College, Pa. Dan Hawbaker is the president, Dave Myers is the project superintendent, Mark Weaver is the steel foreman, and Scott Sechrist is the piling superintendent.

The scope of the project included the construction of a new three-span 475 ft. (145 m) long steel bridge consisting of Spans 1 and 3 being 119.5 ft. (36.4 m) long and 106 in. (269 cm) high through the girders, and Span 2 being a 237.75 ft. (72.5 m) long, 38.25 ft. (12 m) tall heavy truss.

The total amount of structural steel is 1.5 million lbs. (697,142 kg), with nearly 25 tons (23 t) of bolts in the truss alone. The bridge is supported by two new abutments and two new piers. These substructure units consisted of more than 2,300 cu. yds. (1,758 cu m) of concrete and more than 226,000 lbs. (102,512 kg) of reinforcing steel.

According to Bud Dover, senior project manager of Glenn O. Hawbaker Inc., the abutments and piers are supported by more than 13,300 linear ft. (4,054 m) of steel H-piling. Abutment 1 and both piers were built within sheet pile cofferdams requiring constant pumping to keep the water levels inside the cofferdams down to enable construction. Abutment 1 and both piers also were such massive concrete pours that internal cooling piping was run throughout the concrete to carefully monitor and maintain appropriate temperatures during the concrete curing periods.

“Challenges during the project included artesian springs coming up through the bottoms of the cofferdams, which greatly increased the amount of pumping necessary to keep the water level down during the substructure construction,” Dover said. “Also, many of the piles went down longer than anticipated, some over 120 feet, requiring many splices to the piles. Additionally, Span 1 and part of Span 2 had to be constructed under electric lines which reduced the length of crane boom to be used, even though the power was turned off.”

Major suppliers were High Steel of Lancaster and Williamsport, Pa., for structural steel; Titusville Fabricators of Franklin, Pa. for reinforcing steel; and Centre Concrete of State College and Montoursville, Pa. for concrete.

Major subcontractors are K.W. Reese Inc. of Mercersburg, Pa., for railroad construction; and Kevin Raker Construction of Sunbury, Pa., for installing the reinforcing.

Major equipment used included a Caterpillar 330 excavator, ICE I-19 and ICE 416 vibratory pile hammers, a Grove RT 600 crane and Link-Belt 218, 138, RT8065, and RTC8050 cranes.


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025









39.95234 \\ -75.16379 \\ Fort Washington \\ PA