List Your Equipment For Free  /  Seller Login

VIDEO: Mammoet Successfully Lifts Wellsburg Bridge in West Virginia

Tue July 13, 2021 - Northeast Edition
Mammoet



Taken at sunrise right before start of voyage. Jacking system on barges supporting the bridge, in Flatiron Construction’s prepared slips, where the bridge was built on the bank of the Ohio River. After sunrise the loaded barges are removed from their slips via four tug-boats and begin the voyage from the slips to the jacking location. Tug boats rotate the bridge in the middle of the river and properly orient the barges into the prepared jacking location directly south of the bridge foundation piers. The bridge span jacked up to its greatest height to clear existing bridge construction. To be moved north via the tug boats and jacked down onto the foundation piers for installation.

Mammoet and Flatiron Construction have successfully completed the main span float and lift of the Wellsburg Bridge which connects Wellsburg, W.V., and Brilliant, Ohio. History was made on the Ohio River during the Wellsburg Bridge project as floating a bridge had never been done before in West Virginia.

In addition, it is the heaviest floating bridge lift ever executed in the United States. Upon completion, the tied-arch bridge will significantly reduce travel time between the two communities, aiding in improved local commerce.

Mammoet's proposed technical solution utilized its Mega Jack system to jack-up and install the Wellsburg Bridge, weighing 8.5 million lbs. The overall length of the bridge spanned more than 830 ft., the length of more than two American football fields.

Mammoet was the chosen contractor based on its expertise and experience jacking and floating bridges.

Mammoet's Mega Jack solution provided the least disturbance for ships on the river as the work could be completed in a maximum of two days. An alternative strand jacking method would have the bridge hanging on strand jacks for at least two weeks.

Flatiron Construction opted for using Mega Jacks due to increased efficiency, reduced disturbance and a more controlled method, which offered a higher level of safety. This was the first time the Mega Jack 5200 system was used on a barge, and the first time the system of this type and capacity was used in the United States.

Mammoet mobilized eight Mega Jack 5200 towers and eight 500-ton strand jacks and installed the equipment onto four prepared barges in New Orleans and began function testing of the system. Flatiron Construction floated the barges to Wellsburg, W.V., where Mammoet then took over the load of the bridge on its Mega Jack system.

Mammoet jacked-up the bridge with a total of six jacking beam layers and its client executed the float in operation. Once positioned next to the bridge piers, Mammoet jacked up the bridge again in order for the bridge to be floated between the piers and over the bridge bearings and the approach girder.

Mammoet's tool kit consisted of a total of 18 jacking beam layers to cover all possible water levels during execution. In the end, the load was jacked up a total of 15 jacking beam layers on six towers and 16 jacking beam layers on the other two towers to account for variances in the interface beams, which were provided by others.

Next, the jack-down operation began to precisely position the bridge on its bearings and to allow the barges to be floated away. Mammoet's technical solution provided advantages, such as allowing the bridge to be built at ground level and allowing it to be safely jacked-up while loaded on the barge — bringing the bridge to the elevation required for installation. Therefore, all jacking works could be executed at a lower level and reduce working at height.

Forecasted windy weather conditions prompted a decision to expedite the schedule and complete the full float in and jacking operation in one day instead of two as originally scheduled. With safety as highest priority, Mammoet skillfully executed the scope of work ahead of schedule in one day without incident.

Mammoet used its global engineering resources and the world's largest heavy lift equipment fleet to make sure it could deliver the right expertise, in the right place, at the right time.

For more information, visit www.mammoet.com.




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA