List Your Equipment For Free  /  Seller Login

Massana Construction Lifts 11 Bridges in Five Counties

Wed April 01, 2020 - Southeast Edition #8
Irwin Rapoport – CEG Correspondent


In addition to several types of jacks, work crews utilized a Cat 303.5 mini-excavator; Cat 289 tracked skid steer; two Cat 255 telehandler forklifts; Mack and Kenworth tractors and 40-ft. dove-tailed trailers for equipment moves and mobilization, among other machines.
In addition to several types of jacks, work crews utilized a Cat 303.5 mini-excavator; Cat 289 tracked skid steer; two Cat 255 telehandler forklifts; Mack and Kenworth tractors and 40-ft. dove-tailed trailers for equipment moves and mobilization, among other machines.
In addition to several types of jacks, work crews utilized a Cat 303.5 mini-excavator; Cat 289 tracked skid steer; two Cat 255 telehandler forklifts; Mack and Kenworth tractors and 40-ft. dove-tailed trailers for equipment moves and mobilization, among other machines. Massana Construction Inc. was awarded GDOT’s contract for the $8 million rehabilitation of 11 bridges over Interstate 20 and Interstate 16 in Newton, Green, Morgan, Taliaferro and Laurens counties. Paving efforts along one of the 11 bridges rehabbed and lifted by Massana Construction. The average length of the bridges in this project is 262 ft. Each work crew was responsible for three steel beam bridges, and many of the crew members united for the raising of the concrete beam bridge. The final product of the concrete beam bridge (Almon Road over I-20).

Punch list items are all that remain on the Georgia Department of Transportation's (GDOT) $8 million rehabilitation of 11 bridges over Interstate 20 and Interstate 16, which raised the height of bridges in Newton, Green, Morgan, Taliaferro and Laurens counties.

The contract, awarded to Massana Construction Inc., had three separate crews operating on parts of the state that were 60 miles from Atlanta and about 75 miles apart from each other between the outermost bridges.

The work began in October 2018 and the last bridge was finished on February 29 of this year. Each crew was responsible for three steel beam bridges, and many of the crew members united for the raising of the concrete beam bridge.

"The focus of the project was to raise all 11 bridges to increase the clearance for trucks underneath," explained Steve Roeser, Massana's project manager. "It was primarily a bridge jacking job and there was a multitude of incidental work that needed to happen once the bridge was raised — the guardrail, approach decks, wing walls and other road work."

The average length of the bridges was 262 ft. The steel beam bridges (four spans, two abutments and three piers) had one lane in each direction, while the concrete beam bridge (Almon Road over I-20: two spans, two abutments and one pier) in Newton County had two lanes in each direction, plus a center turn lane.

Roeser was primarily dealing with three GDOT officials — Robert Rowland, the assistant area engineer, Joe Champion, the project engineer, and Charles Smith, the on-site project inspector.

"Some of the biggest challenges for this project were that the contractor had to jack each bridge simultaneously," Champion stated. "If not, they risked damaging the beams and bridge deck. Also, the contractor had to stage the construction to complete the work under traffic utilizing temporary traffic signals and lane closures. The expected lifespan of the bridge raising is for the life of the bridge or until the interstate clearance height is raised to where the new bridge heights are in conflict. Usually maintenance projects like these take about two years to go through the planning and design phase before being let for construction."

Roeser was well aware of the many challenges associated with the initiative.

"One of the biggest hurdles was that for three of the bridges, when we raised them, the engineer called for the complete removal of the concrete caps," he said. "We basically built a shoring tower around the piers, raised the bridges up, removed the caps and then poured new caps at an elevation that was approximately one foot higher."

Another issue for crewmembers was navigating traffic.

"GDOT allowed us to shut down three bridges in Morgan County for 45 days," Roeser said. "But for everything else, we had to maintain one lane of traffic. To solve that problem, we used portable traffic signals on either side of the bridge. In order to get done on schedule, we worked on three bridges at a time, and in one case, four. Each bridge took about 15 weeks to complete."

To maintain traffic on the open lanes, a variety of techniques were employed. In one case, for a dirt/gravel road, GAB (Graded Aggregate Base) was used to build a ramp; for another, the paving subcontractor paved the wedges in; and for another, as the approach slabs came up, a ramp was placed on each end.

"This all required extensive planning," said Roeser, who noted that day shifts were only needed for 10 bridges. "For the concrete bridge, it was weekends only for the top work — the approach slabs removal and replacement, asphalt paving and final striping."

The concrete bridge required maintaining one lane in each direction, during weekend work.

"The first phase of the work was the selective demolition of some of the backwalls and the second phase was raising the bridge that had 11 beams — we started at the abutment and moved to the center pier, and then the other abutment," said Roeser. "It only came up 4 in. The whole bridge was jacked at one time, being raised incrementally between 0.5 in. to 1-in. per-hour."

Once raised, crews did some concrete work — replacing some of the backwalls and wing walls. After this was done, the work shifted to weekend work.

"The approach slabs, asphalt paving, two-part epoxy overlay and final polyurea striping were done in five weekends," Roeser said. "One of the biggest challenges was jacking the center pier. There was a concrete median, so we had to put a left-hand lane closure with barrier wall in each direction on I-20 and had 14 days to get it done. Once access was secured, we had to jack each end of the beams and we had 88 jacks on the center pier. We had to assemble our shoring system to give us a place to jack from. The bearing was only was only 2.5 in., so there was no daylight and it was real tight."

One common element for all the bridges was the application of a two-part epoxy overlay. The concrete bridge was one of the last to be completed. For the others, the plan of attack was similar, starting with the installation of the temporary traffic signals, select demolition work, access to shoring to set up the jacking systems, raising the bridge and once raised, all of the top work.

"One of the important pieces of work was the installation of new steel bearings," Roeser said. "If the bridge was raised 10 in., we had to install 10-in. high bearings as well."

Each crew developed a good rhythm, which included taking nothing for granted and ensuring that safety was a priority at all times.

One crew dealt with the bridges that required the cap removal and replacement, and the other two crews dealt with the steel beam bridges that were similar in their design. Each crew had about six Massana people — a superintendent, a foreman and four workers, along with some subcontractor employees.

"For the concrete bridge, everybody pitched in and helped us get it done," Roeser said. "Not every bridge was exactly the same. One jacking system was the shoring tower system; another was corbels that we could drill into the sides of the caps, which gave us a seat to jack from; another was more of a hanging system with high strength Coil Rod; and the most straightforward system was putting a jack on the existing caps or abutments and raising it up.

"We had a field engineer, Jonathan Hopkins, on the job full-time and when we peaked out, we had 35 guys," Roeser added. "I was fortunate to have good people and good help. I could not be everywhere all the time. We had good people on each of the bridges that could look after things."

Also assisting were Massana senior superintendents Jeff Fiscus, Tom Root and Michael Terrell. "It was a good team dynamic," Roeser said.

Crews removed 200 tons of asphalt, 800 tons of concrete and 90 tons of steel and rebar. New materials consisted of 2,600 tons of asphalt, 900 cu. yds. of concrete, and 140 tons of steel and rebar. The scrap steel and rebar were sent to scrap yards for recycling and the concrete was repurposed as rip rap for erosion control.

The subcontractors were C&H Paving for asphalt, The Sharon Company for guardrail, Oglesby Construction for final polyurea striping, Tidwell Inc. for thermoplastic markings, ABC Cutting Contractors for concrete cutting and C&G Concrete for the construction of the approach slabs.

Equipment-wise, Massana used a Power Team hydraulic jacking pump system (10,000 PSI); Enerpac and Power Team 50- and 100-ton pancake jacks; four ADDCO PTS-2000 portable traffic signals; a Cat 303.5 mini-excavator; Cat 289 tracked skid steer; two Cat 255 telehandler forklifts; Mack and Kenworth tractors and 40-ft. dove-tailed trailers for equipment moves and mobilization; a GMC dump truck; various hammers; and various air-compressors.

Some work sites had on-site mechanics and other sites brought in mechanics as needed.

"The biggest wear and tear was for some of our hammers and jacking systems," Roeser said. "The trucks, which were instrumental to moving our heavy equipment, required quite a bit of maintenance to keep them moving."

Doug Shoemaker, Massana's equipment manager, played a key role in assigning equipment and keeping an eye on the repairs and maintenance issues.

"He was with us from start to finish," Roeser stated. "Shoemaker and his team helped us through everything, and he would also get out and do repairs on-site himself if necessary."

Massana purchases its Caterpillar equipment from Yancey Bros. Inc. in Atlanta, while the jacks were purchased from Beerman Precision Inc. in New Orleans, La., which has an office in Birmingham, Ala., where jacks could be repaired. When equipment had to be rented, it was provided by Herc Rentals.

"Yancey helped with repairs to some of the demolition hammers," Roeser said. "Herc had a satellite office in Covington, which was very convenient due to the lengthy distances on the project. The dealerships expect us to communicate the problems that the equipment is having and at times we brought the equipment to them so they could have a good shop environment to make the repairs, instead of having their mechanics come into the field. What we expect are good repairs and good maintenance of our equipment."  CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA