MDOT SHA Opens MD 355 Bridge Over Monocacy River Ahead of Schedule

Mon January 22, 2018 - Northeast Edition #2
Construction Equipment Guide


The MD 355 Bridge over the Monocacy River was closed after being struck Dec. 7, 2017.
(MDOT SHA photo)
The MD 355 Bridge over the Monocacy River was closed after being struck Dec. 7, 2017. (MDOT SHA photo)
The MD 355 Bridge over the Monocacy River was closed after being struck Dec. 7, 2017.
(MDOT SHA photo) Crews used steel to brace the bridge prior to repair.
(MDOT SHA photo) Crews worked to put the final touches on the repaired bridge.
(MDOT SHA photo)

After making emergency repairs during bitter cold temperatures, the Maryland Department of Transportation State Highway Administration (MDOT SHA) reopened the MD 355 (Urbana Pike) Bridge over the Monocacy River more than two weeks ahead of schedule.

The bridge opened after rush hour on Jan. 11. The bridge sustained significant damage after being struck by a truck in a crash in December and was not safe for vehicles to use. It was closed, and traffic detoured, with repairs estimated to take 60 days.

Immediately following the collision, MDOT SHA bridge engineers swiftly evaluated the stability of the structure and developed an emergency repair plan. Part of the plan included developing a bridge support system that braced and stabilized the bridge to enable crews to safely perform the work.

“This emergency bridge repair was a tremendous team effort and excellent partnership between MDOT SHA and our contractors and suppliers, who worked in bitter cold temperatures through the holiday season to complete the work,” said MDOT SHA Administrator Greg Slater. “Thanks to residents and commuters for their patience while we made the bridge safe for travel again.”

Once crews installed the stabilization system, they removed the damaged steel beams and installed specially fabricated pieces to replace damaged elements. MDOT SHA ordered materials and repurposed some from existing inventory from previous projects to use for the sister beams and jacking tower. Crews worked 12 hour days; cold weather and short daylight hours slowed progress but the work progressed with very few unanticipated problems.

Crews thoroughly tested the bridge following the emergency repair prior to opening the travel lanes to commuters.




Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA