The Maryland Transportation Authority (MDTA) began a project in the summer of 2016 to rehabilitate the Chesapeake Bay Bridge, which is officially named the “Gov. William Preston Lane Jr. Memorial Bridge” after the governor who initiated its construction.
The dual-span structure crosses the bay in Maryland and connects the Eastern and Western Shores. It is part of U.S. Routes 50 and 301, and serves as a connection between the Baltimore-Washington Metropolitan Area and Ocean City and other coastal destinations.
Project notice to proceed was given on July 11, 2016, with expected completion set for summer of 2018.
The contract award amount is $29.6 million, which is completely funded by toll revenue. The project is part of the MDTA's $273 million system preservation and safety investment at the Bay Bridge over the next six years.
Kiewit Infrastructure Company is the prime contractor, with Nick Scarpato serving as the project manager.
The project includes the installation of supplemental cables; rehabilitation of the suspension span superstructure and bearings; and priority repairs found during annual inspections.
“Maintenance of traffic on the Bay Bridge during construction is a challenge,” said John Sales, public affairs manager for the MDTA. “The current plan is to perform most of the work during off-peak hours, i.e. night time full bridge and double-lane closures and temporary daytime lane closures, throughout the duration of the project. There are multiple construction and maintenance projects ongoing at the bridge, so significant coordination is required. Daytime work will be performed using alternative access methods. Workers will take boats to platforms that are not visible from the roadway.”
Sales noted that the project involves a comprehensive suspension span rehabilitation. Multi-faceted work will enhance the durability and extend the useful life of the original suspension system and help the bridge perform optimally in all weather conditions. This is the first time this work has been done in Maryland, although it has been done in other states.
Major subcontractors on the job include Johnson, Miriam & Thompson Inc. (JMT); Parsons Transportation Group Inc.; Northeast Work & Safety Boats LLC; Wirerope Works, Williamsport, Pa., strand and rope supplier; Crystal Steel Fabricators Inc., Demar, Del., major steel supplier; and Sunrise Safety Services, Baltimore, Md., performing nightshift maintenance of traffic service
Major equipment used on the job includes a 180-ton crane for erection of main cable strands and various winch and jacking systems.
According to Sales, crews installed access platforms in various locations along and beneath the westbound Bay Bridge roadway. Installation of permanent repairs, visible from the roadway, began in December and will continue throughout 2017.
“This project will include geometry improvements to the existing structure,” Sales noted. “Though it may not be perceived by the traveling public, the work will improve the functionality of the bridge by allowing natural expansion and contraction of the bridge elements to occur with reduced friction on the existing components.”
The original bridge opened in 1952. At the time, it was the world's longest continuous over-water steel structure, with a length of 4.3 mi. (6.9 km). The parallel span was added in 1973. They are relatively similar in structure, and were both designed by J.E. Greiner Co. (which became a part of AECOM through the acquisition of URS Corporation).
They consist of a 3,200-ft. (975 m) suspension span over the western channel with a maximum clearance of 186 ft. (56.7 m), which allows for accommodation of ocean-going vessels and tall ships; and a through-truss cantilever span over the eastern channel with a maximum clearance of 58 ft. (17.7 m).
According to Wikipedia, the bridge is known as one of the scariest in the United States because of its height, the narrowness of the spans with no hard shoulders, the low guardrails, and the frequency of high winds that occur in the area.
The bridge reportedly has been closed four times because of extreme weather: Sept. 18, 2003, during Hurricane Isabel; Aug. 27, 2011, because of the impacts of Hurricane Irene; Oct. 29, 2012, because of Hurricane Sandy; and March 6, 2013, during a nor'easter.—CEG
Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.
Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.
Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.