Milani Works to Deliver I-83 Bridge By 2021

Mon March 16, 2020 - Northeast Edition #6
Brenda Ruggiero – CEG Correspondent


Milani Construction LLC crewmembers work on driving pile along Interstate 83 in Maryland.
Milani Construction LLC crewmembers work on driving pile along Interstate 83 in Maryland.
Milani Construction LLC crewmembers work on driving pile along Interstate 83 in Maryland. Local traffic is diverted around lane widening efforts as part of the Maryland Department of Transportation’s I-83 improvement project. Milani Construction’s Grove RT 540E, one of many cranes used on this project, is put to work. Another view of the I-83 work zone. This Cat 321D hydraulic excavator utilizes its hammer attachment to break down concrete during the partial demolition process of MDOT’s I-83 bridge project.

In Timonium, Md., which is located in Baltimore County, the Maryland Department of Transportation's State Highway Administration (MDOT SHA) is heading up a project to replace the 70-year-old Interstate 83 (Harrisburg Expressway) dual bridges over Padonia Road. Safety improvements also will be added to the interchange.

The $22 million construction project began in the summer of 2018. It is scheduled for completion in the fall of 2021.

The contract was awarded to Milani Construction LLC of Washington, D.C., under the direction of Ira Kaplan. Milani Construction is a general contractor serving the Baltimore-Washington metropolitan areas performing infrastructure and marine work.

MDOT SHA is replacing the bridges as part of its ongoing structure preservation program.

According to Shanteé Felix, assistant media relations manager, Office of Communications, MDOT SHA, the project includes the total replacement of both the north and south bridges; the widening of Padonia Road under the bridges to create a new dedicated left turn lane on eastbound Padonia Road for the ramp from eastbound Padonia Road to northbound I-83 towards Hunt Valley, and to create new shoulders on both sides of Padonia Road; as well as the widening of the end of the ramp from southbound I-83 to Padonia Road to improve interchange traffic operations and reduce backups on the ramp. A box culvert carrying a branch of Beaver Run underneath the interchange also will be widened.

"This project involves the total replacement of the I-83 north and south at the I-83/Padonia Road interchange," Felix said. "The bridges date to the 1950s, and while they are safe to drive on, they have reached the end of their service life."

She stated that currently this project is in phase one of construction, with the southbound and northbound lanes on I-83 shifted towards the outside of the roadway bed. The inside and outside shoulders are closed, with concrete barriers protecting the bridge work zone in the middle of I-83. This phase is scheduled for completion in the spring of 2020.

Phase two is scheduled to begin this spring.

"During this phase, southbound and northbound lanes on I-83 will be in a split traffic pattern," Felix said. "There will be two lanes to the left and one lane to the right, with concrete barriers creating a new bridge work zone in between the lanes."

All lanes will be through lanes, but drivers wishing to exit I-83 at Padonia Road must stay in the right lane. This split traffic pattern will be in effect through late fall 2020.

During construction, the left turn ramp from eastbound Padonia Road to I-83 North will be closed 24 hours a day, seven days a week until the project is completed in 2021.

"Some challenges we have faced with this project include dealing with the traffic volumes on both I-83 and Padonia Road," Felix said. "More than 100,000 vehicles travel I-83 each year and due to these heavy traffic volumes, we cannot allow daytime closures on this segment. I-83 is a key interstate commuter and commercial truck route that links Harrisburg, York and other southern Pennsylvania regions to metropolitan Baltimore, the Helen Delich Bentley Port of Maryland and BWI Thurgood Marshall Airport.

"Traffic flow is very directional, in that I-83 southbound traffic is heavy in the morning and I-83 northbound traffic is heavier in the afternoon and evening hours. Additionally, Padonia Road is a busy county connector road between north-south routes such as MD 25 [Falls Rd.], I-83 and MD 45 [York Road] linking residential, industrial and commercial corridors."

Felix noted that crews had to maintain at least one lane of traffic in each direction on Padonia Road during peak morning and evening travel hours, with temporary detours only at night. They also had to maintain at least three lanes of traffic in each direction of I-83 during peak morning and evening travel hours.

There will be occasional overnight closures of Padonia Road under the bridge during partial demolition of the old bridges and steel beam placement for the new bridges. Portable digital message signs on Padonia Road will alert travelers to upcoming road closures.

As of June 2019, the speed limit on I-83 in the vicinity of the Padonia Road interchange work zone was reduced from 60 mph to 55 mph.

According to Felix, approximately 38 people are working this project on a daily basis.

Felix reported that major equipment on the job includes a Grove, Hylab and Cat cranes; Hitachi and Cat excavators; Cat dozers; Hamm, Cat and Bomag rollers; Cat and John Deere pavers; a Gradall; and an International boom truck. CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

VIDEO: Two Major Roadway Project Contracts Awarded by State Officials in West Virginia

VIDEO: First of Two Sections of NYC's $1.45B East Side Coastal Resiliency Project Is Complete

John Deere Construction Introduces Flexible Customer Training Options

INFRA Grant Moves Ohio's N. Coast Connector Project Steps Closer


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA