List Your Equipment For Free  /  Seller Login

New System-to-System Interchange in Vegas Takes Shape

Wed May 06, 2020 - West Edition #10
Lori Tobias – CEG Correspondent


A contract was awarded to Fisher Sand & Gravel in January to build ramps, flyovers and street connections at Interstate 15 and the 215 Beltway in north Las Vegas.
A contract was awarded to Fisher Sand & Gravel in January to build ramps, flyovers and street connections at Interstate 15 and the 215 Beltway in north Las Vegas.
A contract was awarded to Fisher Sand & Gravel in January to build ramps, flyovers and street connections at Interstate 15 and the 215 Beltway in north Las Vegas.
 The project entails building two massive cast-in-place concrete dual lane flyovers, among other structures, including a 51-ft.-tall, 1,800-ft.-long east-to-north connection that will be the equivalent of five football fields.
 The interchange is expected to open in late 2022.
 A rendering of what the finished product will look like.

Workers on the $99 million I-15/215 Interchange project in north Las Vegas are seeing something of a silver lining in the pandemic that has shut down the city.

"Traffic mitigation is an issue," said Nevada DOT spokesman Tony Illia. "But right now, with COVID-19, we've seen traffic drop off substantially — up to 76 percent in some places depending on the day. It's made it a little bit easier to schedule work. The only impact are the new OSHA guidelines in terms of social distancing, keeping hands clean, congregating in groups of 10 or less and if you have to sneeze, doing so into the crook up your arm."

A rendering of what the finished product will look like.

NDOT canceled a previously scheduled groundbreaking due to the virus, but work to move gas pipelines began in late March. The contract was awarded to Fisher Sand & Gravel in January to build ramps, flyovers and street connections at Interstate 15 and the 215 Beltway in north Las Vegas.

"The new direct system-to-system interchange will greatly improve traffic, enhance safety and increase mobility," Illia said." The interchange currently averages about 34,000 vehicles daily, although future traffic counts are expected to grow by 72 percent over the next two decades."

Currently, the route from I-15 to the 215 Beltway is marked by a couple of stop signs. The new fly over will enable a direct system-to-system connection while still maintaining highway speed, which is simply a more efficient and safer traffic pattern, Illia said. "There is a large VA hospital nearby and members of Nellis Air Force Base also will use the new interchange."

The project entails building two massive cast-in-place concrete dual lane flyovers, among other structures, including a 51-ft.-tall, 1,800-ft.-long east-to-north connection that will be the equivalent of five football fields laid end-to-end, he said. The northbound I-15 to westbound 215 flyover, meanwhile, will be longer than the Eiffel Tower laid on its side. The structures sit atop a network of drilled pilings that reinforce the subsurface, with the largest measuring 10-ft. in diameter and 104-ft. in depth. Atkins is the project designer.

Equipment on site will include motor graders, wheel loaders, excavators, backhoes, haul trucks, cranes, concrete pavers and manlifts. There will be three hydraulic rough terrain cranes, including a 50-ton Link Belt, 100-ton Grove and 160-ton Grove with a 150-ft. boom. There will also be Caterpillar 349 and Volvo 700 excavators as well as Caterpillar 966 wheel loaders.

The improvements also entail new I-15 southbound on- and -off-ramps at Tropical Parkway for greater access as well as widening more than a half-mile of Beltway from four to six travel lanes. Other upgrades call for extending Tropical Parkway to Centennial Parkway, replacing Range Road as an east-west surface connection, with a new eastbound 215 Beltway off-ramp to the new Centennial Parkway and Range Road intersection.

Additionally, there will be new lighting, signage and landscaping, plus 7,815 ft. of drainage pipe. Lage Design is the landscape architect responsible for the new freeway aesthetics made up of boulders and decorative rock, accented by boldly colorful polygonal roadside sculptures that convey the characteristics of water and its impact upon shaping both the natural and built environments.

The interchange is expected to open in late 2022. CEG

Project Fast Facts

Excavation: 128,966 cu. yds.

Painting: 77,687 sq. yds.

Rock mulch: 49,675 cu. yds.

Decorative boulders: 48

Plants: 32

Decorative rock: 3,648 tons

Reinforcing steel: 7 million lbs.

Concrete pipe: 7,815 lineal ft.

Aggregate road base: 115,657 tons

Concrete paving: 2,918 lineal ft.

Asphalt paving: 74,549 tons

Concrete barrier rail: 38,877 lineal ft.


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Protecting Delaware Memorial Bridge

Widespread Catastrophic Damage From Hurricane Awaits Repair Crews in SE States

Flatiron, Dragados JV Set to Finish Major Job in Corpus Christi

JCB Celebrates 20 Years of Engine Making

Robert H. Finke & Sons Holds Open House at New Colchester, Vt. Facility

Snyder Civil Leads Way to Provide Clean Water, Safe Communities, More

Today's Security Tech Helps Contractors Combat Jobsite Theft

Komatsu Company Stores East Holds Open House in Pennsylvania


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA