List Your Equipment For Free  /  Seller Login

Nine I-95 Bridges Being Rebuilt or Repaired in Hampden, Maine

Thu November 12, 2020 - Northeast Edition
MaineDOT


An effort to rebuild and rehab a total of nine deteriorating bridges along four miles of Maine's portion of Interstate 95 currently is under way, with a completion set for late 2022.

The Hampden Bridge Bundle Project, valued at $44.7 million, consists of four northbound/southbound bridge pairs at four different sites along Interstate 95 between Exit 174 and Exit 180 in Maine's mid-south near Bangor.

The Maine Department of Transportation (MaineDOT) is rebuilding eight bridges, while rehabilitating another. Three of the bridge pairs cross Souadabscook Stream and one pair carries traffic over Emerson Mill Road and the Central Maine & Quebec Railway. The sole bridge rehabilitation occurs at the Exit 180 off-ramp on Cold Brook Road over I-95.

Cianbro Corporation of Pittsfield is the general contractor on the New England bridge replacement project.

Hampden bridges on I-95 are approximately 60 years old and are approaching the end of their useful lives, according to MaineDOT. The new spans will include non-corrosive materials to reduce future maintenance needs. The bridges over the Souadabscook Stream will be single-span structures to eliminate the need for piers in the water.

When the Hampden Bridge Bundle Project was being planned, it included the demolition and removal of all eight existing bridges and the design and construction of eight full replacement bridges using the design-build method. The Cold Brook Road Exit 180 off-ramp will consist of pier substructure rehabilitation.

In 2020, temporary diversion roadways and bridges have been constructed in the median of I-95 to maintain two travel lanes in each direction throughout much of the project. After the diversions were installed, the northbound traffic on the interstate moved to the median roadway while the northbound bridges were under construction.

Once the new northbound bridges are complete, northbound traffic will move onto the new bridges and southbound traffic will move to the median roadway while construction occurs on the southbound bridges. Following completion of the southbound structures, traffic moving in that direction will begin to travel onto those bridges, and removal of the median roadways and bridges will begin.

Median work started in February and will continue through the end of the year. Most of the northbound bridge work will be completed in 2021, and southbound bridge work will be completed in 2022.

To construct the median roadway and bridges in Hampden, there are times that interstate travel lanes are reduced to one lane either northbound, southbound or both. MaineDOT and the contractor are monitoring traffic daily to best adjust the days and times for the lane closures and prevent delays.

By keeping two lanes operating at all possible times, MaineDOT said traffic impacts have so far been minimal and it expects it to remain so throughout the duration of the project.

Traffic will flow freely on all the new bridges in November 2022.




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA