NTSB Confirms Cracks May Have Contributed to Deadly FIU Bridge Collapse

Thu May 24, 2018 - National Edition
Associated Press


The NTSB released a preliminary report looking into the collapse of a pedestrian bridge in Florida that suggested investigators are focused on cracks in the south and north ends of the pedestrian bridge.
(Miami Herald/Tribune photo)
The NTSB released a preliminary report looking into the collapse of a pedestrian bridge in Florida that suggested investigators are focused on cracks in the south and north ends of the pedestrian bridge. (Miami Herald/Tribune photo)

Federal investigators looking into the collapse of a pedestrian bridge in Florida that killed six people earlier this year confirmed May 23, 2018, that they are focusing in part on the emergence of cracks in the structure before the accident.

The National Transportation Safety Board (NTSB) released a preliminary report light on details but that suggested investigators are focused on cracks in the south and north ends of the bridge near a Miami-area university campus.

The cracks were discovered in the days before the March 15 collapse, which killed a bridge worker and five people in vehicles crushed by the falling structure.

Photographs released by NTSB noted three cracks in the north end of the span, where crews were working on tensioning a structural component of the crossing when the failure occurred. A crew was on the bridge working on the diagonal beam at the time.

When completed, the bridge was to span a busy highway and canal and connect Florida International University's campus to the neighboring community of Sweetwater.

The bridge was highlighted by FIU officials as an achievement for an accelerated construction method that was supposed to reduce risks to workers and pedestrians and minimize traffic disruption.

When the bridge fell, construction was behind schedule and millions over budget, in part because of a key change in the design and placement of one of the span's supports, public documents showed.

The NTSB's preliminary report did not reveal a probable cause in the accident, and the agency said it is still examining several bridge structural components and testing various other pieces.




Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA