List Your Equipment For Free  /  Seller Login

ODOT's I-77 Bridge Replacement Project Tackles Obstacles, Progresses

Tue July 24, 2018 - Northeast Edition #15
Irwin Rapoport – CEG Correspondent


The widening and reconstruction of the I-77 bridge is part of ODOT’s Cleveland Innerbelt Modernization Plan.
The widening and reconstruction of the I-77 bridge is part of ODOT’s Cleveland Innerbelt Modernization Plan.
The widening and reconstruction of the I-77 bridge is part of ODOT’s Cleveland Innerbelt Modernization Plan. The work will see the current I-77 bridge (one southbound and one northbound 420-ft.-long structures, two lanes in each direction) demolished and replaced with a 510-ft.-long bridge that has three lanes in each direction. Equipment being used for the project includes: Link-Belt 218 and 138 crawler cranes for pile driving; an I-19 pile hammer; Cat 336 excavators, one of which is equipped with a Movax SP100 steel pile installer; a Komatsu PC228 excavator; a Cat D6 dozer; and a Volvo L120 loader.

As part of the Cleveland Urban Core Projects, the Ohio Department of Transportation (ODOT) has what it calls the Cleveland Innerbelt Modernization Plan. One of the initiatives in the work is the widening and reconstruction of the I-77 bridge over I-490 and the improvement of I-77 south of I-490 — a $25.6 million contract that was awarded to The Ruhlin Company.

The ongoing I-77 work has not been easy, but the Ruhlin project team and crews are tackling any obstacles that come their way.

The work will see the current I-77 bridge (one southbound and one northbound 420-ft.-long structures, two lanes in each direction) demolished and replaced with a 510-ft.-long bridge that has three lanes in each direction.

The other road work includes 700 ft. of approach roads on either side of the new bridge, along with ramp roadway replacement and improvements.

The work started last October and is expected be completed in October or late fall of 2019. This project is being financed by state and federal funding.

“This piece of the Innerbelt Modernization Plan will improve safety and add capacity on I-77 into and out of downtown Cleveland,” said Amanda McFarland, ODOT's District 12 public information officer. “The planning began in 1997, however the work was put on hold as it was the alternate route for the Innerbelt Bridge reconstruction work. The area was a pinch point for north and southbound traffic prior to construction. Congestion-related crashes along this corridor will hopefully be solved by this project.”

The old bridge was built in 1964 and carries 71,400 cars and trucks daily. The new bridge was designed by Richland Engineering Limited.

“The bridge deck was reaching the end of its useful life,” said McFarland, “and would have been scheduled for replacement had this project not been in the works. The lifespan for the new bridge is 75 plus years. All new roads and bridges are built to current design standards and can carry heavy loads.”

The I-77/I-490 interchange has four levels — level one (lowest level) is I-490 (six lanes of traffic), levels two and three are system interchange ramps and level four (top) is I-77. The existing vertical clearances between all these levels are substandard.

“We had to ensure the new bridge had sufficient vertical clearance to accommodate replacement of the ramp bridges at their proper vertical clearance,” said James Calanni, an ODOT transportation engineer. “So instead of increasing the vertical clearance by 1.5 feet over the level 3 ramp, we increased the vertical clearance by 6.15 feet. This resulted in the profile of I-77 being raised significantly, but the profile couldn't be raised too much because we had to meet the profile of the Kingsbury Run bridge to the north and get under the proposed Broadway Avenue bridge to the south (and maintain proper vertical clearance).

“We had to design girders that were much shallower than the existing ones,” he added. “To do this, hybrid girders were used. Hybrid girders use stronger steel for the flanges than the steel used for the web. However, shallower girders typically mean larger deflections, so the designer had to adjust girder size and spacing to meet the design requirements for strength and deflection, in addition to ensuring they did not raise the I-77 profile too much.”

Calanni noted that while the hybrid girders are not a new concept, they are not used too often because most highway bridges do not have the girder depth and clearance challenges that ODOT faced with this bridge.

“Also, metalizing is not a new concept, but it is not used too frequently because of cost,” he said. “In our case it was more cost effective to metalize the girders in the shop than to field paint the girders or shop paint and then field touch-up the paint. Metallizing is very durable, so it requires a lot less field touch-up than paint does.”

The work has impacted traffic year-round as the work proceeded over the winter; Ruhlin crews temporarily closed some lanes on I-77, as well as ramps at the I-77/I-490 interchange, in order to accommodate demolition operations during the winter months.

“Through fall 2019, all lanes of I-77 north and southbound over I-490 will be shifted in order to accommodate bridge demolition and construction operations,” stated the project web page. “In addition, the Orange Avenue entrance ramp to I-77 southbound is reduced to one lane in order to accommodate bridge demolition and construction operations through fall 2019.”

Thus far Ruhlin has completed partial demolition of the outside parapets and girders from the existing bridge and begun the outside approach roadway work. Piling and substructure construction is complete for the Phase 1 portion of the project and steel erection is underway for the superstructure.

“We removed approximately nine feet off the outside of the existing bridges — one girder line, and then we'll widen out the new bridge,” said Mark Myers, Ruhlin's project manager. “The big challenge is working around the traffic, and the next phase will have us boxed inside the active lanes. All access to the work site will have to come from a lane closure off I-77.”

“Most of the activities for demolition and erection require closures of the ramps, and often the closure of I-490,” said Myers, “and there are limited closure periods that must be coordinated with special events such as Cavs' and Indians' games. We also must coordinate operations with an adjacent ODOT project that is underway at the same time — the Broadway Bridge.”

Jackie Guttman, Myers' assistant superintendent, handles a lot of the detailed coordination considerations to schedule the work. The team also includes: Greg Eichler, project superintendent; Dustin Shifferly, general labor foreman; Mike Moser, carpenter foreman; Chris Baumhoer, chief project engineer; Scott Cooper, structural steel superintendent; Jerry Sloan, pile driver foreman; and Steve Revay, iron worker foreman.

Other challenges include the tight workspace.

“The areas to put equipment in are extremely tight,” said Myers, “and we're having to do a lot of temporary excavation support in and around the existing structure to allow for the construction of the new substructure. It is a challenging environment with tight constraints.”

An on-site construction office was set up nearby to help manage the day and night work that is ongoing.

“We have multiple shifts based on permissible lane closures,” said Myers. “We try to do most of the work, production and substructure work during the day, but a lot of the demolition and steel erection have to happen at night. ODOT is very understanding of the challenges, and they have a good project team and we're working together to mitigate the delays. They have a prescribed maintenance of traffic plan, and they have over a dozen portable message boards throughout the interchange system of Cleveland providing advance warning to motorists.”

Another unforeseen challenge has been the soil conditions which affect pile driving.

“It has created a delay which might push the project out an additional month,” said Myers. “We're working with ODOT, which is selectively directing us to accelerate by working some overtime in an effort to recover the schedule.

“There are areas where the piling had to be driven deeper than anticipated, which required additional set-up periods or wait time to allow the piling to gain the required capacity,” he added. “We're driving 16-inch diameter cast-in-place pipe piles. Some had to go down 90 feet and when we reached that depth, we didn't have the prescribed bearing and we had to drive them down another 40 feet. After this we still didn't have the capacity. So we had to give it additional set up/wait time. These are all friction pilings and rock was not shown anywhere on the borings.

“With these soft soils in the Cleveland area,” he added, “often you need to give the pilings seven to 10 days to gain capacity. Re-strike tests verify the capacity. If you wait it out, the piles will typically gain capacity. But we need to prove it before we can move on and pour the concrete footer on top of the piling. This happened on numerous foundation locations and has impacted the schedule.”

The steel girder erection, with the challenge posed by the ramp bridges below the new bridge, require the use of large hydraulic cranes to do the demolition and removal of the existing steel beams.

“We've done difficult projects like this in the past,” said Myers, “and we'll get past the challenges on this one.”

Ruhlin had time to plan the project schedule between the time of the bid phase and start of the construction.

“We continue to develop plans as we go,” said Myers. “Baumhoer and Guttman help with a lot of the heavy engineering planning for the supportive excavation, demolition and erection. All the engineering work is done in-house and we have the plans reviewed by an outside engineering firm for a second check.”

There are currently about 30 construction workers, along with five plus support staff on site. The major subcontractors are: Armstrong Steel for reinforcing steel; Karvo for asphalt; Miller Cable for highway lighting; RAR Contracting for concrete delivery; Follow the River for SWPPP inspection and erosion controls; A&A Safety for maintenance of traffic and striping; M.P. Dory for traffic signs and sign supports; and Lake Erie Construction for guard rail. Stupp Bridge fabricated the new steel girders, and they were metalized and delivered to site by Ohio Structures.

Materials removed from the site should total 1,500 tons of steel and 2,000 tons of concrete. New materials should include 3,000 tons of steel; 7,000 cu. yd. of concrete; and 16,000 cu. yd. of asphalt.

The work site is close to Ruhlin's shop and mechanics are sent in as needed to deal with typical wear and tear issues.

The crews are using Link-Belt 218 and 138 crawler cranes for pile driving; an I-19 pile hammer; Cat 336 excavators, one of which is equipped with a Movax SP100 steel pile installer; a Komatsu PC228 excavator; a Cat D6 dozer; and a Volvo L120 loader.

“We'll be renting large hydraulic cranes for the steel erections and demolitions,” said Myers, “including a Liebbherr LPM 1400 crane to erect the center drop-in girders for the bridge.”

The cranes will be rented from Maxim Crane Works.

Ruhlin purchases its Cat equipment from Ohio Cat and piling equipment from HMC.

Other projects in the Urban Core program include the Opportunity Corridor and Lakefront West initiatives.

CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA