Officials Review Port of Alaska

Wed May 08, 2019 - West Edition #10
Associated Press


The cost estimates of a scaled-back port project have increased to nearly $2 billion. The project was expected to cost $350 million a decade ago.
(Port of Alaska photo)
The cost estimates of a scaled-back port project have increased to nearly $2 billion. The project was expected to cost $350 million a decade ago. (Port of Alaska photo)

ANCHORAGE, Alaska (AP) Anchorage officials have hired consultants to help determine the best path forward for the stalled modernization project of the Port of Alaska.

The Alaska Journal of Commerce reports the Anchorage Assembly's Enterprise and Utility Oversight Committee approved a $45,000 contract last week for the project management firm Ascent PGM and the consulting firm Northern Compass Group.

The Northern Compass Group is led by former U.S. Sen. Mark Begich.

The assembly approved funding in March for consulting work to review aspects of the port expansion project, including figuring out why costs have skyrocketed.

The cost estimates of a scaled-back port project have increased to nearly $2 billion. The project was expected to cost $350 million a decade ago.

Begich said the consultants expect to produce a report by mid-September.




Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

VIDEO: First of Two Sections of NYC's $1.45B East Side Coastal Resiliency Project Is Complete

John Deere Construction Introduces Flexible Customer Training Options

INFRA Grant Moves Ohio's N. Coast Connector Project Steps Closer

Ohio Gov. Announces Millions for Local Bridge Improvements


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA