List Your Equipment For Free  /  Seller Login

Old River Road Overpass On I-16 Nears Its Finish

Thu June 10, 2021 - Southeast Edition #12
Irwin Rapoport – CEG Correspondent


McLendon Enterprises Inc. is the general contractor tasked with replacing a two-lane, 215-ft. long concrete overpass, built in 1960, with a 186-ft., five-lane bridge that spans four mainline lanes of I-16.
McLendon Enterprises Inc. is the general contractor tasked with replacing a two-lane, 215-ft. long concrete overpass, built in 1960, with a 186-ft., five-lane bridge that spans four mainline lanes of I-16.
McLendon Enterprises Inc. is the general contractor tasked with replacing a two-lane, 215-ft. long concrete overpass, built in 1960, with a 186-ft., five-lane bridge that spans four mainline lanes of I-16. For the bridge construction, 3,320 linear ft.  of 16-in. piling, 1,835 linear ft. of concrete beams, 784 cu. yds. poured concrete and 147,000 lbs. of steel reinforcement will be brought in. For the roadway work, crews will be using 4,500 tons of asphalt, 13,000 tons of GABC base, 4,430 ft. of curb and gutter, 2,200 sq. yds. of concrete median, 1,600 ft. of storm drain pipe, and 26,000 sq. ft. of MSE wall. The work also includes widening Old River Road in each direction from the new overpass to two lanes in each direction. The old bridge was demolished between Oct. 26 to  Nov. 20, 2020.
 To date, McLendon Enterprises has completed the Stage 1 bridge construction, MSE walls 1 through 4 and Stage 1 roadway including new storm drainage systems. The project, which started in December of 2018 and should be completed in 2021, is being undertaken to handle increased traffic flow due economic expansion in the area. Equipment utilized by McLendon crews include: a Cat D6N dozer, a Cat 326F excavator, a Cat 345DLQ excavator, a John Deere 544k loader; a Komatsu 270 loader, a HAMM H5l roller, a BOMAG roller, a Cat 140M motor grader and a Power Curber PC57C02. The completed Stage 2 bridge work includes the piles, columns and caps, beams and bridge deck. The remaining items consist of Stage 2 bridge approaches, traffic barrier over the bridge and the median. The remaining Stage 2 roadway work consists of GABC base, curb and gutter, median and asphalt paving.

McLendon Enterprises Inc. is a few months away from completing the Georgia Department of Transportation's (GDOT) $8,575,000 Old River Road Overpass at Interstate 16 project in Bloomingdale, Effingham County.

The initiative is replacing a two-lane, 215-ft. long concrete overpass (built in 1960) with a 186-ft., five-lane bridge that spans four mainline lanes of I-16 and intro/exit ramps on each side of the diamond interchange. The new structure has two lanes in each direction and a turn lane in the middle with a 4-ft. raised median.

The work also includes widening ¼ mi. of Old River Road in each direction from the new overpass to two lanes in each direction.

According to reports, "advancing the widening and other upgrades at I-16/Old River Road will improve safety for car and truck traffic and will also enhance the attractiveness of the area to new commercial opportunities."

The project, which started in December of 2018 and should be completed in 2021, is being undertaken to handle increased traffic flow due economic expansion in the area — the construction of warehouses and commercial buildings — based on the phenomenal growth of the Port of Savannah, which is experiencing increased volumes of goods passing through it. The port is expanding in size and constructing new facilities will be able to handle the growing number of ships utilizing its facilities.

The overpass — 20 mi. from the port — carried a fair amount of commuter and truck traffic prior to the reconstruction.

Moreland Antobelli, purchased by Atlas, designed the new overpass and road work.

The old bridge was demolished between Oct. 26 to Nov. 20, 2020.

"During the demo of the existing bridge, boards were mounted underneath the deck to keep small pieces of debris from falling to ground," said Matthew Betsill, McLendon's project manager." Crews used concrete floor saws to cut the deck into sections that could be lifted out with a crane. We utilized daytime lane closures on I-16 to work our way across the bridge one lane at a time. After the deck was removed, we performed traffic paces at night on I-16 to remove the existing steel beams.

"Police officers slowed traffic of I-16 enough to allow for about a 10 to 15 minute gap," he added. "Crews used that gap to lift each beam out of the way. With the beams off the existing columns, they could be taken down with jack hammers attachments mounted to an excavator. All of the debris was loaded onto trucks and hauled off-site."

The traffic management plan is based on lane closures as the work proceeds. During the overpass reconstruction, one lane was demolished while traffic flowed on the other side. Lanes were also closed for the work on the roads and ramps.

To date, McLendon Enterprises has completed the Stage 1 bridge construction, MSE walls 1 through 4 and Stage 1 roadway including new storm drainage systems. The completed Stage 2 bridge work includes the piles, columns and caps, beams and bridge deck. The remaining items consist of Stage 2 bridge approaches, traffic barrier over the bridge and the median. The remaining Stage 2 roadway work consists of GABC base, curb and gutter, median and asphalt paving.

"Utility conflicts were addressed with the GDOT utility relocation plan," said Betsill. "Georgia Power relocated an overhead line crossing I-16 parallel to Old River Road. This project was almost entirely a day shift project, with night work reserved for setting and removing beams over I-16. I would describe the relationship with GDOT as ‘active'. We work together to complete this project. We are in constant communication about the needs of the project and any questions each of us have."

The eastbound and westbound sides of the bridge were demolished within the same timeframe.

"We didn't close I-16 to traffic," said Betsill. "We used nighttime traffic paces to slow traffic to remove each beam — four paces each night for two consecutive nights on Nov 9 and Nov 10 [2020]."

Remediation Resources Inc., of Pembroke Ga., performed the demolition of the existing bridge using floor saws, an excavator and a crane.

"The bridge was removed piece by piece," said Betsill. "After the demo, the pieces were loaded onto trucks and removed from the site."

Southeastern Site Development Inc., of Newnan, Ga., is the bridge contractor. Crews utilized three cranes in the bridge construction, as well as excavators, front-end loaders and Genie boom lifts.

The road construction is ongoing.

"Southeastern Site is finishing the Stage 2 bridge construction," said Betsill. "When completed, McLendon will build and pave the road to tie into the new bridge. We will then shift traffic to Stage 3 which will divide traffic into two lanes over then new bridge. We will complete the median throughout the whole project. Lastly, finishing up the project with the final 1.5-inch layer of asphalt, new striping and signage. "

Peak days has about 20 McLendon and subcontractor employees on site. The subcontractors include Southeast Site Development for bridge construction; Tricor Construction for MSE wall construction; Remediation Resources Inc. for bridge demo; Middle Georgia Signs for signage; and Guardrail, Moses Grass Co. for permanent grassing.

KRM South is supplying 600 cu. yds. of concrete for the project.

The totals for the materials garnered from the demolition and excavation activities have not been finalized yet.

"The earthen materials generated on site are reused as general fill under slopes on the approach to the bridge," said Betsill. "Milled asphalt is taken back to our asphalt plant to be reused in asphalt production. Demolished concrete is taken to a rock yard to be crushed and reused as base material. Bridge beams are reused by GDOT or the bridge contractor as pile templates."

For the roadway work, crews will be using 4,500 tons of asphalt, 13,000 tons of GABC base, 4,430 ft. of curb and gutter, 2,200 sq. yds. of concrete median, 1,600 ft. of storm drain pipe and 26,000 sq. ft. of MSE wall. For the bridge construction, 3,320 linear ft. of 16-in. piling, 1,835 linear ft. of concrete beams, 784 cu. yds. poured concrete and 147,000 lbs. of steel reinforcement will be brought in.

McLendon is using a Cat D6N dozer, a Cat 326F excavator, a Cat 345DLQ excavator, a John Deere 544k loader; a Komatsu 270 loader, a HAMM H5l roller, a BOMAG roller, a Cat 140M motor grader and a Power Curber PC57C02.

"We have several full-time mechanics that maintain and repair our equipment as needed," said Betsill. "We use several rental companies around the Vidalia area when specific equipment is needed."

On this project, McLendon has secured equipment form Yancey Rents, United Rentals, and Badger Rentals. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

VIDEO: Two Major Roadway Project Contracts Awarded by State Officials in West Virginia

VIDEO: First of Two Sections of NYC's $1.45B East Side Coastal Resiliency Project Is Complete

John Deere Construction Introduces Flexible Customer Training Options

INFRA Grant Moves Ohio's N. Coast Connector Project Steps Closer


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA