List Your Equipment For Free  /  Seller Login

Phase 2 of Route 146/West Main Street Interchange Project Now Under Way

Thu April 26, 2018 - Northeast Edition #9
Andrea Watts - CEG Correspondent


To maintain four lanes of traffic during the entire construction project, traffic was first shifted onto the southbound span while the northbound span was demolished and constructed. Subsequently, the southbound traffic was shifted onto the new northbound bridge as the southbound bridge span is being constructed.
(MassDOT photo)
To maintain four lanes of traffic during the entire construction project, traffic was first shifted onto the southbound span while the northbound span was demolished and constructed. Subsequently, the southbound traffic was shifted onto the new northbound bridge as the southbound bridge span is being constructed. (MassDOT photo)
To maintain four lanes of traffic during the entire construction project, traffic was first shifted onto the southbound span while the northbound span was demolished and constructed. Subsequently, the southbound traffic was shifted onto the new northbound bridge as the southbound bridge span is being constructed.
(MassDOT photo) Currently, the Route 146/West Main Street Interchange project is on schedule for a spring 2020 completion date.
(MassDOT photo) J. H. Lynch & Sons Inc., a firm that has worked on other MassDOT projects, was awarded the $20.4 million five-year construction contract to construct the Route 146/West Main Street Interchange project.
(MassDOT photo) In the Route 146 Transportation Study published in December 2005, the Route 146/West Main Street interchange was identified as needing to be improved due to its 1950s’ design that couldn’t accommodate the increased traffic flows.
(MassDOT photo) At the southbound off-ramp intersection of Elmwood Street and West Main Street, a new roundabout replaced the previously signaled intersection and traffic has already noticeably improved.
(MassDOT photo) Construction of the northbound span of the bridge carrying Route 146 took all of 2017, and construction of the southbound span is on schedule for completion at the end of 2018.
(MassDOT photo)

The construction of the replacement bridge that carries Route 146 over the city of Millbury's West Main Street may be the most visible component of MassDOT's Route 146/West Main Street Interchange project, but it's not the only improvement within the project area. In fall 2017, the installation of two roundabouts — one at the southbound off ramp intersection of Elmwood Street and West Main Street and a mini-roundabout at the northbound onramp intersection of Elm Street and Elm Court — resulted in noticeable improvements in traffic flow, particularly for southbound travelers exiting Route 146 onto West Main Street. Prior to the installation of the roundabout, traffic would back up onto Route 146, “creating a very undesirable and unsafe condition,” according to Barry Lorion, acting District 3 Highway director.

The reason for this unsafe condition was a result of the 1950s' interchange design that could no longer handle the increased volume of traffic traveling through the area. In 2011, MassDOT calculated the average volume of traffic on Route 146 at 45,500 vehicles, and 14,500 vehicles traveled along West Main Street and Elm Street. In the Route 146 Transportation Study, prepared by the Executive Office of Transportation and Office of Transportation Planning and published in December 2005, this intersection at Route 146's exit 8 was one of five identified as needing to be improved.

When it came time to design the project, a new six-lane, single-span bridge was proposed since the current four-lane, three-span bridge lacked acceleration and de-acceleration lanes, essentially making it “functionally obsolete,” Lorion explained. To improve safety and traffic flow through the onramp and offramp intersections, roundabouts were identified as achieving the project goals, because “these modern roundabouts have more vehicle capacity than the previous intersections and also reduce crashes,” he said.

With a bid amount of just over $20.4 million, the five-year construction contract was awarded to J.H. Lynch & Sons Inc., a firm that has worked on other MassDOT projects. After receiving notice to proceed on September 2015, crews started the first phase of the project, which was the utility relocation.

“We took all the existing overhead utility lines and put them underground in order to construct the bridge,” Lorion said.

A three-phase approach was taken to construct the new bridge. For the first phase, the northbound traffic shifted onto the southbound span so the northbound span could be demolished. When constructing the bridge, Lorion said that because the bridge profile was modified, the contractor had to install an earth support system.

“The earth support system that the contractors designed was a wire mesh retaining wall that's going to be buried into place [once phase 3 is completed],” he explained. “That's been beneficial to the contractor.”

Construction of the two-lane northbound span, along with its exit and onramp, was completed at the end of 2017.

Steve Shamoian, a resident engineer with MassDOT, said that they are now on phase 2 and the demolition of the southbound span was finished in February. It's expected the construction of the southbound span and its exit and on-ramp will be completed at the end of 2018. Phase 3, which is expected to take all of 2019, will consist of constructing the median and subsequently configuring the roadway to include the new acceleration and deacceleration lanes. The final paving and lane marking will occur in spring 2020.

In regards to the bridge demolition, Shamoian said “we haven't had any issues.”

To date 750 cu. yd. of concrete have been removed from the site, while 1,025 cu. yd. and 145,000 lbs. of rebar have been used to construct the new bridge.

To maintain the four lanes of traffic at all times, the northbound lanes were shifted onto the median on the southbound side of the bridge, and the southbound lanes were shifted over into the breakdown lane. Although the majority of the work is being completed during the day, the on-ramps and off-ramps have been closed at night.

Also installed during the summer and fall of 2017 were the two roundabouts at the Route 146 southbound off-ramp at West Main Street and the intersection of Elm Street and Elm Court.

“Even though the roundabouts are in a temporary configuration, we've seen an immediate improvement at both locations,” Shamoian said.

Although these roundabouts are a change from the previous traffic pattern, drivers are adapting, Lorion said, adding that “we no longer see the backups that we had prior to installing the roundabouts, so the traffic is moving much easier through the intersection.”

The final curbing and sidewalks will be completed in fall 2019. In addition to improving traffic flow, the roundabout design also improves the access of pedestrian and bicyclist through the intersections. Lorion said that they are still on schedule for a spring 2020 completion date.

As with all MassDOT projects, Lorion said that they've worked closely with the city of Millbury to develop the project and even agreed to the city's request of painting the bridge a different color so it's officially part of the community. “The bridge will be painted Millbury maroon,” he said, “which is the town's color and that is a little bit different than our standard bridge colors.”

CEG




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA