List Your Equipment For Free  /  Seller Login

Portion of Interstate 20/59 to Accommodate 160,000 Vehicles

A portion of Interstate 20/59 in Alabama is being reconstructed to accommodate an increased flow of traffic, which currently is the highest rate of traffic flow in the entire state.

Thu March 31, 2016 - Southeast Edition
Brenda Ruggiero


A portion of Interstate 20/59 in Alabama is being reconstructed to accommodate an increased flow of traffic, which currently is the highest rate of traffic flow in the entire state.
A portion of Interstate 20/59 in Alabama is being reconstructed to accommodate an increased flow of traffic, which currently is the highest rate of traffic flow in the entire state.

A portion of Interstate 20/59 in Alabama is being reconstructed to accommodate an increased flow of traffic, which currently is the highest rate of traffic flow in the entire state. More than 160,000 vehicles travel this area each day. This number is projected to increase to more than 225,000 daily motorists by 2035. Under the current conditions, the Alabama Department of Transportation (ALDOT) reported that the existing bridge design is unable to safely accommodate traffic flow. The bridges were originally built with a 50-year lifespan, and designed to carry up to 80,000 vehicles per day.

John Cooper, director of ALDOT, announced the start of construction on the project through downtown Birmingham's Central Business District on July 29, 2015.

ALDOT's construction plan has three phases, at a total cost of more than $400 million. Throughout the early phases, access to and from downtown remained uninterrupted. ALDOT completed all work on the new ramps leading into and out of the city before closing off any existing access points.

The contract for Phase One was awarded to Brasfield & Gorrie for $7.4 million. It involves widening roadways and elevating certain bridges in preparation for the larger project.

ALDOT began working with local elected officials, the Birmingham community, business leaders and others in 2011 to develop a comprehensive plan to improve the route interchanges and replace the bridges on I-59/20. The approved plan will reportedly simplify access into and out of downtown, and ease the flow of commerce and traffic through Birmingham's Central Business District. Community input was sought throughout the planning and design process.

The contract for Phase One was awarded to Brasfield & Gorrie LLC for $7.4 million on July 22, 2015. It involves widening roadways and elevating certain bridges in preparation for the larger project. Work began on Aug. 26, 2015 and the estimated completion date is May 12.

The project covers .4 mi. (.6 km), and includes bridge widening and approaches (grade, drain, base, pave, bridge raising and highway lighting).

According to ALDOT, the most challenging part of this portion of the project has been managing traffic.

To date, this phase of the project has included 5,000 cu. yds. (3,822 cu m) of unspecified excavation, 275 cu. yds. (210 cu m) of Cl. B concrete, and 162 (123 cu m) of Cl. DS concrete.

Russo Corporation was subcontracted for drill shafts.

At the start of this project, Brasfield Gorrie submitted a value engineering proposal to change from steel piling to drill shafts, which was approved at a cost savings to this project.

Phase Two involves redesigning and constructing the new interchange ramps at I-65. There will be new ramps to 17th Street and 6th Avenue North, as well as new ramps from 11th Avenue North to the Interstate System. The project also involves construction between Arkadelphia Road and I-65 along I-59/20.

ALDOT issued a notice to proceed for this phase to Granite Construction of Watsonville, Calif., on March 15 for a contract of more than $208 million.

Throughout construction of Phase Two, access to and from downtown will reportedly remain open. Granite will complete all work on the new I-65 ramps leading into and out of the city before access points are closed for Phase Three.

“Over the past 40 years, as traffic has skyrocketed through the city of Birmingham, the junction of I-65 with I-59/20 has become labeled as Malfunction Junction,” said DeJarvis Leonard, east central region engineer. “Phase Two is designed to address this problem. Regardless of what happens with the long-term prospects of the central business district bridges, this work is necessary and will provide significant improvements for motorists traveling along this Interstate — the busiest stretch of roadway in Alabama.”

Work on Phase One — the widening of three bridges and elevating two others along I-65 — is nearing completion. This phase was necessary in order to avoid major traffic issues during construction of the later phases, and a precursor for the work that will be completed in Phase Two.

Phase I was expected to last 130 working days from the time construction began. Phase II will last approximately 30 months and Phase III, which will go out for bid by mid-2016, is projected to take approximately 12 to 14 months from start of construction. Work on Phase III will begin only after the new ramps leading into and out of downtown have been completed as part of Phase II.

ALDOT will use a segmental bridge design for the new bridges downtown. This design will allow for faster construction time, and cut down on the noise and vibrations associated with the traffic flow once completed.

This project is being paid for through a combination of funds from ALDOT, the Federal Highway Administration, and the Birmingham Metropolitan Planning Organization.

Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA